HomeMy WebLinkAboutResolution_Establish CRP_HungryJctRdKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA DATE:
ACTION REQUESTED:
AGENDA STAFF REPORT
May 4, 2021
Request to approve a Resolution to establish County
Road Project (CRP) number supporting the
reconstruction of Hungry Junction Road
BACKGROUND: Kittitas County has been selected to receive
$3,631,500.00 from the Rural Arterial Program
(RAP) for the reconstruction of Hungry Junction
Road. The roadway is narrow and is showing areas
of significant pavement distress. This existing
pavement will be removed and replaced. There are
also four vertical curve which are to be
reconstructed to improve sight distance. The
roadway is also to be widened with additional safety
improvements such as guardrail and flattening of
slopes. This project proposes to reconstruct from
mile point 0.0 to mile point 1.74.
INTERACTION:
Public Works
RECOMMENDATION: Approve the Resolution establishing a County Road
Project (CRP) number supporting the reconstruction
of Hungry Junction Road.
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution establishing CRP No. 304-20
LEAD STAFF: Joshua Fredrickson, County Engineer
RESOLUTION NO.
BEFORE THE BOARD OF COUNTY COMMISSIONERS OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter
of initiating a county road project designated as:
CRP NO: 304-20 JOB NO: RC2093
IT IS HEREBY RESOLVED for Hungry Junction Road (M.P. 0.00-1.74) Improvements
The existing BST pavement is narrow with areas of significant longitudinal cracking and settling over the top of drainage
structures. This existing pavement will be removed and replaced per design. There are also four vertical curves that need
to be corrected to meet safe sight stopping distance design standards for the posted speed limit. The road will be
widened, and above ground obstacles will be removed or relocated, guardrail installed or slopes flattened where
warranted.
ARTERIAL ❑
ACCESS
This project is hereby declared to be a public necessity and the Director of Public Works acting as the County Engineer is hereby
ordered and authorized to report and proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070).
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the Director of
Public Works' estimate, is hereby made in the amounts and for the purposes shown:
PURPOSE
AMOUNT
TOTALS
PRELMINARY ENGINEERING
$ 504,044
CONSTRUCTION ENGINEERING
$ 168,015
RIGHT-OF-WAY ACQUISITION
$ 50,000
SUB -TOTAL
$
is
722,059
County Forces CONSTRUCTION
$
CONTRACT CONSTRUCTION
$ 3,629,119
SUB -TOTAL
3,629,119
TOTAL PROJECT COST
$
4,351,178
GRANT OR OTHER FUNDS
$
3,631,500
Grant Source: RAP
Is
TOTAL COUNTY ROAD FUND ALLOCATION
719,678
_osh Fredrickson, P.E.
County Engineer
® THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2021 ANNUAL ROAD PROGRAM AS
ITEM NO. 12
❑ THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM IN
ACCORDANCE WITH RCW 36.81.130
IT IS FURTHER RESOLVED THAT:
® THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ.
❑ THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN ACCORDANCE WITH RCW 36.77.065 AND
WAC 136-18.
ADOPTED this day of
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chair
2021. Attest:
Clerk of the Board
Laura Osiadacz, Vice -Chair
Cory Wright, Commissioner
g:\base\forms\eng\crp-frm 4/28/2021