BACKGROUND: In early December 2019, significant roadway deterioration
became apparent along the entire length of Bullfrog Road.
Staff has filled nearly 100 potholes in the past several
months and recently the Board reduced the speed limit to
35 MPH along the entire roadway — minimizing ongoing
damage to vehicles. Public Works anticipates grinding
(milling) the existing roadway surface and then placing a
new two-inch asphalt overlay along the entire length of
Bullfrog Road.
INTERACTION: Public Works.
RECOMMENDATION: Approve the Resolution to authorize the addition of
Bullfrog Road Pavement Repaving to the 2020 Annual
Construction Program and assign a County Road Project
Number.
HANDLING: Return one original to Public Works
ATTACHMENTS: Resolution
LEAD STAFF: Mark R. Cook, Director
RESOLUTION NO.
BEFORE THE BOARD OF COUNTY COMMISSIONERS OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter
of initiating a county road project designated as:
CRP NO: 300-20 JOB NO: RC2002-ST
IT IS HEREBY RESOLVED Bullfrog Road #92275 MP 0.00-2.70
Bullfrog Road is currently experiencing significant pavement failure creating a hazard for the traveling public. Work will
include milling the existing roadway and overlaying with hot mix asphalt to provide a new roadway surface for Bullfrog
Road.
ARTERIAL ❑
ACCESS E
This project is hereby declared to be a public necessity and the Director of Public Works acting as the County Engineer is hereby
ordered and authorized to report and proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070).
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the Director of
Public Works' estimate, is hereby made in the amounts and for the purposes shown:
PURPOSE
AMOUNT
TOTALS
PRELIMINARY ENGINEERING
$ 200,000
CONSTRUCTION ENGINEERING
$ 25,000
-
RIGHT-OF-WAY ACQUISITION
$
SUB -TOTAL
$ 250,000
County Forces CONSTRUCTION
$
CONTRACT CONSTRUCTION
$ 1,300,000
SUB -TOTAL
$ 1,300,000
TOTAL PROJECT COST
$ 1,525,000
GRANT OR OTHER FUNDS
$ 650,000
Grant Source: STBG
TOTAL COUNTY ROAD FUND ALLOCATION
lks 925,000
1�
Mark Cook, P.E.
Interim County Engineer
❑ THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED 2020 ANNUAL ROAD PROGRAM AS
ITEM NO.
® THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM PROJECT #11
IN ACCORDANCE WITH RCW 36.81.130
IT IS FURTHER RESOLVED THAT:
E THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ.
❑ THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN ACCORDANCE WITH RCW 36.77.065 AND
WAC 136-18.
ADOPTED this day of , 2020. Attest:
BOARD OF COUNTY COMMISSIONERS Clerk of the Board
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chair Laura Osiadacz, Vice Chair Cory Wright, Commissioner
g:\base\formsleng\crp-frm 1/28/2020