HomeMy WebLinkAboutRes to Approve Change Order No 11 for Teanaway Road Paving ProjectKITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
STAFF REPORT
AGENDA SESSION DATE: January 5, 2016
ACTION REQUESTED: Approve Change Order # 11 for the Teanaway
Paving Project.
BACKGROUND: Various quantity over -runs and under -runs, when
calculated together, result in a cost over -run total of
$113,172.43.
Primary contributors to the over -run was the
significant amount of Hot Mix Asphalt needed to
pre -level the roadway and achieve the design cross
slope throughout the entire length of the project.
Also significant were quantity over runs in beam
guard rail, posts, non -flared terminals, anchors,
labor and traffic control made necessary when
guardrail sections were added due to previously
unanticipated steep side slope conditions. These
roadway sections were not identified in the original
FHWA topographic survey.
All additional work was performed in accordance
with appropriate design standards and best
engineering practices under the oversight and to the
satisfaction of the County Engineer.
INTERACTION: Public Works
RECOMMENDATION: Motion to approve Change Order #11 for the
Teanaway Paving Project.
HANDLING: Return a copy of the Resolution to Public Works.
Return two copies Change Order #11.
ATTACHMENTS: Change Order 411
Justification and Cost Analysis
Resolution
LEAD STAFF: Roy Chance, Construction Manager
BOARD OF COUNTY COMMISSIONERS
COUNTY OF HITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2016 -
TO APPROVE CHANGE ORDER #11 FOR
THE TEANAWAY PAVING PROJECT
WHEREAS: Additional Costs are required for Hot Mix Asphalt, guard rail and other
associated items; and
WHEREAS: The Contractor has offered unit price extensions for each; and
WHEREAS: It has been determined that the Change Order Total is $113,172.43. The
Director of Public Works recommends approval of Change Order 411.
NOW, THEREFORE BE IT RESOLVED that the Board of County Commissioners, in
the best interest of the public, does hereby approve Change Order #11 for
the Teanaway Paving Project for the amount of $113,172.43.
DATED on this 5th day of January, 2016, at Ellensburg, Washington.
BOARD OF COUNTY COMMISSIONERS
HITTITAS COUNTY, WASHINGTON
Chair
Vice -Chair
Commissioner
ATTEST:
Clerk of the Board
�p""p s... TO fbf.0
�E OCL
MMTAS COUR"fY
KZTTZTAtS COUNTY
DEPARTMENT OF PUBLIC WORKS
Mark Cook, Director
CHANGE ORDER JUSTIFICATION & COST ANALYSIS
Date: January 5, 2016 Change Order #11
Project Name: Teanaway Paving Project
Project Number: RC 1560-B1
Prepared by: Roy Chance, Construction Manager
Justification:
A significant amount of Hot Mix Asphalt was needed to pre -level the roadway and achieve the
design cross slope throughout the entire length of the project.
Quantity over runs in beam guard rail, posts, non -flared terminals, anchors, labor and traffic
control were also experienced when guardrail sections were added due to previously
unanticipated steep side conditions.
Cost analysis:
The contractor offered extensions of unit costs on all material over runs, which was deemed
reasonable by Public Works.
411 N. Ruby St., Suite #1 TEL (509) 962-7523
Ellensburg, WA 98926 FAX (509) 962-7663
SHEET 1 OF 2
KITTITAS COUNTY
CHANGE ORDER NUMBER
DATE: 01/04/16
DEPARTMENT OF PUBLIC SERVICES
I1
CHANGE ORDER
® Ordered by Engineer in accordance with Section
TO: Granite Construction
1-04.4 of the Standard Specifications
80 Pond Road
Yakima, WA 98901
® Change order proposed by Contractor
ENDORSED BY:
PROJECT TITLE: Tearaway Paving Project
Signature Date
Title:
Contract No. RC 1560 -BI
CONSENT GIVEN BY SURETY: (When
required)
By:
Attorney -in-fact Date
DESCRIPTION OF WORK
YOU ARE ORDERED TO PERFORM THE FOLLOWING DESCRIBED WORK UPON RECEIPT OF AN
APPROVED COPY OF THIS CHANGE ORDER. THE UNDERSIGNED HEREBY PROPOSES TO
UNDERTAKE AND COMPLETE THIS IMPROVEMENT, IN ACCORDANCE WITH SAID PLANS,
SPECIFICATIONS, AND CONTRACT, AND THE FOLLOWING SCHEDULE OR RATES AND PRICES:
This change order facilitates payment to contractor for quantity over runs primarily in I IMA '/z in. PG 64-28 and
additional guardrail.
CONTRACT TIME
No (0) additional working days are added to this contract due to this change order.
ORIGINAL
CURRENT CONTRACT
ESTIMATED NET
ESTIMATED CONTRACT TOTAL
CONTRACT AMOUNT
AMOUNT
CHANGE THIS
AFTER CHANGE
$3,000,300.00
$3,295,206.38
ORDER
$3,408,378.81
$ 113,172.43
APPROVAL RECOMMENDED
APPROVED
Project Engineer Date
Chairperson Date
APPROVED
Board of County Commissioners
Director Date
SHEET 2 of 2
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
CHANGE ORDER ESTIMATE
Teanaway Paving Project
Change Order#11
ITEM
BID
DESCRIPTION
UNIT
UNITPRICE
ESTIMATED
ESTIMATED
NO.
MEAS
QUANTITY
CHANGE
NO.
FROM THE
ORIGINAL
CONTRACT
Sl- Il
LS
$113,172.43
1
$113,172.43
ESTIMATED TOTAL COST