HomeMy WebLinkAboutResolution_Prospectus Hungry JctKITTITAS COUNTY
Board of County Commissioners
AGENDA STAFF REPORT
AGENDA DATE: August 18, 2020
ACTION REQUESTED: Request to approve a Resolution authorizing the Chair's signature on
the County Road Administration Board Rural Arterial Program
Project Final Prospectus for the biennium 2021 — 2023 for the Hungry
Junction Road Widening Project.
BACKGROUND: The Rural Arterial Program (RAP) is a biennial road and bridge
reconstruction funding program in which counties compete for Rural
Arterial Trust Account (RATA) funds within their respective regions.
In February 2020, Public Works submitted a Rural Arterial Program
Preliminary Prospectus for widening and improving Hungry Junction
Road from MP 0.00 (Highway 97) to MP 1.74 (Reecer Creek Road).
INTERACTION: The Department of Public Works is requesting the County Road
Administration Board Rural Arterial Program participate in funding
for said project.
RECOMMENDATION: Approve the Resolution authorizing the Chair's signature on the
County Road Administration Board Rural Arterial Program Project
Final Prospectus for the biennium 2021 — 2023 for the Hungry
Junction Road Widening Project.
HANDLING: Return one original to Public Works
ATTACHMENTS: Resolution; Prospectus
LEAD STAFF: Mark Cook, Director
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2020 -
AUTHORIZING CHAIR SIGNATURE ON THE COUNTY ROAD
ADMINISTRATION BOARD RURAL ARTERIAL PROGRAM PROJECT
FINAL PROSPECTUS FOR BIENNIUM 2021-2023 FOR THE HUNGRY
JUNCTION ROAD WIDENING PROJECT
WHEREAS: The Department of Public Works is proposing to widen and improve
Hungry Junction Road from MP 0.00 — MP 1.74; and
WHEREAS: The Department of Public Works submitted a preliminary prospectus to
the County Road Administration Board in February of 2020, and
WHEREAS: The Department of Public Works is competing for Rural Arterial Trust
Account (RATA) funds within the region; and
WHEREAS: This construction project is included on the County's Six Year
Transportation Improvement Plan;
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in
the best interest of the public, does hereby approve the Chair's signature
on the County Road Administration Board Rural Arterial Program Project
Final Prospectus for Biennium 2021-2023 for the Hungry Junction Road
Widening Project.
DATED on this 18th day of August 2020, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
Laura Osiadacz, Vice -Chairman
Cory Wright, Commissioner
STATE OF WASHINGTON - COUNTY ROAD ADMINISTRATION BOARD
RURAL ARTERIAL PROGRAM
FINAL PROSPECTUS
Biennium: 2021 - 2023
Region: SE County: Kittitas
IDENTIFICATION
State Legislative District: 13 Six -Year T.I.P. Priority No: 17 Total Points: 91.37
Road Number(s) I Road Name(s) FFC(s) I TRC(s) I BMP(s) I EMP(s)
31510 Hungry Junction Road 08 T3 1 0.0001 1.740
PROJECT TYPE
Project Type: 313 - Rehabilitate, Resurface, Restore
DESCRIPTION OF PROPOSED IMPROVEMENTS - Attach Rating Worksheets
Roadway Structural Section, or Bridge Condition:
The existing BST pavement is narrow with areas of significant longitudinal cracking, and settling
ever the top of drainage structures. It will be removed and replaced with 9 inches of CSBC and 0.30
foot of HMA asphalt.
Horizontal Alignment:
There will be no effect on the horizontal alignment.
vcniwi rwiynnronr.
There are four vertical curves that need to be corrected to meet safe sight stopping distance design
standards for the posted speed limit.
vviun I.
The existing roadway has two - 10 foot lanes with little to no shoulder, the roadway will be widened
to 12 foot lanes with 2 foot shoulders.
Dther: Clear Zone, Slopes, Guardrail, Illumination, sianals etc.:
The clear zone will be improved by removing or relocating above ground obstacles, beveling culvert
ends, and installing guardrail or flattening slopes where warranted.
STIMATED FUNDING AND TIMING Estimated Year
Phase Est Total Cost RATA Amount Start End
Design/Prelim. Engr.
$461,000
$414,900
Mar -22
Jun -23
Right of Way
$100,000
$90,000
Sep -22
Jun -23
Construction
$3,474,000
$3,126,600
Sep -23
Dec -24
TOTAL
$4,035,000
$3,631,500
Schedule of CRAB reimbursements for
Construction will be or dependent on Pro ect
SPECIAL CONSIDERATIONS THAT MAY AFFECT PROJECT SCHEDULE:
v❑Wetlands Z✓ NMFS ❑✓ R.O.W. ❑./ Shorelines ❑✓ USFWS ❑BIA ✓ZHPA F -IRR F/ USACE
❑✓ WDFW Q✓ Cultrual (Hist. Arch. Palen.) Tied (Other agency work) Other
LOCAL PROJECT APPROVAL
RAP Project Prospectus prepared under the supervision of:
RAP Project Prospectus submitted to CRAB with the approval of:
vol 4Ze
Signature - County Engineer / Date
Signature of Chair of the Board of County
Commissioners or County Executive / Date