HomeMy WebLinkAbout2020-12-14-minutes-public-works-study-sessionKITTITAS COUNTY COMMISSIONERS
Public Works Study Session
Regular Meeting
Monday December 14, 2020 -1:30 PM
Webex
1. Call to Order
2. Federal Highway Administration Federal Lands Access Program Grant Application - Swauk
Creek Bridge Replacement at Liberty Road.
3. Other business
4. Adjourn
Created on 12/11/2020 11:48:57 AM
KITTITAS COUNTY
PUBLIC WORKS STUDY SESSION MINUTES
Webex
Regular Meeting
MONDAY 1:30 PM DECEMBER 14, 2020
Board members present: Chairman Brett Wachsmith, Vice -Chairman Laura
Osiadacz, Commissioner Cory Wright
Others: Candie Leader, Josh Fredrickson, Liz Remeto, Rebecca Cruse,
Public Works; and One (1) Member of the Public
At 1:30 pm Chairman Brett Wachsmith opened the Public Works Study
Session.
FEDERAL HIGHWAY ADMINISTRATION FEDERAL LANDS ACCESS PROGRAM GRANT
APPLICATION - SWAUK CREEK BRIDGE REPLACEMENT AT LIBERTY ROAD
Josh Fredrickson gave background on the Federal Lands Access Program
Grant process and stated that a call for projects was sent out to
agencies for consideration. Josh Fredrickson stated that the Swauk
Creek Bridge at Liberty Road was selected to seek funding for due to
the current bridge being load restricted. Josh Fredrickson continued
that staff received numerous letters of support from stakeholders for
the project and that the current condition of the structure is
restricting access for recreation and scheduled timber sales. Josh
Fredrickson added that staff has applied for and received funding
from this program on other projects including the Manastash Sno-Park.
Discussion was held.
Meeting adjourned at 1:42 pm.
2020-12-14 MINUTES
KITTITAS COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: December 14, 2020
TOPIC: Federal Highway Administration Federal Lands Access Program Grant
Application — Swank Creek Bridge Replacement at Liberty Road
ACTION REQUESTED: Informational Only
LEAD STAFF:
Mark R. Cook
RECOMMENDATION:
Informational briefing — no action required by the Board.
BRIEFING SUMMARY:
• The existing bridge crossing Swauk Creek on Liberty Road is load restricted
• The bridge inhibits the United States Forest Service (USFS) from proceeding with
a timber sale
• Bridge replacement is a high priority for the Okanogan Wenatchee National
Forest (OWNF)
• Public Works received good support for the application from diverse stakeholder
groups
BACKGROUND:
The Federal Highway Administration's (FHWA) Federal Land Access Program affords
local government access to federal funding with a nexus to federal lands. Public Works
(PW) targeted this funding program and successfully replaced fish barriers at two
locations on Teanaway Road. Following that success, PW applied to the program for two
additional projects, one replacing the flow constricting bridge on the Teanaway River at
Dickey Creek. That grant award is currently being completed by FHWA design staff
with construction forecast for fall 2023. The road realignment and bridge replacement
project is estimated to cost approximately $8 million. The County is providing survey
services and funding $1M in local Road Fund to the project. The second project applied
for was the Manastash Bank Stabilization and Sno Park Improvements with an estimated
cost of approximately $1.9 million. This grant was also awarded to Kittitas County and
is planned for design in 2021 and construction in 2022. The cost to the County for this
project is approximately $537,000.
Damaged abutments to the Swank Creek Bridge on Liberty Road currently restrict heavy
traffic accessing national forest surrounding the community of Liberty. Emergency
response vehicles are unable to access forest roads used heavily for recreational activities.
Page 1 of 3
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
Since 2010, the Okanogan -Wenatchee National Forest has been working towards
restoration efforts in the Liberty area, Kittitas County, WA. The restoration strategy
produced in 2010 and updated in 2012 evolved in response to continuing large-scale
uncharacteristically severe wildfires and insect outbreaks. The Cie Elum Ranger District
began initial planning on the Swank Pine Project responding to the high risk of habitat
loss resulting from high fire risk and the high ratio of Wildland Urban Interface
associated with the Town of Liberty land use development. The action supports efforts
outlined in the Swank Basin Wildfire Protection Plan authored by the citizens of Liberty
with assistance from Cle Elum Ranger District staff. The Swauk Pine Project reduces the
risk of wildfires by reducing hazardous fuels and reestablishing natural fire regimes
reducing wildfire management costs and better protecting late successional and old forest
structure. The plan cannot be fully implemented without replacement of the County's
load limiting bridge on Swank Creek.
DISCUSSION:
Numerous stakeholders provided letters of support during the permit submittal process
(EXHIBIT 1). Bridge replacement supports reduced fire risk, stream restoration,
emergency rescue access for recreationalist and produces a much healthier forest. Given
PW's funding success with the FLAP program, we elected to make a run at replacing the
Swauk Creek Bridge for an estimated $2.8 million. The County's financial obligation is
approximately $380,000. It is unlikely that the County can replace the bridge without
supplemental funding.
FISCAL IMPACTS:
$384,429.19 in Road Fund ending fund balance if the grant request is awarded by
FHWA.
ATTACHMENTS:
Exhibit 1: Stakeholder grant support letters
Page 2 of 3
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
EXHIBIT 1: STAKEHOLDER GRANT SUPPORT LETTERS
Page 3 of 3
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
KIM SCHRIER
8TH DISTRICT, WASHINGTON
QCongreo of the Nniteb btateg
i)ouse of r%epresenWtlbes
Mightngton, DC 20313
December 2, 2020
Andrew Rasmussen, PE
Washington FLAP Program Manager
Federal Highway Administration
610 East Fifth Street
Vancouver, Washington 98661.
WFL.CallForProjects(@dot.gov
andrew.rasmussen@dot.gov
Hardcopy to follow
Dear Mr. Rasmussen:
1123 L:�M � "]I H'O-s i. L aJ�Lll'.h.
Wns�i'NiaaioN D DG 2 40515
(202)225 1161
I am writing to ask for your consideration of Kittitas County's application for funds through the Washington
Federal Lands Access Program to replace the Swauk Creek Bridge on Liberty Road. Replacing this load limiting
bridge is critical to the completion of long -planned forest health projects aimed at protecting a rural
community in my District from catastrophic wildfire.
The Swauk Pine Project is a collaborative forest restoration project located on National Forest System Land in
Swauk Creek Watershed near the town of Liberty in Kittitas County. Prescribed fire across thousands of acres is
planned. Commercial and non-commercial thinning will help restore overcrowded forests. Aquatic restoration
projects will improve critical fish habitat. But the project cannot be fully implemented until the County's
deficient Swauk Creek Bridge is replaced.
A new bridge will also allow emergency response vehicles to access a popular recreation area. The Swauk Pine
area supports year-round dispersed recreation including camping, mining, hiking, hunting, four-wheel driving,
horseback riding and snowmobiling.
Replacing the Swauk Creek Bridge will unlock countless recreation, safety, forest health and wildfire mitigation
opportunities, and this seems like an ideal fit for Federal Lands Access Program. I urge your full and fair
consideration of this application.
Sincerely,
Kim Schrier, M.D.
Member of Congress — WA08
November 19, 2020
Mark R. Cook, Director
Kittitas County Department of Public Works
411 North Ruby Street, Suite 1
Ellensburg, WA 98926
Dear Mr. Cook:
AFRC is a regional trade association whose purpose is to advocate for sustained yield timber
harvests on public timberlands throughout the West to enhance forest health and resistance to
fire, insects, and disease. We and our members do this by promoting active management to
attain productive public forests, protect adjoining private forests, and assure community stability.
We have been following the Forest Service's Swank Pine Project located in the Liberty area of
Kittitas County since it was first analyzed for restoration work back in 2010. During those 10
years of analysis, the forests located above the town of Liberty have suffered greatly from insect
and disease infestations and accumulation of forest fuels. Creating a high risk of catastrophic
wildfire. To remedy this situation the Okanogan Wenatchee National Forest has planned a timber
sale in that area, which will require an adequate infrastructure of roads and bridges for access.
Unfortunately, that project is now on indefinite hold as the deficient bridge located below the
community of Liberty cannot support timber sale vehicle loads. The condition of the bridge is
one significant factor in the economic viability of this vegetation management proposal.
AFRC supports Kittitas County in its application for grant funding to replace this bridge. And we
look forward to the County moving forward quickly with replacing the deficient bridge. This will
enable the Forest Service to make needed forest health treatments and to reduce potential
wildfire risks by implementing the timber sale. The new bridge will also allow access for fire and
life -safety response vehicles, as well as access for dispersed recreation including camping,
mining, hiking, hunting, four-wheel driving, horseback riding, and snowmobiling. Assuring the
replacement of his bridge in a timely manner will benefit a variety of stakeholders on this portion
of the Okanogan Wenatchee National Forest.
Thank you for your consideration, and we hope this bridge replacement can move forward
quickly.
Sincerely,
Matt Comisky
Washington Manager
American Forest Resource Council
American Forest Resource Council
924 Capitol Way South, Suite 102 • Olympia, Washington 98501
Tel. 360.352.3910 9 Fax 360.352.3917
November 19, 2020
Mark R. Cook, Director
Kittitas County Department of Public Works
411 North Ruby Street, Suite 1
Ellensburg, WA 98926
Dear Mr. Cook:
DEPARTMENT OF
NATURAL RESOURCES
Southeast Region
713 Bowers Road
Ellensburg, WA 98926
509-925-8510
southeast.region@DNR. WA.GOV
W W W.DNR. WA.GOV
We understand that the Kittitas County Department of Public Works completely undated it's
twenty-year Transportation Plan in 2018. The plan completely revised the focus on maintenance
of County Bridges to increase their life spans, in addition to a focus on replacing obsolete
structures. With the number of obsolete bridges in Kittitas County, you show a plan shortfall of
nearly $100,000 million.
This letter affirms our support of Kittitas County Department of Public Works submittal of a
2021-2023 Federal Lands Access Program Grant replacing the Swank Creek Bridge on Liberty
Road. We understand that funding assistance will help Kittitas County in meeting its objectives
as well as objectives of partnering organizations.
The Swank Creek Bridge on Liberty Road is an optimal choice for replacement as its current
load restrictions limit access to a large area of land, inhibiting efforts for forest health, fire
suppression, as well as opportunity for recreation in this area, not to mention the ability of
emergency vehicles to access.
Sincerely,
10,
Todd Welker
Region Manager, Southeast Region
Washington State Department of Natural Resources (DNR)
Washington State Legislature
December 1, 2020
Mark R. Cook, Director
Kittitas County Department of Public Works
411 North Ruby Street, Suite 1
Ellensburg, WA 98926
Dear Mr. Cook:
This letter affirms our support of Kittitas County Department of Public Works submittal
of a 2021-2023 Federal Lands Access Program Grant replacing the Swauk Creek bridge
on Liberty Road. This load limiting bridge is prohibiting implementation of the US
Forest Services' Swauk Pine Project.
Since 2010, the Okanogan -Wenatchee National Forest has been working towards
restoration efforts in the Liberty area, Kittitas County, WA. The restoration strategy
produced in 2010 and updated in 2012 evolved in response to continuing large-scale
uncharacteristically severe wildfires and insect outbreaks. The Cle Elum Ranger District
began initial planning on the Swauk Pine Project responding to the high risk of habitat
loss resulting from high fire risk and the high ratio of Wildland Urban Interface
associated with the Town of Liberty land use development. The action supports efforts
outlined in the Swauk Basin Wildfire Protection Plan authored by the citizens of Liberty
with assistance from Cle Elum Ranger District staff. The Swauk Pine Project reduces the
risk of wildfires by reducing hazardous fuels and reestablishing natural fire regimes
reducing wildfire management costs and better protecting late successional and old forest
structure. The plan cannot be fully implemented without replacement of the County's
load limiting bridge on Swauk Creek.
It is our understanding that in 2018, Kittitas County Department of Public Works
completed an update to its twenty-year Transportation Plan. The plan is completely
revised from previous efforts reflecting impacts from deferred maintenance of County
bridges over a ten-year period (2007-2017). The plan contains a funding plan reflecting a
comprehensive evaluation of all transportation funding mechanisms in Washington State
law as of the publication date (2018). A funding shortfall in the Public Works revenue,
addressing significant infrastructure needs through 2038, identifies as shortfall of nearly
$100,000 million. Without federal funding support for replacing the Swauk Creek
Bridge, other local priorities will likely result in continued load limiting on the structure.
During 2019, we further understand that the County worked with Forest Service District
staff attempting to solve the access issue. A pending timber sale is now on indefinite
hold as the deficient bridge cannot support timber sale vehicle loads. The bridge also
limits significant elements implementing the Swauk Pine Project.
The primary purpose of the Swauk Pine Project is two -fold:
• Improve resilience to wildfires and other disturbances by returning the forested
landscape to a state that is within or closer to the historic range of variability.
• Improve the resilience and function of aquatic systems that have been degraded
by previous and ongoing human actions.
The Swauk Pine area supports year-round dispersed recreation including camping,
mining, hiking, hunting, four-wheel driving, horseback riding and snowmobiling. The
load limited bridge restricts access of many fire -life -safety response vehicles from
serving the area. The Swauk Pine Planning area is 6,484 acres in size encompassing 287
acres of private land and 6,242 acres of National Forest System land that have proposed
restoration objectives across the landscape. A total of 6.4 miles of Forest Service System
jeep trail plus 1.9 miles of Forest Service System road that is dual use. 18 miles of
groomed snowmobile trail are also included in the area. Replacing the deficient bridge
unlocks emergency response vehicle access supporting numerous recreational uses in the
area.
Sincerely,
Senator Judy Warnick Representative Tom Dent Representative Alex Ybarra
13111 District 131h District 131h District
Logi,bti,r Building • Olcmpin. N%A WiOA4A82
MOUNTAINS T c�Mmlmatd 19. Co Ewmp
-,f- as, (l„ ue J vzIItlBF,upial
leudml{ t
i<ARarI. EWICW
REIC op
Fp ;,MM;bn! SMirtary fWbirsi'111 (pM1ni11M(I,iJ wogrdm C. -ti. 3a,'
fun EegG.Em ,us Joshkitaky('I, Pmlm Xcn R,;.am ('t RLstlem Doug Mc(kIMM1X•I, POmn Aisblanl Rag'm Marlagm
sV.,hglm SW,CarvntionC~ Cscaaa Law PPLLC Wadr.l Nan<s Wa*llon SraW Dlat m: M Nalt al .rz
Enmed'm V). Res nl Jassm ,Op i".sCommR,mOah Board Erlgagmnem Comnic:mtBwr "amul;ret,. I
Xun Laese!'I.kaeu ald Axs«iaMs lMNAGL errrcke i'. Panner M Wadual';.ARorrey mnNCeeahv,5,
IPMGLLP NBLGamsLLP Nuunla'.ns to SoaMGremwry Tust
'
November 24, 2020
GREENWAY
Mark R. Cook, Director
Kittitas County Department of Public Works
BOMID OF OLNECi0115
411 North Ruby Street, Suite 1
Lin Anderson. ^eM1m+, SIM Rlves LLP
are „n al.cW ImmeecMmx,
Ellensburg, WA 98926
Am Beta, Re,eed fmnder, xu,Mab Toys
aMar
iM. Ptlet M„Wne<gim
BAs, M.
Dear Mr. Cook:
Marsh"AR Recreakn,sal TarciLlkme,
hla vaiw. seruta
waanvglm ale Deplan mml a N,lwal �mes
Us..
Gaq MML V/&W Rm WLspn
I am writing on behalf of the Mountains to Sound Greenway Trust, in support of Kittitas
WMIArymn Sae Deplanmm, a Natural Relurm
as,rl.Pl<,id<m. Mml<—t—a—dw
County Department of Public Works' submittal of a 2021-2023 Federal Lands Access
W, G.., Dre<m,, Rhp Unsay Pam a Mrealmn
swnonam.ePawGM:.nw,aldngmn
Program Grant replacing the Swauk Creek bridge on Liberty Road. This load limiting
wI Qapnla, I'I. PoM Rmdml aaoun airs eo 5owd 4menway,ul
Wen CMRWM (X). NagC "E dve
bridge currently prohibits implementation of the US Forest Services' Swauk Pine
Kmy [rag Deputy DAenor. Washinyor. Rognm.
nMwdea,esa sooaY
Project.
Xxl fo,yapc. MaragerdlmplemaR�ons,Thpmm� Reueen
Mphle Wes Rpaumsorkty
rviMry Rm,M;ALCpmn;adoeraPubk,arq;
The Okanogan -Wenatchee National Forest has been working towards restoration
Wash;p ,stare DepM,,t Cq arvamal ReWurces
AY,Reinger,EommMryOreMahsagwn
efforts near Liberty, WA since 2010, when insect outbreaks killed large numbers of
o o n p°C °al"ratk w n"� G"
standing trees. The concentration of standing dead timber, occurring near the Wildland
WMh'e,ym Swe N,M d k<realbn Commkvm
MmAHdeman.OwrR2 Copper RvgeP„m:xAq,0.Mp M[mawl
Urban Interface of the town of Liberty, poses a high risk of severe wildfire that could
Angell An K«mm.allr w,aretr. wlmwik Mr.
cnr,,,a,,,„p,,GLm<CmR„Eng;n«,,c<,En�,l<aM1
easily cause massive damage to property and habitat. The Swauk Pine Project reduces
AnaewMMAaxapLwlewnae:'
the risk of wildfires b harvesting the dead trees and masticating other hazardous fuels.
w,neingsbury emeMMwasnMglo¢lnc.
Y g g
Naank
The Mountains to Sound Greenway Trust has partnered with the OWNF and the WA.
Y
USgAiLWa,,-A sWvseme
us=SMLeae--SwOOalmkrvaWMl roma
”"etNK r, R.WEmdm'meM,[G """t
Department of Natural Resources to conduct cultural resources analysis on the insect-
h,MLGossd "Gv p
Xm Xnrdgarwrklaa°nah Alps,ra;hcw
kill area, prior to this work. It is a highly collaborative project that will reestablish
P g Y P 1
r.np,<u,i Exmmrve ol,mn,ErergrmnMounumMx MMNe
Da,a,y de,* M'smA
natural fire regimes, reducing wildfire management costs and better protecting the
Shame Linton, NaranMCOn ftam SLCWWs
pM ne Asv,w(Gm<Mlcanwo, m E.00 m L
forest and nearby communities. However, the Project cannot be fully implemented
ROyam k rA[n RgM Sall EneryY
EXMCN^w .msm 6leervx0Tr ZE sas,e>,wa
without replacement of the Swauk Creek bridge.
ROM[ AbneNM.!mXR U m.]81 PW am,me BmiN compar,e
W40n hl` a Y. A.(; l*`WI dCEO, saidG,OOIW
" All w dd W° ,aTMneparMhm,
In 2018, Kittitas County Department of Public Works completed an update to its
VlaW, %sn SWI<D[padM1meM M Tramm,'JIGn
Gw: NesMrd,DBecmr.MkmwhRpnremenl
twenty-year Transportation Plan which identified a $100 million funding shortfall for
Man Nmeon, Me',tlmailod; Lmm Prefervatan AUM aim
, s0'Xeae.PaddCNWSt aaNinpW aw..
significant infrastructure needs. Without federal support for replacing the Swauk Creek
Ax kan WMM ..
DaaWft RA.D cx..7he,lw FiAtOkL W
Bridge, other local priorities will take precedence, and the bridge will remain load
Alga Pa,r M1, Aas WCean aAaa Afsry
CdkgeaEmironmeM UawrWYOEw,ahMym
limited. A pending timber sale is now on indefinite hold as the deficient bridge cannot
Aias ROeia. NO!eLeAssss.,Ttla y*Assst
rnanFa M DN .o,Can< � Prn;ML S .Mb
support harvest equipment, or emergency response vehicles. This endangers not only
lance fay. lanred AWRam w, C Wp Maas A Publshinq
WW,a,;rymp
the work and investments made by the Greenway and other partners, but also the
Am RaaMNam rl. Ftin qY d smo, Manaq:y Dveclp.
NEAFELWDLLC
community of Liberty, and significant recreational infrastructure.
MkS R^
AAms
eAwmla
wX SahrmYThe Moon lneer Walaan Alpine Gab
.rsNla,Wn,Eawn,IwMm<1m,waa,lyM,T„NA::«mlm,
For these reasons, and in deference to the thousands of Washingtonians who enjoy
Al SmNL PW .."m,Cca LLP
DaesiMM„<Y,nLR<,i,<,,L�<Pmm<MCNMYNaI
year-round camping, hiking, jeeping, horseback riding, hunting and fishing in the Swauk
area, we wholeheartedly support Kittitas County's request for FLAP funding to replace
"°�dyBB ;tango mlp,W PU A
the Swauk Creek Bridge.
xmr,npmaAaelwna�,�omrm.auwMhayml
g
Leah Trd.Orymbaedut kdpmarce Mawgn,
City Bagel OBkexmk
Sincere)Y
MBM WJlims IXL xperv;w,,
,
USES OLarogamWerum�ee HNional fun[
M1MwMbms Re:ked. former SmbY ePrevdnL
H
Yn ,NWA0
lo<'YOM.R!Mpl Royam Wafter.0
Cz,mssn W uMmk Va1kY YMI[W fi h (Y C¢M¢r
ad Clwtmn
u+e Cw+nR�A4ndn
MTSG REENWAY.O RG 2701 FIRSTAVENUE SUITE 240 SEATTLE• WA 981211206.382.5565 I INFO@MTSGREENWAY.ORG
C,
Jon Hoekstra
Executive Director
Mountain to Sound Greenway Trust
(206)890-1474
ion. hoekstra@mtsereenway.ore
and
Nicky Pas
t-4 4
Upper Yakima Basin Community Coordinator
Mountains to Sound Greenway Trust
(509)656-4073
nicky.pasi@mtsgreenway.org
ak APASH Sustainable Forest
Collaborative December 2, 2020
Mark R. Cook, Director
Kittitas County Department of Public Works
411 North Ruby Street, Suite 1
Ellensburg, WA 98926
Dear Mr. Cook,
This letter expresses the support of the Tapash Sustainable Forest Collaborative for the Kittitas
County Department of Public Works submittal of a 2021-2023 Federal Lands Access Program
(FLAP) grant to replace the Kittitas County owned Swauk Creek bridge on Liberty Road.
The Tapash Sustainable Forest Collaborative has a purpose to improve ecosystem health and natural
functions of the eastern Cascades landscape through the use of the best available science,
community input and adaptive management. We pursue this purpose through a collaborative
process that engages five entities' and other associated stakeholders that have a diverse expertise in
forest restoration, management, and protection. This combination of partners in the Collaborative
creates a unique mix of public, non-profit, and tribal land managers working together to create
ecologically sustainable healthy forests on the east side of the Cascades.
A century or more of wildfire suppression, intensive harvesting, grazing, and mining have resulted in
widespread degradation of terrestrial and aquatic habitats and made the Okanogan Wenatchee
National Forest (OWNF) susceptible to uncharacteristic fire, insect, and disease outbreaks. As a
result, there is a need for restoration efforts and stakeholder engagement across the landscape. Time
is critical, and the size and scale of the forest restoration need is growing.
In response, the Tapash Sustainable Forest Collaborative utilizes a collaborative process to move
forward priority forest restoration projects on the OWNF. The Swauk Pine Priority Project area was
identified in response to the high risk of habitat loss resulting from high fire risk, the critical use of
the watershed for various fish species including Endangered Species Act (ESA) listed Steelhead,
forest management, providing access to popular recreation areas, and to the high ratio of Wildland
Urban Interface associated with the Town of Liberty. The purpose of the Swauk Pine Project is to
improve resilience to wildfires and other disturbances by returning the forested landscape to a state
that is within or closer to the historic range of variability, and improve the resilience and function of
aquatic systems that have been degraded by previous and ongoing human actions. The Swank Basin
Wildfire Protection Plan outlines efforts to reduce wildfire risk, reestablish natural fire regimes,
reducing wildfire management costs and better protecting late successional and old forest structure.
The FLAP grant proposal supports efforts outlined in the Swank Basin Wildfire Protection Plan,
which cannot be fully implemented without the funds for design and replacement of the County's
load limiting bridge on Swank Creek. The bridge has been found to be structurally deficient and
currently limits access to the Liberty and Williams Creek Watershed without replacement. The load
' The Nature Conservancy of Washington State, the Washington Department of Fish and Wildlife, Washington
Department of Natural Resources, the U.S. Forest Service, and the Yakama Nation.
atTAPASH Sustainable Forest
Collaborative
December 2, 2020
limited bridge also restricts access of many fixe -life -safety response vehicles from serving the area,
and replacing the deficient bridge will allow access to emergency response vehicle, thus supporting
numerous recreational uses in the area. The development of a new bridge design will accommodate
watershed function restoration critical to a healthy aquatic ecosystem and is supported by the
Tapash Sustainable Forest Collaborative objectives for the landscape. We hope you will advance this
critical FLAP grant.
Sincerely,
Ross Huffman,
Tapash Sustainable Forest Collaborative Chair