DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: August 3, 2021
ACTION REQUESTED: Request to Approve a Resolution to establish
County Road Project (CRP) number supporting the
resurfacing of No. 5 Mine Road
BACKGROUND: In 2019 utilities were extended under No. 5 Mine
Road in preparation for the new Public Works
Upper County maintenance facility. No. 5 Mine
Road had been an asphalt paved surface.
Anticipating heavy construction traffic during
construction of the maintenance facility, the utility
project left the surfacing of No. 5 Mine Road from
the transfer station to the end of the road as gravel
surfacing.
INTERACTION:
At this time the bulk of construction on the
maintenance facility is complete and it is proposed
to reestablish the paved surface for No. 5 Mine
Road and meet current width standard. New
pavement will be placed from a point north of the
transfer station entrance to the end of the road.
County forces will perform the work to pave the
roadway. Funding in the amount of $69,700.00 will
come from the County Road fund.
Public Works
RECOMMENDATION: Approve the Resolution establishing a County Road
Project (CRP) number supporting the resurfacing of
No. 5 Mine Road.
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution establishing CRP No. 307-21
LEAD STAFF: Joshua Fredrickson, County Engineer
RESOLUTION NO.
BEFORE THE BOARD OF COUNTY COMMISSIONERS OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter
of initiating a county road project designated as:
CRP NO: 307-21 JOB NO: RC2198-A1
IT IS HEREBY RESOLVED for No. 5 Mine Road Improvements
Improvement to No. 5 Mine Road from mile post 0.04 to mile post 0.14, reestablish pavement road surface.
ARTERIAL ❑
ACCESS
This project is hereby declared to be a public necessity and the County Engineer is hereby ordered and authorized to report and
proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070).
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the County
Engineer's estimate, is hereby made in the amounts and for the purposes shown:
IN
E/
0
PURPOSE
AMOUNT
TOTALS
PRELMINARY ENGINEERING
$
2,700.00
CONSTRUCTION ENGINEERING
$
6,000.00
RIGHT-OF-WAY ACQUISITION
$
SUB -TOTAL
$
8,700.00
County Forces CONSTRUCTION
$
61,000.00
CONTRACT CONSTRUCTION
$
SUB -TOTAL
$
61,000.00
TOTAL PROJECT COST
$
69,700.00
GRANT OR OTHER FUNDS
$
Source: County Road Fund
TOTAL COUNTY ROAD FUND ALLOCATION
$
69,700.00
Xsh Fredrickson, P.E.
County Engineer
THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2021 ANNUAL ROAD PROGRAM
THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM IN
ACCORDANCE WITH RCW 36.81.130
IT IS FURTHER RESOLVED THAT:
THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ.
® THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN
ACCORDANCE WITH RCW 36.77.065 AND WAC 136-18.
ADOPTED this day of , 2021.
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chair
Laura Osiadacz, Vice -Chair
Attest:
Clerk of the Board
Cory Wright, Commissioner
g:tbase\formsteng\crp-frm 7/27/2021