HomeMy WebLinkAboutResolution_HandH Award_Manastash Bank Stabilization_NaturalWatersKITTITAS COUNTY DEPARTMENT OF PUBLIC WORKS AGENDA STAFF REPORT AGENDA DATE: September 7, 2021 ACTION REQUESTED: Request to Approve a Resolution Awarding Hydraulics and Hydrology Design Support for the Manastash Road Bank Stabilization Project to Natural Waters and Authorize the Director of Public Works to negotiate scope of work and sign the professional services agreement. BACKGROUND: Public Works produced a Request for INTERACTION: Qualifications seeking Hydraulics and Hydrology Design Support for the Manastash Road Bank Stabilization Project. Public Works advertised for said services by issuing a Request for Qualifications in the local paper of record, advertising for a three- week period in July 2021 with no submittals being received. Public Works then readvertised in the local paper of record for a second three-week period in August 2021. One (1) qualified firm responded to the request for qualifications process closing on August 26, 2021. Staff has reviewed the submittal and is recommending awarding said contract to Natural Waters. Public Works RECOMMENDATION: Approve a Resolution to Award Hydraulics and Hydrology Support for the Manastash Road Bank Stabilization Project to Natural Waters and Authorize the Director of Public Works to negotiate scope of work and fee and sign the professional services agreement once negotiated. HANDLING: Return one (1) original to Public Works ATTACHMENTS: Resolution LEAD STAFF: Josh Fredrickson, County Engineer BOARD OF COUNTY COMMISSIONERS COUNTY OF KITTITAS STATE OF WASHINGTON RESOLUTION NO. 2021 - AWARDING HYDRAULICS AND HYDROLOGY DESIGN SUPPORT FOR THE MANASTASH ROAD BANK STABILIZATION PROJECT TO NATURAL WATERS AND AUTHORIZE THE PUBLIC WORKS DIRECTOR TO NEGOTIATE SCOPE OF WORK AND FEE FOR SAID PROJECT WHEREAS: Public Works solicited for qualified hydrology and hydraulic modeling firms pursuant to state and federal procurement regulations soliciting for proposals for three weeks in July 2021 and again in August 2021 after receiving no response from the initial advertisement; and WHEREAS: One (1) qualified hydrology and hydraulic modeling firm responded to the request for qualifications with process closing on August 26, 2021; and WHEREAS: A review committee of Public Works staff evaluated said response and have selected Natural Waters as the preferred firm to provide said services; NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best interest of the public, does hereby authorize the Public Works Director to negotiate a scope of work and fee with Natural Waters for hydraulics and hydrology design support for the Manastash Road Bank Stabilization Project and authorizes the signature of the Public Works Director on the required professional services agreement providing an acceptable scope of work and fee is successfully negotiated. DATED this 7h day of September 2021, at Ellensburg, Washington Attest: ❑ Clerk of the Board- Julie Kjorsvik ❑ Deputy Clerk of the Board- Mandy Buchholz BOARD OF COUNTY COMMISSIONERS KITTITAS COUNTY, WASHINGTON Brett Wachsmith, Chairman Laura Osiadacz, Vice -Chairman Cory Wright, Commissioner