Contract No.: 21 I Project No.: 1503 3 8 I Date: November 26, 2018
Client: Kittitas County
Project Name: 2019 Water Right Technical Assistance
Description of Work
Aspect Consulting (Aspect) is assisting Kittitas County with expanding its
water bank to cover all developable parcels in the County . Significant
over-the-county (OTC) and permit coverage exists in the Upper and
Lower County through past acquisitions and permitting related efforts.
Targeted expansions are planned for 2019 in harder to mitigate areas.
These include the following :
• Expansion of mitigation above KRD in the Lower County. A pilot
in the Wilson-Caribou subbasin is being coordinated by Ecology
currently that looks like it will be approved by June 30, 2018. The
next step will be to seek further expansion into other subbasins.
• Expansion of green zone coverage through use of County in-lieu
fee or other mitigation projects in other key basins (e.g.
Teanaway).
• Completion of permitting for remaining back-mitigation
obligations .
• Expansion of the County's portfolio to ensure adequate mitigation
for future growth .
Aspect will provide on-call permitting, hydrogeologic support, technical
support, Ecology coordination and facilitation, Water Transfer Working
Group attendance (as requested), or other services as directed by Kittitas
County. We understand that Kittitas County continues to add internal staff
capabilities to handle a greater percentage of water banking
responsibilities . In addition, the expectations of Ecology for complete
water bank coverage in the County cannot be readily predicted. In
addition, the expectations of Ecology for complete water bank coverage in
the County cannot be readily predicted. Based on the information
available, Aspect forecasts providing technical assistance not-to-exceed
$17,500 in the first quarter of 2019. Aspect will keep Kittitas County
updated monthly on progress towards meeting these goals .
Cost
Aspect proposes to complete
this work on a time-and-
materials basis, not-to-
exceed:
$17,500
Bainbridge Island Office:
Bellingham Office:
350 Madison Avenue North, Bainbridge Island, WA 98110
907 Harris Avenue, Suite 301, Bellingham, WA 98225
(206) 780-9370
(360) 746-8964
(971) 865-5896
(206) 328-7443
(971) 865-5890
(509) 888-5766
(509) 895-5957
Bend Office:
Seattle Office:
Portland Office:
Wenatchee Office :
Yakima Office:
532 SW 13th St., Ste . 103, Bend, OR 97702
710 2nd Ave, Suite 550, Seattle, WA 98104
522 SW Fifth Avenue, Suite 301, Portland, OR 97204
23 South Mission Avenue, Suite C, Wenatchee, WA 98801
123 East Yakima Avenue, Suite 200, Yakima, WA 98901
www.aspectconsulting.com
Change Order No. 21
Project No. 150338
This change amends contract between Aspect Consulting, LLC and Client dated November 6, 2013 .
Except as amended above, all terms and conditions of contract apply to this contract change.
ASPECT CONSUL TING, LLC
a limit ed liability company Printed Name: Daniel R. Haller, PE
Princi al Water Resources En meer
CLIENT
JJ-. L/ /13
V :\150338 Kittitas County General Permit Technical Assistance\Contracts\Proposal Material\CC21_20181126.docx
Page2
Aspect SCHEDULE OF CHARGES
'CO NS U LTIN G
Unless otherwise stated in the proposal or services agreement, current rates are as follows :
PERSONNEL CHARGES: ENGINEERS, SCIENTISTS, AND ANALYSTS
Principals and Associates
Principal Scientist/Engineer/ Analyst 2
Principal Scientist/Engineer/ Analyst 1
Sr. Associate Scientist/Engineer/ Analyst
Associate Scientist/Engineer/ Analyst
Technical Professionals
Senior Scientist/Engineer/ Analyst 3
Senior Scientist/Engineer/ Analyst 2
Senior Scientist/Engineer/ Analyst 1
Project Scientist/Engineer/ Analyst 3
Project Scientist/Engineer/ Analyst 2
Project Scientist/Engineer/ Analyst 1 -------------------
Staff Scientist/Engineer/ Analyst 3
Staff Scientist/Engineer/ Analyst 2
Staff Scientist/Engineer/ Analyst 1
PERSONNEL CHARGES: TECHNICAL AND PROJECT SUPPORT STAFF
Field/Construction Staff
Field/Construction Supervisor
Field Technician 2
Field Technician 1
Design , CAD, and Graphics Staff
Engineering Designer
Sr. CAD Technician/Specialist
CAD Technician
Technical Editing and Project Operations
Sr. Technical Editor
Technical Editor
Project Coordinator 2
Project Coordinator 1
PERSONNEL CHARGES: TECHNOLOGY AND SOFTWARE DEVELOPMENT
Sr. Technology Project Manager
Technology Project Manager
Senior Software/Database Architect/Developer
Software/Database Architect/Developer
OTHER DISBURSEMENT CHARGES
Legal Testimony (4-hour minimum)
Mileage
Subcontractors and Mis cellaneous Expenses
Other equipment, rentals, and expenses will be provided on a per job basis.
Effective January 2019
Hourly Rate
$253
$239
$221
$207
$207
$195
$182
$167
$155
$145
$134
$121
$113
Hourly Rate
$124
$101
$94
$145
$130
$115
$115
$104
$98
$93
Hourly Rate
$215
$200
$205
$180
$350/hr
Federal Gov Rate Plus 15%
Cost Plus 15%
Client acknowledges that Aspect will adjust the Schedule of Charges annually, and that the Agreement will remain valid for any and al/