HomeMy WebLinkAbout2020-11-23-minutes-public-works-study-sessionKITTITAS COUNTY COMMISSIONERS
Public Works Study Session
Regular Meeting
Monday November 23, 2020 -1:30 PM
Webex
1. Call to Order
2. Request to Authorize Chair's Signature on Joint Endorsement Form Supporting the Federal
Lands Access Program Grant for Liberty Road - Swauk Creek Bridge Replacement Project
3. Hyak Maintenance Facility
4. Sparks Road Quit Claim Deed
5. Coleman Creek and Vantage Highway Update
6. Other business
7. Adjourn
Created on 11/19/2020 2:51:04 PM
KITTITAS COUNTY
PUBLIC WORKS STUDY SESSION MINUTES
Webex
Regular Meeting
MONDAY 1:30 PM NOVEMBER 23, 2020
Board members present: Vice -Chairman Laura Osiadacz, Commissioner
Cory Wright
Others: Mark Cook, Candie Leader, Josh Fredrickson, Public Works; Dan
Carlson, Jessica Miller, Mike Flory, Bridget Pechtel, Pat Nicholson,
Ryan McAllister, Community Development Services; and Two (2) Members
of the Public
At 1:42 pm Vice -Chairman Laura Osiadacz opened the Public Works Study
Session.
Mark Cook requested to remove Item #5 from the agenda.
REQUEST TO AUTHORIZE CHAIR'S SIGNATURE ON JOINT ENDORSEMENT FORM
SUPPORTING THE FEDERAL LANDS ACCESS PROGRAM GRANT FOR LIBERTY ROAD -
SWAUK CREEK BRIDGE REPLACEMENT PROJECT
Mark Cook gave background on the success Public Works has had in
securing grant funding for projects through the Federal Lands Access
Program. Mark Cook continued stating that last year staff worked
with the Forest Service on a proposal to support a timber sale in the
Liberty area however, the bridge crossing Swauk Creek is currently
load rated. Mark Cook added that this grant program is a valid
funding source to get the current bridge replaced and would allow for
the Forest Service to continue with the restoration plan that began
back in 2012. Mark Cook stated that staff is seeking the Chair's
signature on the Joint Endorsement Form to include in the grant
application package. Discussion was held. Commissioner Cory Wright
made a motion to approve the Chair's Signature on the Joint
Endorsement Form supporting the Federal Lands Access Program Grant
for Liberty Road - Swauk Creek Bridge Replacement Project. Vice -
Chairman Laura Osiadacz seconded the motion. Motion passed 2-0.
HYAK MAINTENANCE FACILITY
Mark Cook gave background on the progress being made by Snoqualmie
Pass Utility District on upgrading their wastewater treatment
facility, the approval of their franchise and the expansion of the
company. Mark Cook continued that the services Public Works provides
in the area eventually slowing down and the issues being faced by
Public Works with snow removal it appears that vacating the current
building shared with SPUD in the Hyak area is a possibility. SPUD
has asked staff to provide a cost for the building to be purchased
2020-11-23 MINUTES
and utilized for office space and possibly enter into an agreement to
allow for Public Works to continue storing snow removal equipment
until a decision is made on continued snow removal operations in the
area. Discussion was held. Staff was directed to conduct a cost
evaluation for the building.
SPARKS ROAD QUIT CLAIM DEED
Mark Cook gave background on the next phase of the Washington State
Department of Transportation (WSDOT) I-90 Project and stated that
WSDOT and the County had amended an agreement under Resolution 2020-
126 allowing for the conveyance of a portion of Sparks Road. Mark
Cook continued that after review of the legal description on the Quit
Claim Deed staff noticed WSDOT of corrections to be made. Mark Cook
added that WSDOT declined to use the corrections suggested and that
no further discussions were to be had on the issue. Mark Cook
commented that staff would like to move forward with the document as
proposed by WSDOT and complete the transfer. Discussion was held.
Staff was directed to bring the Quit Claim Deed forward at an
upcoming agenda session for consideration.
COLEMAN CREEK AT VANTAGE HIGHWAY UPDATE
This item was removed from the agenda.
Meeting adjourned at 2:06 pm.
2020-11-23 MINUTES
KITTITAS COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Laura Osiadacz, Vice -Chairman
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMNHSSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: November 23, 2020
TOPIC: 2020 Washington Federal Lands Access Program Grant for Liberty Road
Swank Creek Bridge Replacement
ACTION REQUESTED: Authorize the Chair's Signature on Joint Endorsement
for support of project
LEAD STAFF:
Mark R. Cook
RECOMMENDATION:
Authorize the Chair's Signature on Joint Endorsement showing support of the project.
BRIEFING SUMMARY:
• Liberty Road Bridge at Swauk Creek is load limited.
• The United States Forest Service is unable to move forward with a pending timber
sale and implementation of its 2012 Swauk Pine Project (timber sale and stream
restoration).
• PW does not have sufficient local funding for replacing the bridge.
• PW does not have sufficient resources allowing a multi-year deployment of a
temporary bridge.
BACKGROUND:
During late 2019 and early 2020, PW worked with USFS staff attempting to solve access
restrictions to the Liberty area. The load limited bridge crossing Swauk Creek is
thwarting attempts to open a timber sale that is much needed addressing the concern for
cataphoric wildland fires in the Liberty area. A long-range stream and forest restoration
plan (Swauk Pine Project — USFS) is not able to move forward in the absence of bridge
replacement.
PW desires submitting a Federal Highway Administration, "Federal Lands Access
Program" grant replacing the Swauk Creek bridge at Liberty Road. The grant application
requires Board of County Commission support. The USFS and others are being pursued
for letters of support.
FISCAL IMPACTS:
Preliminary cost estimates for replacing the load limited bridge exceed $2.5 million.
ATTACHMENTS:
Exhibit 1: Joint Endorsement
Page 1 of 2
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
EXHIBIT 1: JOINT ENDORSEMENT
Page 2 of 2
PUBLIC WORKS BOARD OF COUNTY CONMUSSIONERS WORK SESSION STAFF REPORT
2020 Washington Federal Lands Access Program
JOINT ENDORSEMENT - This project is supported and endorsed by
(add agency endorsements as needed)
Project Name
Liberty Road - Swauk Creek Bridge Replacement
Federal Land Agency lies)
Bureau of Land Management
Federal Land Unit Manager's Name
Title
District Manager
Signature
Date
Email Address
Telephone
Point of Contact
Title
Email Address
Telephone
State, County, Local, or Tribal
Government
Kittitas County
Agency Official's Name
Brett Wachsmith
Title
Commissioner
Signature
Date
Email Address
brett.wachsmith@co.kittitas.wa.us
Telephone
509-962-7508
Point of Contact
Mark Cook
Title
Public Works Director
Email Address
mark.cook@co.kittitas.wa.us
Telephone
509-962-7692
Signatures are required for BOTH the Federal Land Management Agency being accessed and the State, County, Local or Tribal
Government. Proposals that do not have the appropriate signature will NOT be eligible for consideration.
2020 Washington (Federal Lands Access Program
JOINT ENDORSEMENT - This project is supported and endorsed by
(add agency endorsements as needed)
Project Name
Liberty Road - Swauk Creek Bridge Replacement
Federal Land Agency lies)
Okanogan-Wenatchee National Forest
Federal Land Unit Manager's Name
Kristin Bail
Title
Forest Supervisor
Signature
Date
Email Address
Kristin.Bail@usda.gov
Telephone
509-664-9200
Point of Contact
Title
Email Address
Telephone
State, County, Local, or Tribal
Government
Kittitas County
Agency Official's Name
Brett Wachsmith
Title
Commissioner
Signature
Date
Email Address
brett.wachsmith@co.kittitas.wa.us
Telephone
509-962-7508
Point of Contact
Mark Cook
Title
Public Works Director
Email Address
mark.cook@co.kittitas.wa.us
Telephone
509-962-7692
Signatures are required for BOTH the Federal Land ManagementAgency being accessed and the State, County, Local orTribol
Government. Proposals that do not have the appropriate signature will NOT be eligible for consideration.
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: November 23, 2020
TOPIC: HYAK Maintenance Facility
ACTION REQUESTED: Support Evaluating a Sale to SPUD
LEAD STAFF:
Mark R. Cook
RECOMMENDATION:
Support staff s evaluation of sale of our interest in the joint Hyak maintenance facility
with Snoqualmie Pass Utility District (SPUD) and authorize the Public Works Director to
begin negotiations with SPUD. PW will return to the Board prior to finalizing any sale.
BRIEFING SUMMARY:
• SPUD desires buying our interest in the joint maintenance facility in Hyak.
• Sale must consider offsetting storage of our grader and snow blower.
• Increasing development in Hyak will eventually require trucking of snow that
Public Works cannot support.
• Eventual abandonment of our presence in Hyak seems inevitable.
BACKGROUND:
SPUD's wastewater expansion is driving the conversation surrounding our joint
maintenance facility in Hyak. As their operation expands, they will require additional
operational space. The same expansion favoring SPUD is working against PW
snowplow capabilities. At the current development rate in Hyak, PW will be unable to
plow and blow roadway snow within the next three to four years. Once trucking of snow
becomes reality, we will no longer require our space in the joint maintenance facility with
SPUD.
DISCUSSION:
Now is the time to begin planning our withdrawal from snowplow operations in Hyak.
SPUD can use the entire facility and its location is better suited for an eventual office
facility than for our use storing our grader and snow blower. PW is discussing options
with SPUD including sale and rent back or sale and accept storage in the pending new
wastewater operations building proposed behind the current maintenance shop. These
options allow SPUD control over the shop recognizing the limited time remaining for PW
maintenance operations in Hyak. The logistics of trucking snow are such that there
appears no path forward for PW. Area streams designated for Bull Trout habitat preclude
local disposal of roadway snow and trucking to lower elevations is the likely outcome.
Page 1 of 3
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
Not only is the expense prohibitive, the service level will drop significantly, and we do
not anticipate being able to keep with larger snowfall events. This reality is positions
SPUD well for shop acquisition.
FISCAL IMPACTS:
PW is estimating the cost of shop recovery expense at $244,204.64 (ER&R Fund).
ATTACHMENTS:
Exhibit 1: Financial Evaluation
Page 2 of 3
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
EXHIBIT 1: FINANCIAL EVALUATION
Page 3 of 3
PUBLIC WORKS BOARD OF COUNTY CONMSSIONERS WORK SESSION STAFF REPORT
Hyak Joint Facility:
Land Purchase
Building
Parking Lot
51,480.50
203,536.57
50,829.17
305,846.24
Depr. To 12/2020 42,386.98
263,459.26
Spud Reserve (19,254.62)
244,204.64
Allocation for Building/Parking Lot
Cost
Improvements
Building
PE -Survey
3,317.58
1,658.79
1,658.79
PE -Design
4,265.98
-
4,265.98
PE -Plans, Permits
3,779.03
-
3,779.03
CE -Survey
4,924.61
-
4,924.61
CE -Design
137.83
-
137.83
CE -Inspection
248.63
-
248.63
CE -Contract Admin
4,427.80
-
4,427.80
Interlocal Admin
219.72
-
219.72
Land Site Preparation
23,339.20
23,339.20
-
Building Contract
179,472.24
-
179,472.24
Propane Tank
3,923.23
-
3,923.23
PE -Parking Lot
321.16
321.16
-
CE -Parking Lot
35.42
35.42
-
Parking Lot Paving
13,196.39
13,196.39
-
Parking Lot Base
12,278.22
12,278.22
-
Interior
478.73
-
478.73
254,365.77
50,829.18
203,536.59
51,480.50
203,536.57
50,829.17
305,846.24
Depr. To 12/2020 42,386.98
263,459.26
Spud Reserve (19,254.62)
244,204.64
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: November 23, 2020
TOPIC: Sparks Road Quit Claim Deed
ACTION REQUESTED: Direct Staff to Prepare Enabling Documents Authorizing
the Chairs' Signature on a Quit Claim Deed to WSDOT
Supporting the Current I-90 Widening Project
LEAD STAFF:
Mark R. Cook.
RECOMMENDATION:
Direct staff to prepare enabling documents conveying a portion of Sparks Road to
Washington State Department of Transportation (WSDOT).
BRIEFING SUMMARY:
• Resolution 2020-126 amends an agreement with WSDOT allowing for the
conveyance of real property (a portion of Sparks Road).
• Staff is preparing enabling documentation allowing Board conveyance of a
portion of Sparks Road.
BACKGROUND:
WSDOT is starting the next phase of I-90 widening following construction delays related
to the COVID-19 pandemic. PW has previously briefed the Board and the Board
amended its agreement with WSDOT in Resolution 2020-126. A quit claim deed from
the County to WSDOT is now required to convey a portion of Sparks Road.
DISCUSSION:
The portion of Sparks Road being impacted results from WSDOT's realignment of
westbound I-90 traffic. While the legal description is not something that the Director or
County Surveyor readily accept, we are begin told that no change to the legal description
will be entertained by WSDOT. That said, we both believe the Board should sign the
requested Sparks Road Quit Claim deed and allow WSDOT to get on with it.
FISCAL IMPACTS:
None.
ATTACHMENTS:
Exhibit 1: Map of area.
Page 1 of 2
PUBLIC WORKS BOARD OF COUNTY COMNUSSIONERS WORK SESSION STAFF REPORT
Page 2 of 2
PUBLIC WORKS BOARD OF COUNTY CON IISSIONERS WORK SESSION STAFF REPORT
i _ �f3''ty�g at:[a ZO s � E Q g �i `= •:
�O' �gyG6 e,,.{e amli
p a � h � °• _ n 2Rm t� s� I -
%� t'n is
wg
ca \:�•�\��\ a fur €� Y A3
ziq
go
n ',9 �$P�\t �' \\ ,��\��5.\� a4S� �g a�u ami p '3� ��• ��
� w: \`\`�., \E +:�i' 144R„ � \ 't•� \\ x. �¢ r N m > i3 ! {rl S� ..
io•vvm `\ s. �`\C`/b}ff � \ y �\ \ , \ \\ (�''`a a r-Y'F' p
n.. \\ri F` n• \ s \ ki \ vi ier is
„ 1 `
,\
•m9nw^w°=�jk= �� i �'a 8� e+ i ,\\ n I � wz FFP � y
aa!yR�R8 2i �i -chg
IF-
Is*
70
.,°.vs
V4 Mb
yy .lam
ILI
4 � r
g / 1
Owan
g�v�„•.
rnb1��
0<_a� a l R, \
�^M.i 9evo•°O � m I �( I�` 't
En�W•w�?� q/ � �O`}rv_�'vn b �iF m.nm� �� a�i�,�a
o �t ro •rtva dJ _o m� n71 St
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS — BOARD OF COUNTY COMNHSSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: November 23, 2020
TOPIC: Coleman Creek at Vantage Highway Update
ACTION REQUESTED: Support Staff's Decision Rejecting Asphalt
LEAD STAFF:
Mark R. Cook and Joshua Fredrickson.
RECOMMENDATION:
Reject unsuitable asphalt paving at Coleman Creek on Vantage Highway.
BRIEFING SUMMARY:
• Fish barrier removal project on Coleman Creek at Vantage Highway is
substantially complete.
• Poor paving without 2% cross -slope is being rejected.
• County is looking for a remedy from the contractor.
BACKGROUND:
During recent final paving at Coleman Creek Fish Barrier Removal Project (Vantage
Highway); the contractor was directed to shape roadway cross -slope ahead of paving.
The contractor refused. The road's inconsistent cross -slope now provides an
unacceptable rough ride. The Contractor is burdened with providing survey control. The
County contract included a bid item for contractor survey control.
DISCUSSION:
Public Works (PW) has noticed the contractor (Belsaas and Smith, Inc.) of our pending
rejection of asphalt paving. PW is awaiting a proposal from the contractor addressing the
pavement deficiency. PW is not paying for any asphalt in the interim. PW is allowing
the contractor to propose a remedy. Anticipated options to remedy the deficient
pavement include: grinding the top layer and repaving with grade control, or removing
all asphalt and replacing with grade control. Failure on the part of the contractor to
provide a suitable correction may result in additional action including non-payment for
pavement work or suspend the contractor for a three year period from doing any further
County construction work.
FISCAL IMPACTS:
Contract paving is bid at: $58,500.00. PW estimates that grinding and re -paving the top
layer of asphalt will likely cost approximately $27,000.00.
Page 1 of 4
PUBLIC WORKS BOARD OF COUNTY CONMSSIONERS WORK SESSION STAFF REPORT
ATTACIMENTS:
Exhibit 1: Roadway plan depicting paving limits.
Exhibit 2: Roadway plan showing required cross -slope.
Page 2 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
EXIIIBIT 1: PAVING LIMITS
Page 3 of 4
PUBLIC WORKS BOARD OF COUNTY CONIMISSIONERS WORK SESSION STAFF REPORT
8
W�iw ervnJ:IgS3'I:AS'1 HM131 y1 J i.. � �i!�n, v i
�p
i.
�36if55i�u-S-�n
z
-
d '
S
vtesst • v�
IT
i
l HaS9t• moi.
' 96-iStLb:� YA ?10
W�iw ervnJ:IgS3'I:AS'1 HM131 y1 J i.. � �i!�n, v i
�p
EXHIBIT 2: REQUIRED CROSS -SLOPE
Page 4 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT