HomeMy WebLinkAboutResolutionAuthorizingChairSignatureProspectusNaneumRoadCulvertKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: August 7, 2018
ACTION REQUESTED: Approve the Resolution Authorizing the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the
Naneum Road Culvert Replacement Project
BACKGROUND: Public Works is planning to rehabilitate Naneum Road at
approximate milepost 3.1 by replacing an undersized
culvert. Water overtops the road at this culvert crossing
every year, and the resulting erosion has washed away
about half of the shoulder. The culvert also presents a
barrier to upstream fish passage and contributes to local
residential and agricultural flooding.
Project work includes replacing the undersized corrugated
metal pipe with a larger structure meeting the hydraulic
demand and fish passage requirements. The project will
also provide for installation of guideposts to improve
delineation, and improving the shoulders to comply with
current design standards.
Construction is planned for summer/fall of 2020. Public
Works is preparing to commence with design work on the
project and is requesting the release of the federal funds for
the Preliminary Engineering phase. This requires the Local
Agency Federal Aid Project Prospectus to be signed and
approved by the Chair of the BOCC.
INTERACTION: Public Works
RECOMMENDATION: Motion to approve the Resolution Authorizing the Chair's
signature on the Local Agency Federal Aid Project
Prospectus for the Naneum Road Culvert Replacement
Project
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution
LEAD STAFF: Sara Folk, Engineering Services Manager
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2018 -
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY
FEDERAL AID PROJECT PROSPECTUS FOR THE NANEUM ROAD
CULVERT REPLACEMENT PROJECT
WHEREAS: The Naneum Road Culvert Replacement project will replace an
undersized culvert on Naneum Road with a larger structure designed to
meet current hydraulic demand as well as fish passage requirements; and
WHEREAS: Public Works received Surface Transportation Block Grant (STBG)
federal funds in the amount of $86,500 for the Preliminary Engineering
phase of this project; and
WHEREAS: In preparation to commence design work, Public Works is requesting the
Washington State Department of Transportation to release the federal
funds for Preliminary Engineering; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the
Chair acknowledging the project has been reviewed and is consistent with
the agency's comprehensive plan for community development; and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in
the best interest of the public, does hereby approve the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the Naneum Road
Culvert Replacement Project
DATED on this 7th day of August, 2018, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Laura Osiadacz, Chairman
Obie O'Brien, Vice -Chairman
Cory Wright, Commissioner
Washington State
Adw
�� Department of Transportation
Local Agency Federal Aid
Project Prospectus
Prefix
Route ( )
Date8/7/18
-
Federal Aid
P-STPR
rgect Number
-
- -- ---
DUNS Number . 01-020-2547
Local Agency CRP 280-18
Project Number —_
WSDOT
( l91-6001349
� Use Only
--- \ /
requirements. Install guideposts to improve delineation, improve shoulders to comply with current design
--
Federal Employer
Tax ID Number
Agency
CAAgency
Federal Program Title
Kittitas County Public Works
n Yes ❑ No
'✓ 20.205 ❑ Other
Project Title
WA 98926
Start Latitude N 47-02-30.94 Start Longitude W 120-28-07.02
Naneum Road Culvert Replacement
Project Prospectus
End Latitude N 47-02-50.37 .End Longitude W 120-28-01.84
Project Termini From -To
_
Title Public Works Director
Nearest City Name
Project Zip Code (+4)
MP 2.89 MP 3.29
Ellensburg,
98926
Begin Mile Post End Mile Post
Length of Project I Award Type
2.89 3.29
0.40 U Local ❑ Local Forces ❑ State ❑ Railroad
Route ID Begin Mile Point
End Mile Point
City Number County Number County Name
L. 0380 19 Kittitas
WSDOT Region Legislative District(s)
Congressional District(s) Urban Area Number
South Central Region 13
$
Total
Local Agency
Phase Start
Phase Estimated Cost
Funding
Federal Funds Date
(Nearest HundredDollar)(Nearest
Hundred Dollar)
(Nearest Hundred Dollar Month Year
P. E. • 100,000
13,500
86,500 Sept 2018
R/W 0
0
0
Const. 650,000
Total 750,000
650,000
1663,500
0 Mar 2020
86,500
__._..............---..-- ----- — - ----- - --- --- - -
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
22 2
jThere is an undersized culvert crossing at the project location, where water overtops the road every year. The
resulting erosion has eroded significant shoulder. Culvert also presents a barrier to upstream fish passage.
r
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Replace undersized corrugated metal pipe with larger structure meeting hydraulic demand and fish passage
requirements. Install guideposts to improve delineation, improve shoulders to comply with current design
standards. Mitigate for geometric deficiencies as allowed within existing right of way.
Local
Local Agency Contact Person Title
Phone
Folk Engineering Services Manager
509-962-7523
Mailing Address City
State Zip Code
411 N Ruby ST, Suite 1 Ellensburg
WA 98926
By
Project Prospectus
-
Approving Authority
_
Title Public Works Director
Date N -Of
oo I Form 140-101 Page 1
Revised 0412015 Previous Editions Obsolete
Agency Protect Title Date
Kittitas County Public Works Naneum Road Culvert Replacement l 8/7/18
Type of Proposed Work
Project Type (Check all that Apply) Roadway Width
Number of Lanes
❑ New Construction ❑ Path / Trail ❑ 3-R 26
2
FV Reconstruction ❑ Pedestrian / Facilities ❑ 2-R
❑ Railroad ❑ Parking Z✓ Other
❑ Bridge
Geometric Design Data
Description
Through Route
Crossroad
❑ Principal Arterial
❑ Principal Arterial
Federal❑Urban
[:1❑Urban Minor Arterial
E]Minor Arterial
Functional
Rural El collector
El Collector
❑ Rural
Classification
❑ Major Collector
❑ NHS
❑ Major Collector
❑ NHS
F/7., Minor Collector
❑Minor Collector
❑ Local Access
❑ Local Access
Terrain
Z Flat ❑ Roll ❑ Mountain
[:]Flat ❑ Roll ❑ Mountain
Posted Speed
50
Design Speed
50
i Existing ADT
<400
�Design-Vear-ADT`----
400
esign Year
2019
Design Hourly Volume (DHV)
NA
Performance of Work
Preliminary Engineering Will Be Performed By Others Agency
Kittitas County Public Works / Consultant 10 %'; 90
Construction Will Be Performed By Contract Agency
Contractor 100 % 0 -
-- — —
Environmental Classification
❑ Class I - Environmental Impact Statement (EIS) Class II - Categorically Excluded (CE)
❑ Project Involves NEPA/SEPA Section 404 L! Projects Requiring Documentation
Interagency Agreement (Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
Lnvironmental permitting needs wit] be identified and pemiits will be acquired during the PE phase. It is anticipated that the
project will be required to submit a Joint Aquatic Resources Permit Application (DARPA) to the U.S. Army Corps of Engineers
(USACE), Washington Department of Fish and Wildlife (WDFW), and Washington Department of Ecology (Ecology.).
Consultations may be required for Endangered Species Act(ESA) Section 7 and National Historic Preservation Act (NHPA)
Section 106.
uu, Form ivu-iu_i Paget
Revised 0412015 Previous Editions Obsolete
Agency
Kittitas County Public Works
of
❑✓ No Right of Way Needed
Project Title Date
Naneum Road Culvert Replacement 8/7/18
❑ Right of Way Needed
`AII construction required by the ❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the exiting right of way.
Utilities I Railroad
❑ No utility work required
[✓ All utility work will be completed prior to the start
of the construction contract
❑
All utility work will be completed in coordination
with the construction contract
U No railroad work required
❑ All railroad work will be completed prior to the start of
the construction contract
❑AII the railroad work will be completed in coordination
with the construction contract
Description of Utility Relocation or Adjustments and Existing Major Structures Involved in the Project
Utility conflicts will be identified during the Design phase of the project, and utility relocation will be
coordinated before construction begins.
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the
Yes U No
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency Kittitas County Public Works
Date By
------ ---- --
Mayor/Chairperson
DOT Form 140-101 Page 3
Revised 0412015 Previous Editions Obsolete