HomeMy WebLinkAboutSet PHearing_Irrigation Franchise_MooreKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: January 19, 2021
ACTION REQUESTED: Request to Set a Public Hearing for February 16, 2021 at 2pm to
consider an irrigation franchise with David Moore along Badger
Pocket Road.
BACKGROUND: David Moore has applied for an irrigation franchise to install
irrigation pipe along Badger Pocket Road. The proposed franchise
is to install a 10" irrigation pipe for 1160' along Badger Pocket
Road to a pump station located on Mr. Moore's property servicing
a pivot utilized by Mr. Moore. Upon approval of the irrigation
franchise, a right of way permit will be required to conduct the
proposed work.
The Franchise Application is complete, and the appropriate
application fee has been collected.
INTERACTION: Public Works
RECOMMENDATION: Set a public hearing on February 16, 2021 at 2:00 pm and advertise
accordingly, to consider an irrigation franchise with David Moore
along Badger Pocket Road.
ATTACHMENTS: Franchise Application
LEAD STAFF: Mark Cook
Director of Public Works
Page 1 of 1
Public Notice
Kittitas County, Ellensburg WA
The Board of Commissioners will meet at 2:00pm on February 16, 2021 at the Commissioners' Auditorium, 205 West 5th
Avenue, Room 109, Kittitas County Courthouse, Ellensburg, WA to consider a franchise application by David Moore for an
irrigation franchise along Badger Pocket Road located in Section 36, Township 17 North, Range 19 East, W.M..
More information is online at http://www.co.kittitas.wa.us/notices/.
Clerk
Publish:
Daily Record: 01/21/2021; 01/28/2021; 02/04/2021
file:///C:fUsers/candie.leader/Downloads/newspaper-text°/`20(l).html 1/12/2021
Page 1 of I
For more information, contact Public Works
file:///C:[Users/candie.leader/Downloads/www-text%20(1).html 1/12/2021
�u�vrcti aawry
3KY1=YYAlS V®Vi%Tf Z
DEPARTMENT OF PUBLIC WORKS
FRANCHISE APPLICATION
Facility in County Road Right of WAY
Fee (NonRefundable): $1,615.00
Owner Name -David.
Mailing Add/ggss 06 MO'F '✓c'NrtQ
Phone Number 360 y q__20 -, 5P61
Applicant Name
Mailing Address
Phone Number
Payment Method: � Check I i 1 I O Cash
Permit#��
DATE STAMP
Pursuant to KCC 15A.03.040, upon receipt of the application, Kittitas County Public Works will
contact the applicant to schedule a meeting with the Director of Public Works and/or the County
Engineer to discuss terms and conditions of franchise agreement and schedule a Public Hearing for
consideration of the franchise agreement by the Board of County Commissioner's.
Su000rtine Documents Required for complete application:
• Detailed Project Plans
• Detailed Vicinity Map batr-Its RC
Schedule for Work to be performevel N
d
CALL BEFORE YOU DIG 1-800424-5555 or 811
Applicant is responsible for calling for underground utility locates 48 hours prior to construction.
Warning: The County does not mark any of the County infrastructures; the Applicant is responsible for any damage
to the County infrastructure.
13 All required supporting documents have been attached.
O Applicant agrees to obtain a work in Right -of -Way permit upon approval of the franchise agreement.
Applicant/Agent Signature "—�- ./r t�f/Y�4A Date
411 N. Ruby St. Suite 1 TEL (509) 962-7523
Ellensburg, WA 98926 FAX (509) 962-7663
Kooy's Irrigation
5284 HWY. 281 N
Quincy, WA 98848
Office: 509-787-3184; (2): 509-797-3524
paul@kooysirr.com
en
}.r k J r 5+>•�c i ^� -
Dave M00fB
4
Page 1 of 3
Pwrc� 4,3
l6h
IbPH�
�c
en
}.r k J r 5+>•�c i ^� -
Dave M00fB
4
Page 1 of 3
Pwrc� 4,3
l6h
IbPH�
Project plan for Dave ,:,00re irrigation project
We are planning on running 1160' of 10" pvc 100# pipe along side Badger Pocket
Rd starting from the KRD canal which is 3900' south of the intersection of Thrall
Rd and Badger Pocket Rd. It will then turn approximately 45 degrees and headNE
through Dave Moore property to an existing pump station point in his field.
Kooy's Irrigation will be installing the pipe. Dave Moore will be hiring an excavator
company to do the trench work.
Currently pvc pipe is hard to get so as soon as the pipe comes in we would like to
start digging and installing this pipe line. Our goal is to have it completed by
March 31, 2021
We will be laying the pipe in the county ditch with a minimum cover of 30". We
will have to dig out the current ditch to get that amount of cover.
Work schedule for Davi Moore
We plan on having this project completed by March 31, 2021, We will be starting
on this as soon as all permits are completed and weather permits.