HomeMy WebLinkAboutResolutiontoRatifyChairSignatureProspectusSafetyandRdsideHazardsProjectKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: July 3, 2018
ACTION REQUESTED: Approve the Resolution to Ratify the Chairman's signature
on the Local Agency Federal Aid Project Prospectus for the
Roadside Hazard Safety Improvements -Countywide Project
BACKGROUND: The Roadside Hazard Safety Improvements -Countywide
project will provide for safety improvements on several
different road segments to lessen the severity of run -off -
the -road accidents by installing guardrail where necessary
to protect roadside hazards. Signs such as advanced
warning signs and chevrons for roadway curves, upgraded
stop signs at intersections, and other delineation devices
will be installed as recommended per MUTCD
requirements to also prevent run -off -the -road accidents.
Public Works successfully received Highway Safety
Improvement Program (HSIP) federal funds in the amount
of $689,000 with no local match requirement if
construction is authorized prior to April 30, 2019. This
project was identified as the 41 priority in the Kittitas
County 2017 Safety Plan, and this project addresses safety
improvements to those roadway segments identified in the
safety plan.
Public Works also successfully received Surface
Transportation Block Grant (STBG) federal funds in the
amount of $203,275 with a 13.5% local match requirement.
Public Works is preparing to advertise the project for
construction in the fall of 2018 and is requesting the release
of the Federal Construction Funds. This requires the Local
Agency Federal Aid Project Prospectus to be signed and
approved by the Chair of the BOCC.
The prospectus has been modified from previously signed
prospectuses for separate projects to utilize an alternate
processing method through WSDOT Local Programs to
allow for quicker authorization of construction funds;
whereby allowing project work to begin in September
instead of mid-October. Construction is expected to last up
to 10 weeks.
INTERACTION: Public Works
RECOMMENDATION: Motion to approve the Resolution to Ratify the Chairman's
signature on the Local Agency Federal Aid Project
Prospectus for the Roadside Hazard Safety Improvements -
Countywide
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution
Local Agency Federal Aid Project Prospectus
LEAD STAFF: Sara Folk, Engineering Services Manager
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2018 -
TO RATIFY THE CHAIRMAN'S SIGNATURE ON THE LOCAL AGENCY
FEDERAL AID PROJECT PROSPECTUS FOR THE ROADSIDE HAZARD
SAFETY IMPROVEMENTS - COUNTYWIDE PROJECT
WHEREAS: The Roadside Hazard Safety Improvements — Countywide project will
provide for safety improvements on several different road segments to
lessen the severity of run -off -the -road crashes by installing guardrail
where necessary to protect roadside hazards, and installing signage and
other delineation measures to prevent run -off -the -road crashes; and
WHEREAS: Public Works has been awarded federal funding for this project through
the Highway Safety Improvement Program in the amount of $689,000
with no local match requirement if construction is authorized prior to
April 30, 2019; and
WHEREAS: Public Works has been awarded federal funding for this project through
the Surface Transportation Block Grant program in the amount of
$203,275 with a 13.5% local match requirement; and
WHEREAS: In preparation to advertise the project for construction in fall of 2018,
Public Works is requesting the Washington State Department of
Transportation to release funds for construction; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the
Chair acknowledging the project has been reviewed and is consistent with
the agency's comprehensive plan for community development; and
WHEREAS: Public Works staff secured the Chairman's signature on the Prospectus on
June 27th, 2018; and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in
the best interest of the public, does hereby ratify the Chairman's signature
on the Local Agency Federal Aid Project Prospectus for the Roadside
Hazard Safety Improvements — Countywide project.
DATED on this 3rd day of July, 2018, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Laura Osiadacz, Chairman
Obie O'Brien, Vice -Chairman
Commissioner
MWashington State
AP Adw
Department of Transportation
Local Agency Federal Aid
Project Prospectus
Prefix
Route ( )
Date 6/27/18
Federal Aid HSIP
Project Number
0005
DUNS Number O1-020-2547
_
Lo je Agency
Project Number CRP 278-17
! WSDOT
` Use Only J
Federal Employer 91-6001349
Tax ID Number
Agency CAAgency
Federal Program Title
Kittitas County Public Works n Y__e__s_ ❑ No
[_f_20.205_❑_Other
Project Title
_
Start Latitude N VARIES Start Longitude W VARIES
Roadside Hazard Safety Improvements - Countywide
End Latitude N VARIES End Longitude W VARIES
Project Termini From -To
Nearest City Name
Project Zip Code (+4)
VARIES VARIES
Ellensburg,
98926-7989
Begin Mile Post End Mile Post Length of Project Award Type
VARIES VARIES NAI U Local ❑ Local Forces ❑ State ❑ Railroad
Route ID Begin Mile Point End Mile Point
City Number County Number County Name
0380 19 Kittitas
WSDOT Region Legislative District(s)
Congressional District(s)
Urban Area Number
South Central Region 13
8
Total
Local Agency
Federal Funds Phase Start
Phase Estimated Cost
Funding
Date
_--(Nearest Hundred Dollaq_
{Nearest Hundred Dollar)
(Nearest Hundred Dollar MonthYear_
P. E. 70,000
70,000
0 March 2018
R/W 0
— -
0
0 ._
Const. X924000
31,725
-- - --
892,275 July 2018
Total 994,000
101,725
892,275
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
VARIES 2
Many roads have roadside hazards and non standard or non-existent delineation.
Description of Proposed Work
------.-..-.-. - -- ---
- --
Description of Proposed Work (Attach additional sheet(s) if necessary)
Install guardrail where necessary to protect roadside hazards. Signs such as advanced warning signs and
chevrons for roadway curves, upgraded stop signs at intersections, and other delineation devices will be
installed throughout the County at various locations.
Local Agency Contact Person Title
Phone
Sara Folk Engineering Services Manager
509-962-7523
Mailing Address City
State Zip Code
411 N Ruby ST, Suite I Ellensburg
WA 98926
-
By ----------------
A-pproving Authority
Project Prospectus
Title Public Works Director
ry
Dateb j.� /d
Uvi rorm 14u-1 ui Paget
Revised 04/2015 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
Roadside Hazard Safety Improvements
- Cot
6/27/18
Type of Proposed Work
Project Type (Check all that Apply)
Roadway Width
Number of Lanes
❑ New Construction ❑ Path / Trail
❑ 3-R NA
2
❑ Reconstruction ❑ Pedestrian / Facilities
❑ 2-R
❑ Railroad ❑ Parking
L' Other
❑ Bridge
Geometric Design Data
Description
Through Route
Crossroad
EV: Principal Arterial
❑ Principal Arterial
Federal❑Urban
�' MinorArterial
El Urban
El Minor Arterial
Functional
Rural
CCollector
❑ Rural
❑Collector
Classification
❑ NHS
Major Collector
El NHS
❑ Major Collector
Minor Collector
❑ Minor Collector
❑ Local Access
❑ Local Access
❑ Flat ❑ Roll U Mountain
❑ Flat ❑ Roll ❑ Mountain
Terrain
Posted Speed
VARIES
Design Speed
VARIES
Existing ADT
VARIES
Design Year ADT
VARIES
Design Year
2018
Design Hourly Volume (DHV)
NA
Performance of Work
Preliminary Engineering Will Be Performed By
Others Agency
Kittitas County Public Works / Consultant
10 % 90
Construction Will Be Performed By
Contract Agency
Contractor
100 %.I 0 ode
Environmental Classification
_..-.._
❑ Class I - Environmental Impact Statement (EIS)
Class II - Categorically Excluded
(CE)
❑ Project Involves NEPA/SEPA Section 404
L Projects Requiring Documentation
Interagency Agreement
(Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
Non anticipated.
uvi rurm 14u-1UI Page
Revised 04/2015 Previous Editions Obsolete
Agency Project Title Date
Kittitas County Public Works Roadside Hazard Safety Improvements - Col 6/27/18
Right of Way
❑✓ No Right of Way Needed ❑ Right of Way Needed
* All construction required by the ❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the exiting rioht of way.
Utilities I Railroad
❑ No utility work required
[✓ All utility work will be completed prior to the start
of the construction contract
❑All utility work will be completed in coordination
with the construction contract
U No railroad work required
❑ All railroad work will be completed prior to the start of
the construction contract
[-]All the railroad work will be completed in coordination
with the construction contract
Description of Utility Relocation or Adjustments and Existing Major Structures Involved in the Project
No anticipated or known utility conflicts
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the
Remarks
Yes I✓, No
This project has been reviewed by the legislative body of the administration agency or agencies, or it
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Ag(
Date By
DOT Form 140-101
Revised 0412015
Page 3
Previous Editions Obsolete