HomeMy WebLinkAboutResolution_Vantage Hwy ProspectusKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: February 4, 2020
ACTION REQUESTED: Approve the Resolution Authorizing the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the
Vantage Highway Project, CRP 298-19.
BACKGROUND: On December 19, 2019, Kittitas County Public Works was
advised by Washington State Department of Transportation
(WSDOT) that our Vantage Highway Project was selected
to receive funding through the Highway Safety
Improvement Program (HSIP) for the installation of
guardrail.
This project will be combined with an asphalt overlay that
will happen concurrently in the same location with funding
through the Rural Arterial Program.
This Project Prospectus covers the Federal Funding portion
for the (HSIP) design phase and needs to be approved by
WSDOT Local Programs. The approval needs to happen so
WSDOT can evaluate the need to assign Kittitas County an
Underutilized Disadvantaged Business Enterprise (UDBE)
participation commitment goal prior to advertisement for
design services.
Public Works is preparing to solicit for design services in
March of 2020. This requires the Local Agency Federal
Aid Project Prospectus to be signed and approved by the
Chair of the BOCC.
INTERACTION: Public Works
RECOMMENDATION: Approve the Resolution Authorizing the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the
Vantage Highway Project, CRP 298-19.
HANDLING: Return two (2) originals to Public Works
ATTACHMENTS: Resolution, Local Agency Federal Aid Project Prospectus
LEAD STAFF: Mark Cook, Director
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2020 -
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY
FEDERAL AID PROJECT PROSPECTUS FOR THE VANTAGE HIGHWAY
PROJECT, CRP 298-19
WHEREAS: The Vantage Highway Project Federal funds (HSIP) will be used to install
and upgrade non-compliant guardrail, and protect hazardous slopes along
Vantage Highway MP 21.25 —MP 27.51; and
WHEREAS: This project will be tied with a Rural Arterial Program project, which will
repair and provide an asphalt overlay on all lanes of Vantage Highway to
build surface depth and structural capacity at the same location; and
WHEREAS: In preparation to advertise the project for design in the spring of 2020
Public Works is requesting the Washington State Department of
Transportation to release the Federal Funds for design; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the
Chair acknowledging the project has been reviewed and is consistent with
the agency's comprehensive plan for community development;
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in
the best interest of the public, does hereby approve the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the Vantage
Highway Project, CRP 298-19.
DATED on this 4th day of February, 2020, at Ellensburg, Washington.
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
Laura Osiadacz, Vice -Chairman
Cory Wright, Commissioner
Adm
Wash5ngton State
TAf Depatrtment of Transportation
Local Agency Federal Aid
Project Prospectus
DOT Form 140-101 Page 1
Revised 04/2015 Previous Editions Obsolete
Prefix
Route
( )
Date
1/16/2020
Federal Aid
Project N umber
HSIP
2020
DUNS Number
01-020-2547
Local Agency
CRP 298-19, RC 1913
WSDO y
Federal Employer
91-601349
Project Number
\ Use Only
\
Tax ID Number
Agency
CAAgency
Federal Program Title
Kittitas County
❑✓ Yes ❑ No
7/20.205E] Other
Project Title
Start Latitude N 46057'31.23"
Start Longitude W 120° 7'22.99"
Vantage Highway
End Latitude N 46°56'56.04"
End Longitude W 119°59'44.22"
Project Termini From -To
Nearest City Name
Project Zip Code (+4)
21.25 27.51
Ellensburg
98950-AO21
Begin Mile Post
End Mile Post
Length of Project
Award Type
21.25
27.51
6.26 Miles
❑✓ Local ❑ Local Forces ❑ State ❑ Railroad
Route ID
Begin Mile Point
End Mile Point
City Number
Coun�Nmbe,
Name
21.25
27.51
19tas
WSDOT Region
Legislative District(s)
Congressional District(s)
Urban Area Number
South Central Region 1
13
8
Total
Local Agency
Federal Funds
Phase Start
Phase
Estimated Cost
Funding
Date
Nearest Hundred Dollar
Nearest Hundred Dollar
Nearest Hundred Dollar
Month Year
P. E.
355,343
252,943
102,400
March 2020
RNV
0
0
0
Const.
3,104,887
2,052,687
1,052,200
April 2021
Total
13,460,230
12,305,630
1,154,600
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width
Number of Lanes
MP 21.25-23.36 = 38', MP 23.36-27.51=26'
MP 21.25-23.36 = 3 lanes, MP 23.36-27.51 = 2 lanes
The segment has non compliant guardrail, and many hazardous slopes. This segment shows HMA distress in
the form of transverse and longitudinal cracking, with significant annual maintenance and repair costs.
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
HMA repair and an asphalt overlay on all lanes in an attempt to build surface depth and structural capacity.
Federal funds will be used to install/upgrade guardrail.
Local Agency Contact Person
Title
Phone
Darren Case
Construction Manager
(509)962-7523
Mailing Address
City
State
Zip Code
411 N Ruby St, Suite 1
Elle burg
WA
98926
By
Approving Authority
Project Prospectus
Title County Engineer/Public Works Director
Da? 'AF-
DOT Form 140-101 Page 1
Revised 04/2015 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County
Vantage Highway
1/16/2020
Type of Proposed Work
Project Type (Check all that Apply)
Roadway Width
Number of Lanes
❑ New Construction ❑ Path / Trail
❑ 3-R
26-38
2-3
❑✓ Reconstruction ❑ Pedestrian / Facilities
❑ 2-R
❑ Railroad ❑ Parking
❑ Other
❑ Bridge
Geometric Design Data
Description
Through Route
Crossroad
❑ Principal Arterial
❑ Principal Arterial
Federal
❑Urban
E]Minor Arterial
ElUrban
ElMinor Arterial
Functional
❑✓ Rural
❑ Collector
❑ Rural
❑ Collector
Classification
❑ NHS
❑ Major Collector
❑ NHS
❑ Major Collector
❑✓ Minor Collector
❑ Minor Collector
❑ Local Access
❑ Local Access
Terrain
❑ Flat ❑ Roll ❑✓ Mountain
[:]Flat ❑ Roll ❑ Mountain
Posted Speed
50
Design Speed
50
Existing ADT
586
Design Year ADT
Design Year
2020
Design Hourly Volume (DHV)
Performance of Work
Preliminary Engineering Will Be Performed By
Others
Agency
Kittitas County Public Works / Consultant
80 %
20
Construction Will Be Performed By
Contract
Agency
Contractor
100 %
%
Environmental Classification
❑ Class I - Environmental Impact Statement (EIS)✓❑
Class II - Categorically Excluded
(CE)
❑ Project Involves NEPA/SEPA Section 404
❑✓ Projects Requiring Documentation
Interagency Agreement
(Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
DOT Form 140-101 Page 2
Revised 04/2015 Previous Editions Obsolete
Agency Project Title Date
Kittitas County Vantage Highway 1/16/2020
Right of Way
0✓ No Right of Way Needed ❑ Right of Way Needed
*All construction required by the ❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the exiting right of way.
Utilities Railroad
❑ No utility work required ❑✓ No railroad work required
❑✓
All utility work will be completed prior to the start ❑ All railroad work will be completed prior to the start of
of the construction contract the construction contract
F-1 All utility work will be completed in coordination ❑AII the railroad work will be completed in coordination
with the construction contract with the construction contract
Description of Utility Relocation orAdjustments and Existing Major Structures Involved in the Project
Utility adjustments needed will be identified when survey and preliminary design are done. The utility
companies will be notified of the conflicts and be required to either temporarily move or relocate their utility
out of the projects way prior to construction. It is anticipated that this will include communication and fiber
optic buried lines in conflict with guardrail post locations.
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the proposed project? ❑ Yes ❑✓ No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency Kittitas County Public Works
Date By
Mayor/Chairperson
DOT Form 140-101 Page 3
Revised 0412015 Previous Editions Obsolete