HomeMy WebLinkAboutResolution Establish CRP_Swauk Creek BridgeKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: January 18, 2022
ACTION REQUESTED: Request to Approve a Resolution to establish
County Road Project (CRP) number supporting the
Replacement of the Swauk Creek Bridge, Bridge
No. 07101.
BACKGROUND: Kittitas County has been selected to receive
$2,463,000.00 from the Federal Lands Access
Program for the Swauk Creek Bridge replacement
project. This grant funding, along with an estimated
local match of $484,000 from the Road Fund, will
be used to replace the load restricted structure on
Liberty Road over Swauk Creek. The work includes
removal of the existing bridge, design, and
construction of a new bridge meeting current
WSDOT safety specifications and requirements.
Public Works
RECOMMENDATION: Approve the Resolution to establish County Road
Project (CRP) number for the Replacement of the
Swank Creek Bridge, Bridge No. 07101.
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution
LEAD STAFF: Joshua Fredrickson, County Engineer
RESOLUTION NO.
BEFORE THE BOARD OF COUNTY COMMISSIONERS OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter
of initiating a county road project designated as:
CRP NO: 306-21 JOB NO: RC2193
IT IS HEREBY RESOLVED that the Liberty Road over Swauk Creek (07101) Bridge Replacement
The project will replace bridge #07101 on Liberty Road crossing Swauk Creek at Milepost 0.02. The bridge is currently
load restricted limiting vehicles from accessing the Town of Liberty and nearby public lands. The project will include
replacing the existing bridge, guardrail, approaches and shoulders to meet current Washington State Department of
Transportation safety specifications and requirements.
ARTERIAL
ACCESS
This project is hereby declared to be a public necessity and the County Engineer is hereby ordered and authorized to report and
proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070).
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the County
Engineers estimate, is hereby made in the amounts and for the purposes shown:
PURPOSE
AMOUNT
TOTALS
PRELMINARY ENGINEERING
s 440,000
CONSTRUCTION ENGINEERING
s 150,000
RIGHT-OF-WAY ACQUISITION
s 50,000
SUB -TOTAL
s 640,000
County Forces CONSTRUCTION
$
CONTRACT CONSTRUCTION
s 2,307,000
SUB -TOTAL
s 2,307,000
TOTAL PROJECT COST
s 2,947,000
GRANT OR OTHER FUNDS
s 2,463,000
Grant source: STBG / American Rescue Plan
As
TOTAL COUNTY ROAD FUND ALLOCATION
484,000
oshua Fredrickson,75.E.
County Engineer
® THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2022 ANNUAL ROAD PROGRAM AS
ITEM NO. 04
❑ THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM PROJECT 04
IN ACCORDANCE WITH RCW 36.81.130
IT IS FURTHER RESOLVED THAT:
® THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ.
❑ THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN ACCORDANCE WITH RCW 36.77.065 AND
WAC 136-18.
ADOPTED this day of , 2022. Attest:
BOARD OF COUNTY COMMISSIONERS Clerk of the Board
KITTITAS COUNTY. WASHINGTON
Laura Osiadacz, Chair
Cory Wright, Vice -Chair Brett Wachsmith, Commissioner
g:\base\forms\eng\crp-frm 111112022