HomeMy WebLinkAboutRes-2021-054BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTTON No. 2021- 05 4
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY
FEDERAL AID PROJECT PROSPECTUS CONSTRUCTION PHASE FOR THE
VANTAGE HIGHWAY PROJECT, CRp 298-19
WHEREAS: The Vantage Highway Project was awarded Federal funds (HSIP) that will
be used to install and upgrade non-compliant guardrail, and protect
hazardous slopes along Vantage Highway MP 21.25 - MP 27.51; and
WHEREAS: This project will be tied with a Rural Arterial Program project, which will
repair and provide an asphalt overlay on all lanes of Vantage Highway to
build surface depth and structural capacity at the same location; and
WHEREAS: In preparation to advertise the project for construction in April of 2021
Public Works is requesting the Washington State Department of
Transportation to release the Federal Funds for construction; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the
Chair acknowledging the project has been reviewed and is consistent with
the agency's comprehensive plan for community development; and
NOW' THEREFORE BE IT RESOLVED that the Board of County Commissioners, in
the best interest of the public, does hereby approve the Board's signature
on the Local Agency Federal Aid Project Prospectus for the Vantage
Highway Project, CRP 298-19.
DATED on this lth day of April, 202I, at Ellensburg, Washington.
BOARD OF COUNTY
COMMISSIONERS.,rtrtt\ll I I I I l///ltrrr,
^.$,*.1..I9.Y !!{;,.,
S oY."' ' ..on,2--
-s .r --...- '.."(f Z
-: i f\ n5- *--
".?^'--:;5! 1"itr'"',.1, v i@=
=-,. -.1 , /J: u .
=-A'.. =\ --'t,.j-t j
*; . AtteJl .+S
i'o)'n: cterk 6toi Board- Jul ie Kjorsvik'4;,YNry 1,y6ei))\+"'///11y1,,,,,,,i1rt\\'
KITTITAS COLINTY A
ABSENT
Laura Vice-Chairman
TON
n Deputy Clerk of the Board- Mandy Buchholz
Cory W Commissioner
Prefix Route ()
FederalAid
Proiect Number HSrP - 19CN(003)
Local Agency
Project Number cRP 298-19, RC 1913
^-.w Washington State
Department of Tlansportation Local Agency Federal Aid
Project Prospectus
Date March 25,2021
DUNS Number 0I-020-2547
Federal Employer
Tax lD Number 9l-601349WSDOT
Use Only
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
HMA repair and an asphalt overlay on all lanes in an attempt to build surface depth and structural capacity
Federal funds will be used to install/upgrade guardrail.
Local Agency Contact Person
Darren Case
Title
Construction Manager
Phone
(s09)962-7s23
Mailing Address
411 N Ruby St, Suite I
City
Ellengburg
State
WA
Zip Code
98926
Project Prospectus
By
Approving Authority
I1;s Deputy Director / County Engineer oa€"y'.z/z.zt
Agency
Kittitas County
CAAgency
TlYes n ruo
Federal Program Title
Yzo.zos n otner
Project Title
Vantage Highway
Start Latitude N 46o 57'3I.23"
End Latitude N 46o56'56.04"
Start Longitude W 120' 7'22.99"
End Lonoitude W 119'59'44.22"
Project Termini From-To
21.25 27.51
Nearest City Name
Ellensburg
Project Zip Code (+4;
98950-A021
Begin Mile Post
2t.25
End Mile Post
27.51
Length of Project
6.26 Miles
Award Type
M tocat! tocat Forces l-l State ! Raitroad
Route lD Begin Mile Point
21.2s
End Mile Point
27.5r
City Number County Number
t9
County Name
Kittitas
WSDOT Region
South Central Region
Legislative District(s)
13
Congressional District(s)
8
Urban Area Number
Phase
Total
Estimated Gost
(Nearest Hundred Dollar)
Local Agency
Funding
(Nearest Hundred Dollar)
Federal Funds
(Nearest Hundred Dollar)
Phase Start
Date
Month Year
P.E 355,300 252,900 102,400 March2020
RA/V
Const.4,I71,400 2,981,400 1,190,000 April202I
Total 4,526,700 3,234,300 1,292,400
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width
MP 21 .25-23.36: 38', MP 23.36-27.5I:26'
Number of Lanes
MP 2L25-23.36:3 lanes, MP 23.36-27.51 :2lanes
The segment has non compliant guardrail, and many hazardous slopes. This segment shows HMA distress in
the form of transverse and longitudinal cracking, with signihcant annual maintenance and repair costs.
Revised 0412015 Previous Editions Obsolete
Page 1
Agency
Kittitas County
Project Title
Vantage Highway
Date
March 25,202I
Type of Proposed Work
Project Type (Check all that Apply)
! tlew Construction n Path /Trail n g-n
! Reconstruction E peOestrian / Facilities VZ-A
! Raitroao
n srioge
! Parking n otner
Roadway Width
26-38
Number of Lanes
2-3
Geometric Design Data
Description Through Route Crossroad
Federal
Functional
Glassification
! urnan
Z Rurat
flruHs
! erincipalArterial
I MinorArterial
! collector
! nllalor Collector
Z Minor Collector
! tocat Access
! uroan
! nurat
! ruHs
! erincipalArterial
I MinorArterial
! collector
I tvtalor Collector
! trllinor Collector
! tocat Access
Terrain Flat Roll M Mountain Flat Roll Mountain
Posted Speed 50
Design Speed 50
Existing ADT 586
Design YearADT
Design Year 2020
Design Hourly Volume (DHV)
Performance of Work
Preliminary Engineering Will Be Performed By
KPG (Consultant) / Kittitas County Public Works
Others
80 o/
Agency
20 o/o
Construction Will Be Performed By
Contractor
Contract
100 o/o
Agency
o/o
Environmental Classification
I Ctass I - Environmental lmpact Statement (ElS)
flProject lnvolves NEPA/SEPA Section 404
lnteragency Agreement
I Ctass lll - EnvironmentalAssessment (EA)
M Ctass ll - Categorically Excluded (CE)
! Projects Requiring Documentation
(Documented CE)
Project lnvolves NEPA/SEPA Section 404
lnteragency Agreements
Environmental Considerations
Revised 0412015 Previous Editions Obsolete
Agency
Kittitas County
Project Title
Vantage Highway
Date
March 25,202I
Right of Way
Z tlo Right of Way Needed
* AII construction required by the
contract can be accomplished
within the exiting right of way.
! nigrtt of Way Needed
n ruo Relocation ! Retocation Required
Utilities Railroad
n llo utility work required
f, rul utility work will be completed prior to the start
of the construction contract
nnlt utility work will be completed in coordination
with the construction contract
M ruo railroad work required
All railroad work will be completed prior to the start of
the construction contract
nntt the railroad work will be completed in coordination
with the construction contract
Description of Utility Relocation orAdjustments and Existing Major Shuctures lnvolved in the Project
Three power poles were permanently relocated by the utility company during the design phase to get them
outside ofthe clear zone.
FAA lnvolvement
ls any airport located within 3.2 kilometers miles of the project?!ves Mruo
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's com plan
Agen
< lt lzr Mayor/Chairperson
Date
DOT Form 140j101
Revised 0412015
By
Previous Editions Obsolete
munity development.
Page 3