HomeMy WebLinkAboutResolutionAuthorizingChairSignatureProspectusRdsideHazardSafetyImprovementsKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: June 19, 2018
ACTION REQUESTED: Approve the Resolution Authorizing the Chair's signature on
the Local Agency Federal Aid Project Prospectus for the
Roadside Hazard Safety Improvements -Countywide Project
BACKGROUND: The Roadside Hazard Safety Improvements -Countywide
project will provide for safety improvements on several
different road segments to lessen the severity of run -off -the -
road accidents by installing guardrail where necessary to
protect roadside hazards. Signs such as advanced warning
signs and chevrons for roadway curves, upgraded stop signs at
intersections, and other delineation devices will be installed as
recommended per MUTCD requirements to also prevent run-
off -the -road accidents.
Public Works successfully received Highway Safety
Improvement Program (HSIP) federal funds in the amount of
$689,000 with no local match requirement if construction is
authorized prior to April 30, 2019. This project was identified
as the #1 priority in the Kittitas County 2017 Safety Plan, and
this project addresses safety improvements to those roadway
segments identified in the safety plan.
This project will be tied with the 2018 Kittitas County Safety
Improvements Project, and the two projects will be advertised
for construction as a single contract.
Public Works is preparing to advertise the project for
construction in the fall of 2018 and is requesting the release of
the Federal Construction Funds. This requires the Local
Agency Federal Aid Project Prospectus to be signed and
approved by the Chair of the BOCC.
INTERACTION: Public Works
RECOMMENDATION: Motion to approve the Resolution Authorizing the Chair's
signature on the Local Agency Federal Aid Project Prospectus
for the Roadside Hazard Safety Improvements -Countywide
HANDLING: Return one (1) original to Public Works
ATTACHMENTS: Resolution
LEAD STAFF: Sara Folk, Engineering Services Manager
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
AUTHORIZING THE CHAIR'S SIGNATURE ON THE LOCAL AGENCY
FEDERAL AID PROJECT PROSPECTUS FOR THE ROADSIDE HAZARD
SAFETY IMPROVEMENTS -COUNTYWIDE PROJECT
WHEREAS: The Roadside Hazard Safety Improvements -Countywide Project will
provide for safety improvements on several different road segments to
lessen the severity of run -off -the -road crashes by installing guardrail
where necessary to protect roadside hazards, and installing signage and
other delineation measures to prevent run -off -the -road crashes; and
WHEREAS: This project will be tied with the 2018 Kittitas County Safety
Improvements project, which also provides for safety improvements on
several roadway segments countywide to lessen the severity of run -off -
the -road accidents by installing guardrail to protect roadside hazards; and
WHEREAS: Public Works received Highway Safety Improvement Program federal
funds in the amount of $689,000 with no local match requirement if
construction is authorized prior to April 30, 2019; and
WHEREAS: In preparation to advertise the project for construction in the fall of 2018
Public Works is requesting the Washington State Department of
Transportation to release the Federally Funds for construction; and
WHEREAS: A Local Agency Federal Aid Project Prospectus must be executed by the
Chair acknowledging the project has been reviewed and is consistent with
the agency's comprehensive plan for community development; and
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in
the best interest of the public, does hereby approve the Chair's signature
on the Local Agency Federal Aid Project Prospectus for the Roadside
Hazard Safety Improvements -Countywide Project.
DATED on this 19th day of June, 2018, at Ellensburg, Washington.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY,
WASHINGTON
Laura Osiadacz, Chairman
Obie O'Brien, Vice -Chairman
Paul Jewell, Commissioner
Washington State
MoAll
Washington
of Transportation
Local Agency Federal Aid
Project Prospectus
DOT Form 140-101 Page 1
Revised 04/2015 Previous Editions Obsolete
Prefix
Route
( )
Date
6/13/18
Federal Aid
Project Number
HSIP
0005
DUNS Number
O1-020-2547
Local Agency
CRP 278 17
r WSDOT l
Federal Employer
91-6001349
Project Number
` Use Only J
Tax ID Number
Agency
CA Agency
Federal Program Title
Kittitas County Public Works
❑d Yes ❑ No
720.205 ❑ Other
Project Title
Start Latitude N VARIES
ngitude W VARIES
FEndrtLLo'nqitude
Roadside Hazard Safety Improvements - Countywide
End Latitude N VARIES
W VARIES
Project Termini From -To
Nearest City Name
Project Zip Code (+4)
VARIES VARIES
Ellensburg,
98926-7989
Begin Mile Post
End Mile Post
Length of Project
Award Type
VARIES
VARIES
NA
Z✓ Local ❑ Local Forces ❑ State ❑ Railroad
Route ID
Begin Mile Point
End Mile Point
City Number
County Number
County Name
0380
19
Kittitas
WSDOT Region
Legislative District(s)
Congressional District(s)Urban
Area Number
South Central Region
13
$
Total
Local Agency
Federal Funds
Phase Start
Phase
Estimated Cost
Funding
Date
Nearest Hundred Dollar
Nearest Hundred Dollar
Nearest Hundred Dollar
Month Year
P.E.
60,000
60,000
0
March 2018
RAN
0
0
0
Const.
689,000
0
689,000
July 2018
Total
1749,000
60,000
689,000
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width
Number of Lanes
VARIES
2
Many roads have roadside hazards and non standard or non-existent delineation.
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Install guardrail where necessary to protect roadside hazards. Signs such as advanced warning signs and
chevrons for roadway curves, upgraded stop signs at intersections, and other delineation devices will be
installed throughout the County at various locations.
Local Agency Contact Person
Title
Phone
Sara Folk
Engineering Services Manager
509-962-7523
Mailing Address
City
State
Zip Code
411 N Ruby ST, Suite 1
Ellensburg
WA
98926
By
Approving Authority
Project Prospectus
Title Public Works Director
Date��3
DOT Form 140-101 Page 1
Revised 04/2015 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
Roadside Hazard Safety Improvements
- Cot
6/13/18
Type of Proposed Work
Project Type (Check all that Apply)
Roadway Width
Number of Lanes
❑ New Construction ❑ Path / Trail
❑ 3-R
NA
2
❑ Reconstruction ❑ Pedestrian / Facilities
❑ 2-R
❑ Railroad ❑ Parking
❑✓ Other
❑ Bridge
Geometric Design Data
Description
Through Route
Crossroad
❑✓ Principal Arterial
❑ Principal Arterial
Federal
❑ Urban
❑✓ MinorArterial
❑ Urban
❑ Minor Arterial
Functional
Z Rural
ZCollector
❑Rural
F1 Collector
Classification
❑ NHS
❑✓ Major Collector
❑ NHS
❑ Major Collector
❑✓ Minor Collector
❑ Minor Collector
❑ Local Access
❑ Local Access
Terrain
❑ Flat ❑ Roll ❑✓ Mountain
❑ Flat [:]Roll ❑ Mountain
Posted Speed
VARIES
Design Speed
VARIES
Existing ADT
VARIES
Design Year ADT
VARIES
Design Year
2018
Design Hourly Volume (DHV)
NA
Performance of Work
Preliminary Engineering Will Be Performed By
Others
Agency
Kittitas County Public Works / Consultant
15 %
85 %
Construction Will Be Performed By
Contract
Agency
Contractor
100 %
0 %
Environmental Classification
❑ Class I - Environmental Impact Statement (EIS)
❑✓ Class II - Categorically Excluded (CE)
❑ Project Involves NEPA/SEPA Section 404
Projects Requiring Documentation
Interagency Agreement
(Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
Non anticipated.
uui corm 14u-1 u1 Page
Revised 04/2015 Previous Editions Obsolete
Agency
Project Title
Date
Kittitas County Public Works
Roadside Hazard Safety Improvements - Col
6/13/18
Right of Way
�✓ No Right of Way Needed
❑ Right of Way Needed
"AII construction required by the
❑ No Relocation ❑ Relocation Required
contract can be accomplished
within the exiting right of way.
Utilities
Railroad
❑ No utility work required
0 No railroad work required
❑✓ All utility work will be completed prior to the start
[:]All railroad work will be completed prior to the start of
of the construction contract
the construction contract
❑ All utility work will be completed in coordination
❑ All the railroad work will be completed in coordination
with the construction contract
with the construction contract
Description of Utility Relocation orAdjustments and Existing Major Structures Involved in the Project
No anticipated or known utility conflicts
Involvement
risFAA
any airport located within 3.2 kilometers (2 miles) of the proposed project? ❑ Yes ❑✓ No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency Kittitas County Public Works
Date By
Mayor/Chairperson
DOT Form 140-101 Page 3
Revised 04/2015 Previous Editions Obsolete