HomeMy WebLinkAboutResolution_Prospectus_Bridge Rail ImprovementsKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: February 1, 2022
ACTION REQUESTED: Request to Approve a Resolution Authorizing the
Chair’s signature on the Local Agency Federal Aid
Project Prospectus for Bridge Rail Improvements
Phase 1, CRP 314-21
BACKGROUND: Kittitas County has been selected to receive
$664,000 from the Highway Safety Improvement
Program (HSIP) for Bridge Rail Improvements,
Phase 1, in Kittitas County Road Maintenance
Districts A-F. This project will install bridge rail,
approaches, and terminals on bridges with wooden
non-standard bridge rail and/or no existing bridge
rail at locations. This project is the first phase to
address this type of non-standard rail. HSIP funding
is through the Washington State Department of
Transportation (WSDOT) Local Programs Office
and requires approval for each phase of the project.
This Project Prospectus covers the Federal Funding
for the preliminary engineering phase which is
estimated at $63,000.00.
Public Works is preparing to begin this work with
County staff upon obligation of funds.
INTERACTION: Public Works
RECOMMENDATION: Approve the Resolution Authorizing the Chair’s
signature on the Local Agency Federal Aid Project
Prospectus for the Bridge Rail Improvements Phase
1, CRP 314-21.
HANDLING: Return two (2) original to Public Works
ATTACHMENTS: Resolution
LEAD STAFF: Joshua Fredrickson, County Engineer
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2022 -
AUTHORIZING THE CHAIR’S SIGNATURE ON THE LOCAL AGENCY FEDERAL
AID PROJECT PROSPECTUS FOR THE BRIDGE RAIL IMPROVEMENTS PHASE 1,
CRP 314-21.
WHEREAS: Public Works has received federal safety funding for Bridge Rail Improvements
Phase 1 at various locations within Maintenance Districts A – F; and
WHEREAS: The federal funding will be used for the preliminary engineering phase to design,
develop and prepare construction plans and specifications for these
improvements; and
WHEREAS: In preparation to begin work in the Spring of 2022 Kittitas County Public Works
is requesting the Washington State Department of Transportation release the
federal funds for preliminary engineering; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the Chair
acknowledging the project has been reviewed and is consistent with the County’s
comprehensive plan for community development; and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best
interest of the public, does hereby approve the Chair’s signature on the Local
Agency Federal Aid Project Prospectus for Bridge Rail Improvements Phase 1,
CRP 314-21.
DATED on this 1st day of February 2022, at Ellensburg, Washington.
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
__________________________
Laura Osiadacz, Chairman
Attest:
☐ Clerk of the Board- Julie Kjorsvik __________________________
Cory Wright, Vice-Chairman
☐ Deputy Clerk of the Board- Mandy Buchholz ___________________________
Brett Wachsmith, Commissioner
______________________________
Adift
Washington State
Department of 7Yanss(parr4ation
Prefix
Federal Aid HSIP
Project Number
Local Agency CRP 314-21/ RC2199
Project Number
Local Agency Federal Aid
Project Prospectus
Route ( ) Date
DUNS Number 01-020-2547
Agency
CAAgency
Kittitas County Public Works
Yes ❑ No
Project Title
Bridge Rail Improvements: Code 3 -Phase 1
Project Termini From -To
VARIES VARIES
Begin Mile Post
End Mile Post
Length of Project
VARIES
VARIES
N/A
Route ID
Begin Mile Point
End Mile Point
VARIES
VARIES
VARIES
WSDOT Region
Legislative District(s)
South Central Region
13
r WSDOT ) Federal Employer 91-601349
Use Only J Tax ID Number
Federal Program Title
Z 20.205 ❑ Other
Start Latitude N VARIES Start Longitude W VARIES
End Latitude N VARIES End Longitude W VARIES
Nearest City Name Project Zip Code (+
Ellensburg, WA 98926
Award Type
W✓ Local ❑ Local Forces ❑ State ❑ Railroad
City Number County Number County Name
N/A 19 Kittitas
Congressional District(s) Urban Area Number
8
Total Local Agency Federal Funds Phase Start
Phase Estimated Cost Funding Date
Nearest Hundred Dollar Nearest Hundred Dollar Nearest Hundred Dollar Month Year
P. E. 63,000 63,000 02/2022
R/W
Const. 601,000 601,000 06/2023
Total 664,000 1664,000
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
VARIES 2
There are several bridges and culverts that have inadequate or non-existent safety rail, approaches, or terminals
throughout the County.
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Add / upgrade bridge rail, including approaches and end terminals. Also includes associated ADA and utility
work as needed.
Local Agency Contact Person Title Phone
Darren Case Construction Manager 509-962-7019
Mailing Address City State Zip Code
411 N. Ruby, Suite 1 Ellensburg WA 98926
By ell
Project Prospectus le Approving Authority
Title County Engineer Date /ZZZ-
DOT Form 140-101 Page 1
Revised 04/2015 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
Bridge Rail Improvements:
Code 3 -Phase 1
Type of Proposed Work
Project Type (Check all that Apply)
Roadway
Width
Number of Lanes
❑ New Construction ❑ Path / Trail
❑ 3-R
varies
varies
❑ Reconstruction ❑ Pedestrian / Facilities
❑ 2-R
❑ Railroad ❑ Parking
0 Other
❑ Bridge
Geometric Design Data
Description
Through Route
Crossroad
0 Principal Arterial
0 Principal Arterial
Federal
❑ Urban
0 Minor Arterial
❑ Urban W1 Minor Arterial
Functional
❑✓ Rural
Collector
❑✓ Rural Collector
Classification
❑ NHS
Major Collector
❑ NHS Major Collector
Minor Collector
Minor Collector
❑ Local Access
❑ Local Access
Terrain
❑ Flat
❑ Roll ❑ Mountain
❑ Flat ❑ Roll ❑ Mountain
Posted Speed
Varies
Design Speed
Varies
Existing ADT
Varies
Design Year ADT
Varies
Design Year
2022
Design Hourly Volume (DHV)
N/A
Performance of Work
Preliminary Engineering Will Be Performed By
Others
Agency
Kittitas County Public Works
0 %
100
Construction Will Be Performed By
Contract
Agency
Contractor
100 %
esu
Environmental Classification
❑ Class I - Environmental Impact Statement (EIS) ❑✓ Class II - Categorically Excluded (CE)
❑ Project Involves NEPA/SEPA Section 404
0 Projects Requiring Documentation
Interagency Agreement
(Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
None Anticipated
DOT Form 140-101 Page 2
Revised 04/2015 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
Bridge Rail Improvements: Code 3 -Phase 1
Right of Way
❑✓ No Right of Way Needed
❑ Right of Way Needed
All construction required by the
❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the exiting right of way.
Utilities
Railroad
❑ No utility work required
❑✓ No railroad work required
0✓ All utility work will be completed prior to the start
❑ All railroad work will be completed prior to the start of
of the construction contract
the construction contract
All utility work will be completed in coordination
F] All the railroad work will be completed in coordination
with the construction contract
I with the construction contract
Description of Utility Relocation orAdjustments and Existing Major Structures Involved in the Project
No anticipated or known utility conflicts
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the proposed project? ❑ Yes ❑✓ No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency Kittitas County
Date By
Mayor/Chairperson
DOT Form 140-101 Page 3
Revised 0412015 Previous Editions Obsolete