HomeMy WebLinkAboutResolutiontoapproveTO16KPFFKITTITAS COUNTY DEPARTMENT OF PUBLIC WORKS AGENDA STAFF REPORT AGENDA DATE: October 2, 2018 ACTION REQUESTED: Request to approve a Resolution authorizing Chair Signature on KPFF Task Order No. 16, Big Boulder Creek Bridge Replacement BACKGROUND: In 2018, The United States Forest Service discovered a damaged abutment on the wooden bridge at Big Boulder Creek. Public Works received Title 1 funding from the United States government during 2018 and anticipates additional funding in 2019. The bridge is located on Fish Lake Road and is maintained by the Forest Service. Replacement of bridge is not likely without the Title 1 funding. The road is utilized by a handful of residents and provides a recreation access to hikers in the summer and snow mobiles in the winter. The Forest Service is anxious to replace the structure in 2019. KPFF is an approved structural consultant appearing on Public Works 2017 professional roster. The cost of design and construction support service is $173,000. INTERACTION: Public Works RECOMMENDATION: Authorize the Chair's signature on KPFF Task Order No. 16 for design and construction support services; Big Boulder Creek Bridge Replacement. HANDLING: Return one original to Public Works ATTACHMENTS: Resolution, Task Order No. 16 with KPFF LEAD STAFF: Mark R. Cook, Director BOARD OF COUNTY COMMISSIONERS COUNTY OF KITTITAS STATE OF WASHINGTON RESOLUTION NO. 2018 - AUTHORIZING THE CHAIR'S SIGNATURE ON KPFF TASK ORDER NO. 16 FOR BIG BOULDER CREEK BRIDGE REPLACEMENT ENGINEERING AND CONSTRUCTION SERVICES WHEREAS: KPFF was selected from a competitive selection process in 2017 as a structural engineering service provider; and WHEREAS: The United States Forest Service recently load rated the Big Boulder Creek Bridge for a failing bridge abutment; and WHEREAS: The bridge is located on Fish Lake Road and serves County residents; and WHEREAS: Public Works has recently placed the Big Boulder Creek Bridge on the annual construction program for 2019; and WHEREAS: Replacement of the failing bridge is a high priority for the United States Forest Service who is maintaining Fish Lake Road for the County on a maintenance agreement; and NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in the best interest of the public, does hereby authorize the Chair's signature on KPFF Task Order No. 16 for engineering and construction support services replacing Big Boulder Creek Bridge. BE IT FURTHER RESOLVED that cost of KPFF Task Order is set at $173,000. DATED this 2nd day of October, 2018, at Ellensburg, Washington. Attest: ❑ Clerk of the Board- Julie Kjorsvik ❑ Deputy Clerk of the Board- Mandy Buchholz BOARD OF COUNTY COMMISSIONERS KITTITAS COUNTY, WASHINGTON Laura Osiadacz, Chairman Obie O'Brien, Vice -Chairman Cory Wright, Commissioner ����� '", KZTTITAiB COUNTY DEPARTMENT OF PUBLIC WORKS K17 TITAS W UFT} Formal Task Order Document KPFF Task Order Number 016 Maximum Amount Payable $173,000 Completion Date 12/30/2019 The general provisions and clauses of Local Agency Agreement Number (KCPW 2017- 19ENG2) shall be in full force and effect for this Task Order. Location of Project: Kittitas County Project Title: Big Boulder Creek Bridge Replacement Description of Work: KPFF will prepare the PS&E documents for the replacement of the Big Boulder Creek Bridge in coordination with Kittitas County staff. The design team includes: KPFF — Project Management and Structural Engineering Hart Crowser — Geotechnical Engineering Watershed Science and Engineering — Hydraulic Engineering Jacobs — Environmental/Permitting Tentative Project Advertisement is April 2019, but will be dependent on permitting, fish windows, and bridge procurement schedules. The existing timber bridge is located on Cle Elum Valley Road over Big Boulder Creek approximately three miles north of the Salmon La Sac Campground. The bridge is currently posted for a 5 Ton weight limit due to scour at the timber sill foundation. The County prefers to replace the bridge with a single lane prefabricated superstructure. TASK 1 PROJECT MANAGEMENT KPFF will manage the development of the PLANS, SPECS & ENGINEERING COST ESTIMATE (PS&E) in such a manner to ensure the County is able to achieve the desirable bidding date. This effort will include appropriate in-house duties such as invoicing, contract �SL�UF4 _.. l0 PIS, �'� �-` KITTITgfS COTJNTY W, pop DEPARTMENT OF PUBLIC WORKS MI I ITAS COU.\TV compliance assurance, file and staff organization, client communications (emails and telephone), and general project oversight. Project Management tasks include: 1.1 Project Team Management and Coordination 1.2 Monthly Progress Reports/Invoices (Assume 8) 1.3 Monthly Project Progress Meetings/Minutes (Assume 8 meetings, held via teleconference) 1.4 Coordination with WDFW (Assume 8 hours) 1.5 Management Reserve - allocation of the reserve funds for additional out of scope tasks based on written approval of the County TASK 2 STRUCTURAL ENGINEERING KPFF shall perform the structural engineering analysis and design of the Big Boulder Creek Bridge substructure. KPFF shall perform appropriate analysis and design calculations in accordance with the most current edition (at the time of NTP) of the WSDOT Bridge Design Manual (BDM) and the AASHTO LRFD Bridge Design Specifications, and the Local Agency Guidelines. Considering the location and use of the bridge, alternative criteria, such as Forest Service guidelines, may be considered to reduce construction costs. TASK 2.1 — Project Kickoff Meeting and Site Visit A project kickoff meeting will be held at the existing bridge site. TASK 2.2 — Alternative Analysis Memo Brief memo to summarize site constraints, design criteria and preferred bridge structure TASK 2.3 — Development of PS&E/Contract Bid Documents TASK 2.31 — Plan and Calculation Preparation • Project Cover Sheet • General Notes and Quantities • Bridge Layout - plan and elevation • Structural notes • Foundation Plan — Layout • Foundation Design and Details • Wingwall Layout/Details TASK 2.32 — Structural Special Provisions t GPSCA�l.S ... lO ]Nf'CO KZTTITAS COUNTY DEPARTMENT OF PUBLIC WORKS MTTITAS COUNTY TASK 2.33 — Cost Estimate TASK 2.34 — Deliverable preparation TASK 2.40 — Quality Control Checks and Reviews TASK 2.50 — Technical Collaboration Structural design engineers will coordinate with survey, civil, geotechnical, hydraulics and environmental engineers for project design and contract coordination. TASK 2.60 — Construction Support If needed to provide support during construction to respond to RFI's and review submittals. TASK 3 GEOTECHNICAL ENGINEERING TASK 3.10 — Planning and Research Hart Crowser will review readily available geologic maps and water well logs that cover the site vicinity, and other reports and plans provided by others (if any) for general information regarding subsurface soil and groundwater conditions and geologic hazards. Hart Crowser will coordinate field explorations with KPFF, Kittitas County, USFS, drilling subcontractors, and internal staff. If required, Hart Crowser will submit a traffic control plan for review by the County. TASK 3.20 — Field Work TASK 3.21 — Site Reconnaissance and Utility Locates Hart Crowser will conduct a reconnaissance to get familiarized with the site. Relevant features will be noted, and the proposed exploration location marked for the utility locators. Hart Crowser will notify "One -Call" service for public utility locates. TASK 3.22 — Field Explorations Hart Crowser will advance one boring near the south side of the bridge. (The north side of the bridge cannot be accessed with drilling equipment due to load restrictions.) The boring will be advanced using a TSi 150CC Sonic Drill, which can typically penetrate "r c"scnues _. io hn; ,��°"° `�9 KZTTITAiS C®ZJNTY DEPARTMENT Of PUBLIC WORKS M1 ]FASCOUN11 through boulders and similar materials. The boring will be advanced until one of the following criteria is reached: I) the boring penetrates 10 feet into rock, 2) refusal occurs within nested boulders, or 3) we reach a depth of 50 feet. If thick soil layers (sand, gravel, etc.) are encountered, then occasional soil samples will be obtained by driving split -spoon samplers in accordance with the standard penetration test (SPT) procedure (American Society for Testing and Materials [ASTM] D 1586). Hart Crowser will observe the exploration, log the subsurface conditions, collect representative soil and rock samples, and transport the samples to the laboratory for further visual evaluation and testing. The borehole will be backfilled in accordance with Department of Ecology regulations. The upper 1 foot of the borehole will be patched with gravel surfacing. Excess spoils from the borehole will be spread on the ground adjacent to the borehole. If required, Hart Crowser's subcontractors will provide traffic control services during drilling. TASK 3.23 — Sample Review and Laboratory Testing Soil and rock samples obtained from the explorations will be visually classified in the field by Hart Crowser and in Hart Crowser's geotechnical laboratory based on the Unified Soil Classification System (USCS) and ASTM classification methods. Hart Crowser will conduct a series of geotechnical laboratory tests on selected soil and bedrock samples obtained from the explorations to evaluate the engineering and index properties of the site soils. The specific tests conducted will depend upon actual conditions encountered. For budgeting purposes, Hart Crowser has assumed the tests will include up to eight moisture content determinations, one Atterberg limits determination, three grain -size distribution tests, and one unconfined compressive test. TASK 3.30 — Office Work TASK 3.31 — Engineering Analysis and Consultations Hart Crowser will conduct engineering analyses to evaluate seismic hazards, ground settlement, abutment stability, foundation and retaining wall alternatives and design parameters, and earthwork guidelines. Engineering analysis will be completed in general conformance with appropriate Washington State Department of Transportation (WSDOT) design manuals. Hart Crowser will consult with the design team regarding their findings and foundation alternatives. °� ` KITTZTA6 COUNTY DEPARTMENT OF PUBLIC WORKS gTTITAS COUNTY TASK 3.32 — Geotechnical Reporting Hart Crowser will prepare a geotechnical report to document their findings and recommendations. The geotechnical report will address design and construction issues, including: • Site and boring location plan(s); • Description of subsurface soil, rock, and groundwater conditions; • Site preparation and earthwork recommendations; • Seismic hazards and WSDOT-based seismic design parameters; • Temporary and permanent abutment foundation alternatives, design recommendations, and stability; • Retaining wall alternatives and design parameters; and • Construction considerations. A draft report will be provided to the design team for review and comments. A final report will be prepared that addresses review comments from the design team. TASK 3.33 — Project Management and Meetings Hart Crowser will provide geotechnical project management and support services, including coordinating staff and subcontractors and conducting telephone consultations and email communications with the design team. Hart Crowser will attend up to one meeting at KPFF's office. TASK 3.40 — Construction Support The geotechnical engineer will provide support during construction to respond to RFFs or changes in field conditions. TASK 4 HYDRAULIC DESIGN Watershed Science & Engineering (WSE) will provide hydraulic engineering services for the Big Boulder Creek Bridge Replacement Project in Kittitas County, Washington. WSE will lead the hydraulic engineering portions of the project which will include completing the following tasks. TASK 4.10 — Data Collection and Review WSE will collect and review existing data and information needed to complete the hydraulic investigation. Data will include but not be limited to topographic maps including LiDAR data, "tiG,ors -,IDn p°" '`v., KITTZTAS COUNTY DEPARTMENT OF PUBLIC WORKS MMTAS COUNTY historical aerial photos, flood data, bridge maintenance records, and anecdotal information on past flood events from County maintenance staff. Assumptions: • County will supply relevant data they possess TASK 4.20 — Site Inspection WSE will conduct a one -day field inspection to examine the crossing and Big Boulder Creek. WSE will examine hydraulic and geomorphic characteristics, sediment transport, debris flow potential, lateral erosion, and scour. Assumptions: • NTP is received in time to allow WSE to visit the site before snow fall. TASK 4.30 — Channel Survey WSE will survey up to eight cross sections and a longitudinal profile of the stream channel as part of the site inspection task above. WSE will merge the stream channel data with the County's survey to develop a single topographic base map required for the hydraulic investigation. Assumptions: • County will or has collected detailed topographic data within the road right-of-way. TASK 4.40 — Hydrology WSE will use USGS regional regression equations to estimate annual instantaneous peak design flow rates. The design event for flow and scour will be the 100 -year flood and the check flood for potential damage will be the 500 -year event. The 500 -year event is not the design event, it is solely used to assess risk in -order to identify any remaining significant erosion or scour issues that might need to be addressed in the design. Assumptions: • USGS regression equations will provide reasonable estimates for the 100 -year and 500 - year annual instantaneous peak flows. If they do not, WSE will use alternative methods to estimate the flows. TASK 4.50 — Hydraulic Analysis ", HZTTITAS COUNTY DEPARTMENT OF PUBLIC WORKS K1171TASCOUNII WSE will develop a simple HEC -RAS model of Big Boulder Creek in the vicinity of the bridge crossing using topographic base map. The model will not be calibrated because observed discharge/highwater marks are not available. Instead, WSE will use engineering judgment to select and adjust model parameters. The model will be used to help size the bridge waterway, to provide data required to evaluate lateral erosion and scour potential, and to develop countermeasures. TASK 4.60 — Channel Stability and Scour Assessment WSE will determine if lateral erosion, local scour, ice, or debris flows pose a threat to the proposed crossing. If they do, WSE will work with KPFF to address these hazards in the design. Assumptions: • These hazards will be addressed through modifications the structure itself (e.g. deeper foundations, longer bridge, etc.) and not through design and installation of external countermeasures (e.g. riprap). If countermeasures are required, the optional task at the end of this scope will be completed. TASK 4.70 — WDFW and Permit Coordination It is anticipated that WDFW personnel have an idea of the length of crossing they would like to see at the site. WSE will work with WDFW personnel, the County, and Jacobs (the company that will acquire the project permits) to collectively arrive at a bridge length that is acceptable to all parties. An allowance is provided for WSE's lead engineer to participate in one meeting with WDFW personnel in Ellensburg. Assumptions: • A reasonable bridge length will be agreed to that the County can afford to build. TASK 4.80 — Hydraulic Design Report WSE will prepare a hydraulic design report to summarize and document the results of the investigation. It will include the recommended NBIS Scour Code rating for the new structure, a code that the County will need for their records. Assumptions: • A draft of the report will be provided to the County and KPFF for review. Upon receipt of comments, WSE will refine the report and submit a final version as a PDF. TASK 4.90 — Meetings and Administration c 5-11rs...10111012 °10111E 0c Fe KZTTITAB COUNTY DEPARTMENT OF PUBLIC WORKS KITTITAS COUNTY An allowance is provided for WSE personnel to attend one meeting at KPFF's Seattle office to discuss the design and one meeting in Ellensburg to meet with the County. Assumptions: • WSE will develop concept sketches of the countermeasures which will be provided to KPFF. KPFF will prepare detailed plans to be incorporated into the project plan set. • WSE will recommend specifications for the countermeasures. • WSE has included a modest cost for this task in the accompanying cost estimate. This estimate will be revisited and may need to be revised once the type and scale of countermeasures required are identified. • At this time it is assumed that scour and erosion protection countermeasures are not necessary and have not been included in the fee TASK 5 ENVIRONMENTAL/PERMITTING The Jacobs team will deliver Environmental Documentation and Permitting in coordination with KPFF and Kittitas County staff. TASK 5.10 — Project Management 1. Project planning, team direction and coordination and ongoing client communication 2. Project Controls a. Prepare monthly invoices and back-up, and monthly progress reports. b. Monitoring and updating Environmental delivery schedule. 3. Deliverables a. Monthly progress reports and invoices TASK 5.20 — Agency Coordination Agency Coordination a. Coordinate with Kittitas County Public Works, Kittitas County Community and Development Services, Department of Fish and Wildlife, Department of Ecology, US Army Corps of Engineers, and other agencies as needed. b. Coordination items include impact analysis, permits required and timelines, and facilitated review of project milestones as needed. TASK 5.30 — NEPA/SEPA Documentation 1. NEPA/SEPA Documentation a. Research and prepare one (1) NEPA Categorical Exclusion (CE) form b. Research and prepare one (1) SEPA Checklist and Draft DNS if needed TASK 5.40 — Biological Assessment 1. Biological Assessment �11 . " � y9, KITTZTPiS COUNTY p`e\ DEPARTMENT OF PUBLIC WORKS K11 T1 WUNTI' a. Field Reviews b. Prepare one (1) Biological Assessment, assumed to be formal consultation with both Services. c. Provide ongoing coordination with agencies throughout the review/approval process. TASK 5.50 — NHPA Section 106 NHPA Section 106 Evaluation a. Develop Area of Potential Effects (APE) and coordinate with SHPO. b. Evaluate cultural and historic resources within the project area of effect as per Section 106 requirements. TASK 5.60 — JARPA Package Preparation and Submittal JARPA Preparation and Submittal a. Populate and submit one (1) JARPA application package. b. Coordination with federal and/or state agencies for the following permits: i. Corps 404 permit, United States Army Corps of Engineers (Assumes Nationwide Permit) ii. Hydraulic Permit Approval (HPA), WA State Dept. of Fish & Wildlife iii. Ecology 401 permit review including development of TESC and SWPPP. TASK 5.70 — Local Permits or Approvals 1. Local Permits or Exemptions a. Coordinate with Kittitas County CDS on SEPA, Shorelines, and Critical Areas requirements. TASK 5.80 — Biology Support During Construction (OPTIONAL) 1. Support services during construction, including worksite isolation support, fish salvage and removal, planting or site stabilization guidance up to 40 hours. This task is not subject to Assumption la. Assumptions: • Coordination with FHWA or WSDOT Local Programs will not be required. • The Biological Assessment that will be prepared will be "Likely to Adversely Affect' for Bull Trout and Steelhead, and will require formal consultation with both USFWS and NMFS. • The US Army Corps of Engineers will issue a CWA Section 404 NWP 14. No individual permit will be required. • Section 106 will be determined as "May Affect', and will require SHPO concurrence • The Department of Ecology will issue a Letter of Verification for CWA Section 402. No individual permit will be required. • No wetlands will be impacted by the project. This Scope does not include wetland delineations or reporting. cn5cnors... n'/He ���"'�'� n`°*e KZTTZTAS COUNTY y DEPARTMENT OF PUBLIC WORKS MIT TTASCOUNTY • No NPDES Permit will be required. • SEPA will be exempt. • If the level of effort and cost for permit or approval acquisition is higher than the budget amount, Jacobs will coordinate with KPFF and the County to determine amendments as needed. • No mitigation planning is included in this scope of work. '`�., KZTTITAIS COUNTY DEPARTMENT OF PUBLIC WORKS KITTITAS COUNTY PROJECT DELIVERABLES: 1. Alternatives Analysis Memo (Draft and Final) 2. 30% Plan Set (Permit set. 3 sheets estimated. Layout, Elevation, Cross-section, structural notes, Cost Estimate) 3. 75% Plan Set (6-8 sheets, updated cost estimate, GSP run -list, 30% comment resolution) 4. 100% Draft Plans (6-8 sheets, updated cost estimate, PDF of GSP's or run -list and PSE files, pending final review by county, 75% comment resolution and complete PS&E) 5. 100% Stamped and Signed Plans (Contract Documents — bid ready) 6. Geotechnical report (Draft PDF and Final PDF + 3 hard copies) 7. One (1) NEPA CE and ECS Form 8. One (1) NHPA Section 106 Compliance Memo 9. One (1) Biological Assessment (Formal Consultation) 10. One (1) SEPA Checklist (Unless Exempt) 11. One (1) JARPA package for delivery to USACE, WDFW, and WDOE 12. Local Agency correspondence for each permit, approval, or exemption PROJECT ASSUMPTIONS: 1. COUNTY to provide KPFF with the project survey base map. County will collect additional data as necessary as requested by KPFF. Contours shall be in at least 2 foot increments and shall preferably extend at least 200 feet to the north, south, east and west of the proposed project limits to include all utilities, driveways, ditches, ROW/property lines and other items which are reasonably likely to impact the bridge layout and design. 2. COUNTY will provide Civil roadway and drainage design for the project. 3. KPFF to provide specifications related to the PS&E they develop (bridge portion only). 4. New bridge is assumed to be designed for one 12 foot lane, and two 2 foot shoulders and no sidewalks. 5. Bridge superstructure will have a 2% crown from the centerline of the roadway, or as prescribed by COUNTY Civil roadway design. 6. There will be no drains on the bridge. 7. Bridge superstructure is assumed to be prefabricated and designed and supplied by the Contractor during construction. 8. Load rating report will be provided by bridge superstructure supplier. KZTTZTAI3 COUNTY DEPARTMENT OF PUBLIC WORKS 9. COUNTY will prepare Division 1 and all Civil special provisions and assemble special provision package and bid package. Cost Breakdown: See Attached Project Schedule: KPFF will provide a PDF of the plans for the 30%, 75%, and 100% design at the dates shown below. For efficiency, the design will continue following milestone submittal while the county performs review of the submitted plans. The COUNTY will endeavor to complete and return to KPFF all comments as soon as possible following receipt of them, but in no case more than 10 business days following the submittal date. Milestone Milestone Delivery Date Description 130% November 2018 Permit set. 3 sheets estimated. Layout, Elevation, Cross-section, basic notes 75% January 2019 6-8 sheets, all items including further development of the notes, specs, and quantities. 100 % Draft March 2019 6-8 sheets, all items developed and ready for construction, pending final review by County. Complete PS&E. 100% Stamped and Signed April 2019 Stamped and Signed Contract Documents — bid ready. Completion Date: December 30, 2019 Agency Signature: Date: Consultant Signature: — Date: ZG ' 61� tso Qbw� a ssec .1e Exhibit D-1 KPFF Consulting Engineers Consultant Fee Summary Negotiated Hourly Rate Consultant Agreement Kittitas County On -Call Task Order #16: BIG BOULDER CREEK BRIDGE REPLACEMENT Overhead (OH) Cost 136.25% Fixed Fee (FF) 28.00% Classification Direct Hourly Total X Negotiated = Cost Rate Hours Hourly Rate Principal $ 64.91 8.00 X $171.52 = $ 1,372.20 Project Manager $ 45.29 104.00 X $119.68 = $ 12,446.60 Technical Specialist $ 64.91 34.00 X $171.52 = $ 5,831.84 Structural Task Lead $ 45.29 134.00 X $119.68 = $ 16,036.96 Project Engineer $ 43.27 120.00 X $114.34 = $ 13,720.92 Design Engineer $ 36.93 0.00 X $97.59 = $ - CAD Technician $ 46.04 144.00 X $121.66 = $ 17,519.14 Project Coordinator $ 28.85 20.00 X $76.24 = $ 1,524.72 Intern $ 22.00 0.00 X $58.14 = $ - Admin $ 23.08 0.00 X $60.99 = $ 0.00 X $0.00 = $ 0.00 X $0.00 = $ 0.00 X $0.00 = $ - Subtotal $ 68,452.38 Reimbursables Mileage (220 Miles x $0.545/mile) $ 119.90 Airfare (Allowance) Per Diem (Hotel + Meals @ $#.## x # trips) Subcontract (Sub Name & Task) (Blank) (Allowance) Subtotal $ 119.90 Subconsultant Costs (See Exhibit E) Management Reserve $88,160.24 $15,673 GRAND TOTAL: $172,405.77 Exhibit E-1 Hart Crowser, Inc. Consultant Fee Summary Negotiated Hourly Rate Consultant Agreement BIG BOULDER CREEK BRIDGE REPLACEMENT Overhead (OH) Cost Fixed Fee (FF) Classification Senior Principal Principal Senior Associate Associate Senior Project Project Senior Staff Staff Senior Drafter Drafter Project Assistant Reimbursables Mileage Laboratory Testing Drilling Sub. Traffic Control Sub. B&O Tax on Subs Subtotal 224.46% 28.00% Direct Hourly Total Negotiated Rate Hours X Hourly Rate _ Cost $ 88.86 0.00 X $313.20 = $ $ 74.38 21.00 X $262.16 = $ 5,505.35 $ 62.22 0.00 X $219.30 = $ $ 52.63 0.00 X $185.50 = $ $ 43.70 0.00 X $154.03 = $ - $ 36.06 36.00 X $127.10 = $ 4,575.49 $ 32.22 34.00 X $113.56 = $ 3,861.13 $ 26.50 0.00 X $93.40 = $ - $ 32.04 10.00 X $112.93 = $ 1,129.28 $ 3C.23 0.00 X $106.55 = $ - $ 29.96 6.00 X $105.60 = $ 633.58 Subtotal $ 15,704.84 (500 Miles x $0.545/mile) Hart Crowser Laboratory - Task 2.3 Holt Services - Task 2.2 Northwest Barricade - I ask 2.2 1.5% of Holt and Northwest Barricade $ 218.00 $ 1.100.0C $ 4,500.00 $ 2,500.00 $ 105.00 $ 8,423.00 GRAND TOTAL: $24,127.84 Exhibit E-1 Watershed Science & Engineering Consultant Fee Summary Negotiated Hourly Rate Consultant Agreement BIG BOULDER CREEK BRIDGE REPLACEMENT Overhead (OH) Cost 188.43% Fixed Fee (FF) 28.00% Classification Direct Hourly Rate Principal $ 67.31 Senior Engineer 1 $ 59.62 Junior Engineer $ 30.77 Contract Administrator $ 30.00 Reimbursables Mileage Airfare Per Diem Subcontract (Blank) Subtotal Total Negotiated X - Cost Hours Hourly Rate 68.00 X $212.99 = $ 14,483.25 5.00 X $188.66 = $ 943.28 83.00 X $97.37 = $ 8,081.34 2.00 X $94.93 = $ 189.86 Subtotal $ 23,697.73 (400 Miles x $0.545/mile) (Allowance) (Hotel + Meals @ $#.## x # trips) (Sub Name & Task) (Allowance) $ 218.00 $ 218.00 GRAND TOTAL: $23,915.73 Exhibit E-1 Jacobs Engineering Consultant Fee Summary Negotiated Hourly Rate Consultant Agreement BIG BOULDER CREEK BRIDGE REPLACEMENT Overhead (OH) Cost Fixed Fee (FF) Classification Env. Group Lead Env. Project Manager Permit Lead Sr. Cultural Cultural Field Tech Env. Engineer Jr Biologist Technical Editor Administration Reimbursables Mileage Airfare Per Diem Subcontract (Blank) Subtotal 117.00% 28.00% Direct Hourly Rate $ 66.15 $ 47.83 $ 33.80 $ 76.13 $ 28.00 $ 33.63 $ 33.80 $ 45.55 $ 25.00 Total Negotiated Hours X Hourly Rate - Cost 49.00 X $162.07 = $ 7,941.31 58.00 X $117.18 = $ 6,796.64 86.00 X $82.81 = $ 7,121.66 2.00 X $186.52 = $ 373.04 50.00 X $68.60 = $ 3,430.00 10.00 X $82.39 = $ 823.94 141.00 X $82.81 = $ 11,676.21 9.00 X $111.60 = $ 1,004.38 4.00 X $61.25 = $ 245.00 Subtotal $ 39,412.17 (500 Miles x $0.545/mile) (Allowance) (Hotel + Meals @ $144/day x 3days) (Sub Name & Task) (Allowance) $ 272.50 $ 432.00 $ 704.50 11GRAND TOTAL: $40.116.6711 1q3ff �.Idll o�om0o�oo� «�mW.w=. EN M ME -------------- EMIMMEMMIMMENEEMI 000�0000moo0 C.. 1q3ff �.Idll kpff �.se„ kmMwmpec. -.. ^n ........ .. 0000® IExse:�rz!l! kpff �.se„ BIG BOULDER CREEK BRIDGE REPLACEMENT m� n vm iMµY.EMENt .crops i®m WnpanmlaMCwgY.nian ' wnW arvs YCIYP<LENOINE[gY0 �.mMe -.. -. aryv ymn.cL vl WnNsnMpnhW Lm ..- wnPOM.nx,,Wxt M.ueA __ aumycon�idcMmvnOPnYm ' vn @ury ,Lxhaen+nnm, HpnaL- EnLna.�rnmm�nN ' vn MFa xo,)unsew NILOLEXOIXEENMO mUW Wal [v.WMum _ sunµ Pwlowd Palin " µ.utlrvvNCmbNem - a pmt NO 1M1M<IAlC E1pMEEPNO v�mo, W np�win nsclgtlen PapMµ "- s��ame< BIG BOULDER CREEK BRIDGE REPLACEMENT �• 'I' o mmi ENAAoocm�)anoxa mruxvu oat xm mxd(a:a.ylc,•wv.,....n — I ai%N'Sn nu lxNim•p •.mre_ rm. Labor Su m: _o_ o __o __e_ _o_ o • o • o JO 1 1 lo_ so 515,)05 Reimburse ble 5u m: _ � EBA3I 1q)ff kPff 1•w .„ BIG BOULDER CREEK BRIDGE REPLACEMENT PR yw T"MMl9WMEr W q iwm W nagmml em uweeamn MMM/ PrwrwbweH��® Mµ vigMhWDa .nnwEne.ma SI UOWR ENOMEERMO NtleA�6��e5 MeveugNiremnPsdECamm BNMumna pMuw M _ d•gUuuia psvMplw —� _ _ mwnryl%.R ami Mn�lswe�v�� E4•NooAM1tl.. m�.au0 ywn pF1'c sumaiN, alcl n mMM '[EOIE[NN ICK E NCIN EERINC ¢�pwNw r�Qaia. _ oaNgyraµ Wu�uaona mamgnanamwatmw a xvrnwuc ENMNEERmc 430 C=-, mm u•M..M+Ia wI�Mg kPff 1•w .„ 1q3ff BIG BOULDER CREEK BRIDGE�� REPLACEMENT ENN GY KDOCYMENi 11 q m embT' Swro, CuiN CwuwVs Po� � Lwrsumyl- Le0o.6um: 5 3 311,606 RelmEunage9um: yt,y 1q3ff kpff 1,11.11, - mmOEM IN o�oom OEM CC��CC�o:i e �q,F_oos�000000 kpff 1,11.11, BIG BOULDER CREEK BRIDGE REPLACEMENT E- -.,, I PE0.NIIIH6a*u IEPMEP� Munn _ _ _ epiq_iuln.n z.m,s�m: 41 ae se ss z Ea sa i m P s szzpn aame.,.,cia�m: - nos 1• rsarz