Aviation Revitalization Loan Program Application Forms
This document includes form fields to be completed for the Aviation Revitalization Loan Program.
Saving the PDF document to your computer should allow you to save your entries and then edit the document
at a later time.
Ensure you have completed ALL field entries. Make sure to save your work frequently.
If you are not able to save your work, you will need to print the application before closing the document.
Options for submitting your application:
By Email -
The airport sponsor’s authorized representative can Email the application by attaching the PDF document and
all other supporting documentation to: chenaud@wsdot.wa.gov
By Mail or in Person -
The application forms can be printed and signed by the airport sponsor ’s authorized representative along with
other supporting documentation and can be mailed or hand delivered to WSDOT Aviation’s office at:
WSDOT Aviation Division
Attn: Dave Chenaur, Program Manager
7702 Terminal Street SW
Tumwater, Washington 98501-7264
DOT Form 900-031
Revised 01/2020
Aviation Revitalization Loan Program Application
7702 Terminal Street SW
Tumwater, Washington 98501-7264
Date of Request
1 Applicant
Applicant’s Authorized Representative:
Name:
Title:
Address:
Address 2:
City: State: Zip:
Phone: Cell:
Email:
Federal Tax ID:
2 Project to be Managed by:
Company:
Name:
Address:
Address 2:
City: State: Zip:
Phone: Cell:
Email:
Find your legislative and congressional district at: http://app.leg.wa.gov/districtfinder/
3 Airport:FAA Classification: Legislative District:
NPIAS Non-NPIAS State Classification: Congressional District:
Enter number of annual commercial equipment enplanement last reported to FAA: General Public Access
Yes No
4
No. Project Name and Description Total Project Cost Local Funds
State Grant
Funds
Federal Grant
Funds Loan Request
5 Does the airport have an up-to-date Master Plan or ALP
Narrative Report? Yes No Date:
Does the airport have an approved Airport Layout Plan (ALP)? Yes No Date:
Was the annual requirement to review and update Airport Information
System (AIS) data met for the preceding calendar year? Yes No
Does the airport sponsor have policies to reduce greenhouse gas
emissions? Yes No
If yes, submit a copy of the policies. Submitting copy via:
6 Signature of Applicant’s Authorized Representative
*Only sign IF printing and submitting original paper document, provide signature here.
*IF submitting application electronically (PDF document), Email must be sent directly from airport’s authorized representative.
Century West Engineering
Instructions Aviation Revitalization Loan Program Application (DOT Form 900-031)
1. Applicant
The name of the municipality or person who legally owns and is responsible for managing the airport “airport sponsor”.
The Applicant’s Authorized Representative is the individual who may be duly authorized by the public entity to
act on its’ behalf in the performance of duties overseeing the airport. Typically this is a mayor, city manager, county
commissioner, city councilperson, port director, or tribal council member. The authorized representative should be the
same individual who will sign the Aviation Revitalization Loan Program agreement, if awarded funding. The airport
manager should only be listed if he or she has the authority to negotiate contracts on behalf of the applicant.
Name, Title, Address, Phone, Cell, Email Address, and Federal Tax ID. This should be the contact information for
the applicant’s authorized representative.
2. Project to be Managed by is the individual who will be responsible for the day-to-day management of the project and
will be the appropriate contact for WSDOT Aviation to communicate matters relating to the loan. This person could
be an employee of the airport sponsor. If the airport sponsor would like to authorize their consultant to communicate
directly with WSDOT Aviation on their behalf, than this would be that individual.
3. Airport is the approved name of the airport.
Check if the airport is included in the National Plan of Integrated Airport Systems (NPIAS) or whether it is designated as
a Non-NPIAS airport.
Select the appropriate FAA and State classifications from the dropdown lists.
Select the appropriate Legislative and Congressional districts for the airport from the dropdown lists (If you are unsure
of your districts, click on the hyperlink and enter the airport sponsor ’s address).
4. Project Name and Description, along with Project Funding Sources
Submit only one (1) project per application. Enter the numerical application project number starting with ‘1’. If submitting
more than one application, subsequent applications should be numbered in-ascending order (i.e. 2, 3, 4, etc.). The
Project Name should be descriptive and be similar to the Project Title entered in the State Capital Improvement
Program (SCIP), if applicable. Projects not included in the SCIP can be considered for funding.
Give a brief but accurate description of the project. You will have the opportunity to expand upon this in the Project Data
Sheets to follow.
Insert the full cost of the project, the amount of funds from other local, state, or federal sources, if any, and the amount
you are requesting from the Aviation Division.
The total of the first column must equal the total of all other columns.
Please make these amounts as accurate as you can. Actual project bid amounts or negotiated consultant fees are
preferable. If precise amounts are not yet available you are encouraged to use professional engineering estimates.
If these estimates turn out to be an understatement and inadequate to cover the cost of the actual project, WSDOT
Aviation may not be able to cover the additional costs which may have to be borne by the applicant. You will be asked
to provide additional information supporting these costs and the source on the project data sheets.
5. Other Questions and Required Documentation
Master Plan / ALP Narrative Report - Please indicate if the airport has an approved Airport Master Plan or Airport
Layout Plan (ALP) Narrative Report by checking ‘Yes’ or ‘No’. If ‘Yes’ insert the month and year the report is dated.
Airport Layout Plan (ALP) -Please indicate if the project is included in an approved Airport Layout Plan (ALP) by
checking ‘Yes’ or ‘No’. If ‘Yes’ insert the month and year the plan was approved. The project you are requesting funding
for does NOT need to be shown on the ALP in order to be considered for funding. If the project is not included in an
approved ALP, the sponsor should indicate where the project is to be located on airport property.
Airport Information System (AIS) - Please indicate by checking ‘Yes’ or ‘No’ if the airport sponsor met the requirement
to review and update their data in the AIS for the preceding calendar year by the December 31 deadline
DOT Form 900-031 Instructions
Revised 01/2020
Greenhouse Gas Policy -RCW 70.235.070, outlines fund distribution prerequisites for infrastructure and capital
development projects, all airport sponsors should adopt a greenhouse gas emission reduction policy in accordance
with this new law. Please indicate by checking ‘Yes’ or ‘No’ if the airport sponsor has an adopted policy. If ‘Yes’ submit a
copy of the policy to WSDOT Aviation and indicate how you are submitting by selecting the appropriate response from
the drop-down menu.
For more information on this law, please visit Washington State Legislature’s Revised Code of Washington (RCW) at
http://apps.leg.wa.gov/rcw/default.aspx?cite=70.235.070
While having a policy is currently not a requirement that determines loan eligibility, it is anticipated in the near future
that this will be an added requirement.
6. Signing and submitting the Loan Application
WSDOT Aviation prefers airport sponsors submit the loan application and supporting documentation electronically.
The Aviation Revitalization Loan Application, Project Data Sheet, and Supplemental Justification Sheet will need to
be emailed from the Applicant’s Authorized Representative as a saved pdf file. The email being sent directly from the
Applicant’ Authorized Representative will serve in lieu of an actual signature on a printed document.
The application can still be submitted as a printed document in which case the Applicant’s Authorized Representative
will need to sign the Aviation Revitalization Loan Program Application in the space provided.
There are multiple methods available for submitting the additional supporting documentation either electronically or in
printed form.
Regardless of how the airport sponsor chooses to submit their application, all application forms and supporting
documentation must be received by WSDOT Aviation by the published deadline.
DOT Form 900-031 Instructions
Revised 01/2020
Aviation Revitalization Loan Application Project Data Sheet
Complete a separate Project Data Sheet for each project listed from the Airport Aid Application (Form 900-031
1. Project Category (Select One Only)
Hangar Fueling Infrastructure Passenger Amenities Property
New New Utilities Terminal Business Park
Replace Replace Apron Parking Retail
Renovate Upgrade Taxiway Restaurant/Food Other
Other Other Other Rental
Other
Other
2. Detailed Project Description / Approach to Accomplishing Project:
3. Project Justification:
4. Cost Estimate Details: Source of Project Cost Estimate -
5. Project Schedule:
Expected Start of Project: Expected Completion of Project:
Start of Work Covered by Loan: Completion of Work Covered by Loan:
Submit a detailed project schedule (to include project milestones). Submitting project schedule via:
6. Other Supporting Project Documentation (Required):
Submit a spending and repayment plan identifying anticipated loan expenditures
and repayment schedule by month.
Submitting via:
Submit job creation data using the Aviation Economic Impact Calculator. Submitting via:
7. Other Supporting Project Documentation (As Applicable):
Submit documentation supporting your consultant selection process. Submitting via:
Submit a copy of your consultant’s Scope of Work. Submitting via:
Have project plans and specifications been prepared? Yes No
Has the property been appraised? Yes No
FAA AIP Project Number (if any):
FAA Grant Contract Number (if any):
Other supporting documentation?
DOT Form 900-031A
Revised 01/2020
Instructions for Project Data Sheet(DOT Form 900-031A)
Complete a separate Project Data Sheet for the project listed from the Aviation Revitalization Loan Program Application
(Form 900-031). A individual sheet has been created and has automatically populated data for Airport Sponsor, Airport
Name, and Project Title. If there is more than one project, you will need to complete an additional application packet.
1. Project Category and Type - Mark the appropriate project category. Some categories will also ask for specific project
type information under that category (e.g. Category - Hangar, Project Type – New Hangar). Select only the category of
the most prominent work element of your project.
2. Detailed Project Description - Provide a brief but descriptive narrative of the project to thoroughly explain what will be
accomplished by the project. Please be as clear and specific as possible.
Example: Hangar – Renovate: Remove all existing walls, roof, lighting, mechanical and plumbing systems leaving only
the existing structural steel frame, concrete slab, and foundations in place. Prime and repaint the existing structural
frame. Provide existing structure with new exterior walls, roof and openings including new hangar doors. Provide new
HVAC system and a new high-expansion foam fire suppression system. Provide new electric power, lighting, and
distribution system. Provide a UPS to enable all hangar door operations during a power outage. Provide new above-
slab plumbing. The new large hangar space will be able to house 4 aircraft at a time. Other new interior spaces include:
an addition to the northwest corner to include the fire suppression system and a storage room. The existing “wing”
extending from the northwest building face shall enclose electrical and mechanical rooms, a communications room, two
storage rooms and office spaces, as described.
3. Project Justification - Provide a brief narrative to justify how the project would generate revenue and sustain/expand
airport usage should the project receive a state loan. Cite marketing plans or research that supports the project. List
any deposits or waiting lists for structures proposed. Required: Describe how revenue sources will be used to repay the
loan including rental/lease rates proposed and if there are any anticipated rental rates increases proposed in the future.
Attach any documents that support and identify the revenue sources described as directed under Section 6: Other
Supporting Project Documentation.
4. Cost Estimate Details - Provide specific information as to how the project costs shown on the first page of the Loan
Application were arrived at including the source (i.e. bid tab, engineer’s estimate, vendor quote, etc.). Be sure to
include a detailed itemization of the specific costs (i.e. labor and overhead costs not just construction costs in your
estimate (i.e. design engineering, environmental, project bidding, construction, construction observation, etc.)
5. Project Schedule - Indicate the expected start and completion of the overall project and when the work covered by the
loan is beginning and ending. Note that these two sets of dates can be different. Only eligible costs incurred after the
loan agreement execution date are reimbursable.
Submit a detailed project schedule that includes major milestones, key deliverables, specific actions, etc. A typical
project schedule is included for your convenience. The milestones listed are not necessarily in chronological order.
6. Other Supporting Project Documentation (Required) - 1) Submit a spending plan showing anticipated loan
expenditure amounts by month over the duration of the project, 2) Submit a repayment plan indicating the preferred
loan length (up to 20 years), any grace period desired (up to 3 years) and the source of funds intended to repay the
loan, and 3) Submit information on jobs/revenue created by the project (WSDOT’s Aviation Economic Impact Calculator
is a good tool for this) and/or information that supports revenue projections.
7. Other supporting Project Documentation (As Applicable) - Provide any additional information as applicable that will
help WSDOT Aviation fully understand your project. A Statement of Financial Activity (Income Statement), Statement of
Financial Position (Balance Sheet), and Statement of Cash Flows is highly suggested.
DOT Form 900-031A Instructions
Revised 01/2020
Aviation Revitalization Loan ProgramApplication Supplemental Justification
Complete a separate Supplemental Justification for each project listed from the Airport Aid Application (Form 900-031)
1. Can you provide conclusive evidence that the loan project will provide revenue generating income
opportunities? If yes, please provide details. Yes No
2. Will a specific private development or expansion occur, only if the aviation facility improvement is
made? If yes, explain. Yes No
3. Will this loan project result in the creation of jobs or private sector capital investment? If yes,
please elaborate. Yes No
4. Does this loan project improve opportunities for the successful maintenance, operations, or
expansion of the airport or adjacent business park? If yes, explain. Yes No
5. Does this project result in the creation or retention of long-term economic opportunities? If yes,
elaborate. Yes No
6. Does this project result in leveraging additional federal funding for the airport? If yes, explain. Yes No
7. Project Readiness:
a. Has required environmental documentation (e.g. NEPA/SEPA) been approved?
b. Is project ready to proceed immediately?
Yes
Yes
No
No
8. Land Use Compatibility:
a. Does the local land use jurisdiction recognize the airport as an Essential Public Facility in
its comprehensive plan? If yes, provide reference to the specific location(s) in the plan. Yes No
b.Does the comprehensive plan include policies and/or zoning in place that discourages
the development of incompatible land uses adjacent to the airport? If yes, provide
reference to the specific location(s) in the plan.
Yes No
c.Are regulations and/or zoning in place that prohibit penetration of FAR Part 77 surfaces?
If yes, provide references to the specific regulation(s). Yes No
DOT Form 900-031B
Revised 01/2020
Will be a CATEX