HomeMy WebLinkAboutRoslyn City Hall, Library & Community Center; 1st Floor RenovationAPPLICATION FOR TOURISM-RELATED,LARGE-SCALE
MUNICIPALITY-OWNED CIP LISTING
Applicant Information
Name of Municipality:City of Roslyn
Mailing Address:PO Box 451
Roslyn,WA 98941
Contact Person and Title:Brandi Taklo,City Clerk
Phone:509 649-3105
Email:roslyn@inlandnet.com
Project Title:Roslyn City Hall,Library and Community
Center;1st Floor Renovation
Project Location:201 South First Street,Roslyn WA
Application Requirements
X 1.The project qualifies for lodging tax funds as a capital expenditure of a tourism-
related facility owned or operated by a municipality.
X 2.If this application is not from Kittitas County,the municipality's lodging tax advisory
committee (or equivalent)has been informed of the project and endorsed it.A letter
from the municipalityis included.
X 3.Lodging tax capital project funds are not being substitutedfor other funds that are
already secured or applied for (if applicable).
X 4.A completed project budget is included in the application.
X 5.A detailed 8 ½X 11 vicinity map that clearly shows the location of the project is
included.
APR 1 4 200
1
Tourism-Related,Large-Scale Municipality-Owned Capital Project Narrative
1.Project Description:Please describe the project in detail.Indicate the major work to be
completed,any milestones that need to be overcome in order for the project to move forward,and
include a comparison of existing and proposed conditions.
2.Kittitas County Tourism Infrastructure Plan:Please explain how the project meets the Goals
and Actions in the Kittitas County Tourism Infrastructure Plan as adopted.Also,describe the
specific county tourism infrastructureneeds the project addresses and how the project directly
increases tourism.Explain how the improvementswill promote tourism in Kittitas County and
indicate specifically how the improvementswill directly increase economic activity resulting from
tourists.
3.Real Property:If real property acquisition is a component of the project,please explain.
Include any information of property already secured or evidence of the ability to secure the real
property.
4.Coordination:Please explain how this project has been coordinated with other jurisdictionsas
well as affected stakeholders.Please include letters of support from stakeholders.
5.Studies:Please attach any feasibility or other studies that demonstrate linkages between the
proposed project and the anticipated tourism impacts.Also please include your
operations/maintenancestrategy and other plans for long-term project sustainability(how the
facility or facilities will be operated and maintained over at least five years following completion).
6.Project Readiness:Please provide a detailed project schedule,including milestones necessary
for completion as mentioned in question 1 above.On the schedule,indicate items completed and
exactly where in the schedule the project is at this time.Be sure to include expected completion
date.
7.Applicant Certification:Please sign below in agreement with the statementof certification.
Certification is hereby given that the informationprovided is accurate and the applicable
attachments are complete and included as part of the application package.
I further certi hat he a plication thresholds are met at the time of application.
S gn ure of Offici presentative Titi Date
2
/CITY OF ROSLYN
National Historic District and Preserve America Community
Commissioner Paul Jewell
Kittitas County Lodging Tax Committee
2015 West 5th Avenue,Suite 108
Ellensburg,WA 98926
April 11,2017
Dear Commissioner Jewell,
Roslyn's Lodging Tax Committee fully supports the funding for the completed renovation of
Roslyn's historic City Hall.
A grant from the Kittitas Lodging Tax Committee would allow the City of Roslyn to finish a
larger Library space and a community center that will also be a venue for events and meetings.
Many community funding groups have contributed time and effort to this renovation for over ten
years.A completed project would provide much satisfaction and fill a great need.
We support this project and look forward to you your response.
Sincerely,
ine Brodine Andy Januszkieciwz Jeff Adams
City of Roslyn
2015 16t 5t.,P.O.Box 451,Roslyn,WA 98941
PH 509-649-3105,FAX 509-649-3174
R_ogyndDin1andnet.com
1
1.Project Description -Please describe the project in detail.Indicate the major work to be
completed,any milestones that need to be overcome in order for the project to move
forward,and include a comparison of existing and proposed conditions.
The proposed project is to make renovations to the first floor of what is commonly called Roslyn's
Old City Hall with the possibilityof completing outside landscapingwhich would finalize a long-
term project.The work will preserve a significant historic structure and will be a model example
of geotourism in Upper Kittitas County.As defined,geotourism "sustains or enhances the
geographical character of a place -its environment,culture,aesthetics,heritage and the well-
being of its residents."
This rustic,vernacular structure was constructed at the turn of the 20th century as a recreational
and social hall for the town's coal miners and their families.The building is on both the National
and Local District Registers.The current condition of the building stems from 2001 when it was
badly damaged in the Nisqually Earthquake.It is an anchor building of the Roslyn National
Register Historic District and still in need of major repair.Community members,along with
various funders,have been working hard to stabilize and repair this public building for years.
The building renovationbegan in 2004 and the vision remains:
-Enhance the Roslyn community and the Upper Kittitas County region by expanding space
for the Roslyn Public Library and creating a Community Center for meetings,art,and
educational and cultural activities.
-Preserve a pivotal structure in Roslyn's historic district and expand its uses.
The building played a key role in the Roslyn's culture,providinga gathering space for reunions,
weddings,performances and funerals for many of Roslyn's 26 ethnic and cultural groups.The
need for a large community gathering space remains as much a need in 2016 as it did in 1902
when coal company manager B.F.Bush financed the building as an "attractiveplace of recreation
place for miners."
Existing Conditions:
Thus far,the rehabilitationhas included a new foundation that is pinned to bedrock for seismic
stabilization,a concrete slab for the ground floor,removal of hazardous materials,and an updated
heating and cooling system.The ground floor space was once a public pool for Roslyn miners.It
now is an enclosed space with handicapped accessible restrooms,the City Council's meeting
chambers and temporary space for the public library.The first floor remains in a condition
unsuitable for public occupancyor use.
Proposed Conditions:
Requested funds will enhance the public space including the final home of the Roslyn Library and
a public space which can accommodate large groups.Funds will pay for structural improvements
4
to the former 1st floor gymnasium so it may serve as community center and venue for large
gatherings,performances and displays.The building will provide adequate space for the library
currently located in crowded quarters.City Hall operations and meeting space will be on the
ground floor while the library and a large community space will inhabit the 1st floor.
Work involvesremoving a small stage and adding ADD accessible bathrooms.This phase would
also complete installationof fire sprinklers,electric,plumbing,and heating systems.It would
modernize both the library and the large community and venue space.Details of the plan include:
•Install 1st floor wall insulation
•Install interior and exterior doors;refurbish interior windows
•Complete ground floor ceiling installation
•Retain significant amounts of original 1st floor wall finishes
•Add signage,toilets,accessories and partitions
•Complete fire sprinkler systems for ground and 1st floors
•Install bathrooms on 1st floor;install kitchenette
•Install HVAC system for 1st floor
•Complete electrical work for ground floor and affected areas on 1st floor
•Refurbish exterior siding where needed
•Replace exterior siding where needed
•Provide exterior landscaping
2.Kittitas County Tourism Infrastructure Plan:Please explain how the project meets the
Goals and Actions in the Kittitas County Tourism Infrastructure Plan as adopted.Also,
describe the specific county tourism infrastructureneeds the project addresses and how
the project directly increases tourism.Explain how the improvementswill promote
tourism in Kittitas County and indicate specifically how the improvementswill directly
increase economic activity resultingfrom tourists.
The large,two-story Roslyn City Hall is the first major historic building tourists see when they
drive,bike or walk into town.Because the building is clearly marked City Hall and Library,tourists
routinely stop to ask for suggestions about places to stay,to visit or have a meal.The kind service
proved by City staff augments that of the Roslyn Visitor Center which is open only on weekends.
The Roslyn Library serves both Kittitas County residents and tourists by presenting public
presentations on history or literature.The library also serves as a resource for historic
informationfor many people interested in the past and present of the area.
5
Roslyn City Hall,Library and
Community Center -circa 1910
II
I
Roslyn City Hall,Library and
6CommunityCenter-2016
Goals
While this project addresses many of the goals,it particularlyresponds to Goals 1,5,6,7,10 and
11.
Goal 1 -Develop integrity of place
The entire footprint of Roslyn became a National Historic District in 1978,and the Old City Hall
was a major contributingfactor to that designation.This important public building is on the
Local Historic Designation;State Heritage Register;and National Register of Historic Places.
It serves as the anchor building of the Roslyn Historic District.Since the Old City Hall is the first
major building tourists see as they arrive in town,its presence sets the stage for their experience
in the remainder of the historic town.
Goal 5-Involve the community
The Old City Hall has been a community gathering place for over 100 years.Now,the damage to it
has made it too dangerous to it being too dangerous for occupation.Sadly,over the years of its
disuse,it became a storage space for lumber,metal and all nature of stuff.However in the last
twelveyears,the City of Roslyn and the Friends of the Roslyn Library have collaborated to support
its structural repair and renovation.Community engagement has been constant.To date,over
$1.5 million dollars from federal,community,state,county and private funds have been spent on
exterior and ground floor renovations.
Currently,there are no City-owned buildings or facilities that can accommodate even a small
public gathering.The current library is in temporarycramped quarters in the partially restored
building and the City Hall functions are carried out in a crowded into the remaining ground-floor
space
The intended public use of the 1st floor building upon project completion is as a Community
Center,performance venue,and Library.All building restorationis designed to meet ADA
standards and the facility will provide significant public access.
Community meetings in August and September of 2015 led to the final decisions about the use
first (or upper)floor as a library,communitygathering space and performance center.(SEE
APPERNDIX A FOR COMMUNITY NOTES)
Goal 6 -Benefit the community
Having a completed anchor structure that community groups and business can use for large scale
events meets a huge need.Currently,there are only two venue spaces in town that can hold over
100 people and one is used by people or groups outside the local area.The second space,
Stonehouse 101,recently reopened as a rentable venue has weekend bookings up to six months in
advance.Roslyn's City Clerk reported that she gets five or six calls daily from people outside
Roslyn looking for a venue for a wedding,party or reunion.
7
In order for Roslyn's two inns,restaurants,bars and shops to thrive,the town needs a steady
stream of tourists.Having a space that can be rented for reunions,weddings,art installationsand
performances brings many people to town who then frequent local businesses.The towns
economic vitally depends on it.
The Roslyn Library is of key benefit to the community.Library programs include:Book Club,Story
Time,Ready to Read in Roslyn,Baby &Me.Summer Reading Program,Book a Librarian,World
Affairs Series ,One Book One County,Adult Lecture Series,Stitching Circle,Art in Our Library and
The Imagine Academy.
Goal 7-Encourage businesses to sustain natural habitats,heritage sites,aesthetic appeal
and local culture
The final renovationof this buildingwill serve as a model for the 25 businesses housed in historic
structures in town.Its completion will help maintain the standard of historical appearance which
entices tourists to the town and hence to businesses For example,the Amazon.com Company
chose Roslyn to film the film,The Man in the High Castle due to the historic nature of the
downtowncore.The community space will provide a place for art,music,community and historic
functions.
Goal 10 -Proactively plan
The Roslyn City Hall,Library and Community Center building is 114 years old.With renovation,it
can last another 114 years or longer.Creating a useful,large-scale community and event space
gives an old building meaning and purpose.Its character is an important keystone to encourage
historic preservation in Roslyn's downtowncore,which in turn supports preservation in
residential and commercial overlay zones in town.
Goal 11-Interpret interactively
Roslyn's Library is a repository of Roslyn History.The Librarian and her "mostly "volunteerstaff
regularly engage visitors in learning about the engaging history of Upper Kittitas County.Since
the building sits adjacent to the historic Coal Mining Trail,visitors are often directed along its path
and as well as to the Roslyn Cemetery Complex which showcases the 26 ethnic and cultural
cemeteries and to the 300-acre Roslyn Urban Forest.
Action Items:
Heritage Tourism:Action 8 -Historic district designation and interpretation
As stated in Goal 1,the City Hall building staff disseminates informationabout the historical and
tourist-friendly aspects of town to tourists on a daily basis.The physical location of the building is
also a link to the Coal Mines Trail and the Roslyn Urban Forest,both important to Roslyn's coal-
mining history.
8
Cultural Tourism:Action 14 -Create facilities and exhibits
Since the library is a repository of historic information,having a modernized library will make
Roslyn's connection with tribal history more available to tourists.One example is that what is now
Roslyn's Runje Field was once a seasonal gathering place for tribes from both sides of Snoqualmie
Pass.While there is no signage designating that,it is consistent with local knowledge.
Cultural Tourism:Action 15 -Art installations
Roslyn needs a place for artists to display work.While local artists routinely display art on the
walls of Roslyn Café,the Brick,Marko's Place,the Roslyn Candy Company,Basecamp Books and
Bites,and Maggie's Place,the need for larger installationsand exhibits is great.For example,the
Roslyn Art Festival has need of a space for sixty pieces of art annually.
Cultural Tourism:Action 16 -Music,dance,and drama performance facilities
The large renovated venue will provide a place for theater and drama groups,music and dance
groups,to host plays and music.The Upper County's production company,Boulet Productions,
has been deeply involvedin the community discussions about renovatingthe building.During
2014-2015,the company produced Oliver,the Railway Children and Anne of Green Gables in the
proposed event space -as a demonstrationof potentialuse before occupancy was terminated
because of fire and safety codes.All productions had standing room only.
Cultural Tourism:Action 18 -Visitor centers
As a de facto visitors'center during the weekdays,the City Hall can easily continue to provide
informationabout natural and heritage events including mining,logging,farming,and other
agricultural,recreational,heritage,and cultural sites.
3.Real Property -If real property acquisition is a component of the project,please explain.
Include any information of property already secured or evidence of the ability to secure the
real property.
The building is owned by the City of Roslyn.
Tax Parcel Number:496234
Legal Description:Parcel #49 6234,ACRES 1.32,CD.6196;SEC.17
GPS Coordinates:1518133
Northing:689167
Projection:WA State Plane South
4.Coordination:Please explain how this project has been coordinated with other
jurisdictionsas well as affected stakeholders.Please include letters of support from
stakeholders.
9
The City of Roslyn has been working in partnership with organizations and individualssince 2004
to restore this unique space.This project will not be abandoned;the building is a principal City
asset which needs modernization to serve current and future generations of both community
members and tourists.The goal of this project is the full-time occupancyof the building not only
by City and Library staff but also by members of cultural,historical,artistic and business
community groups.To get to this point the City has encouraged a long visioning process.
The operations and maintenance strategy is simple:it will be maintained as all Roslyn's City assets
are maintained -by city staff including the Public Works Department.Funding will be provided by
the annual City budget.
Financial Stakeholdersinclude those who have invested funds to date:
$798,000 Congressional Appropriation,2009
$300,000 Congressional Appropriation,2006
$150,000 Washington State Legislative Budget,2005
$181,000 Washington State Heritage Capital Projects
$388,000 Washington State Department of Commerce,2015
$41,000 Kittitas County Infrastructure ImprovementFund,2003
$59,000 Kittitas County Infrastructure ImprovementFund,2005
$20,000 City of Roslyn Capital Facilities Fund,2005
$30,000 Friends of the Library,Building Committee,Individuals
$5,000 Hart Foundation
$5,000 Puget Sound Energy Foundation
$2,500 Plum Creek Timber Company
$1,979,500 --TOTAL
5.Studies:Please attach any feasibility or other studies that demonstrate linkages between
the proposed project and the anticipated tourism impacts.Also please include your
operations/maintenancestrategy and other plans for long-termproject sustainability(how
the facility or facilities will be operated and maintained over at least five years following
completion).
The Kittitas County Tourism Plan study supports the concept of this work.According to the plan:
-100%of the 'historical'tourists'said they would,or would likely visit Kittitas County
now that they were aware of the extentof historical destinations and attractions
-85%said they were likely or maybe likely because of historical assets or landmarks
-22%of the respondents wanted more historical informationand 20%wanted more
cultural information
-60%of the follow-up respondents will visit more now that they are aware of
attractions,art galleries,studios,and performances
10
On August 12 and September 30,2015,the city sponsored community meetings to air opinion
about the use of the first floor and to determine interestand commitmentto the project.People
represented seven business and six organizations.
This project is shovel-and permit-ready.The City has architect-designed plans and that all is
needed to proceed is funding.The City can assure these matching funds:
$260,000 Design work and plan set -current state grant
$750,000 Sale of City property and unsecured loan
6.Project Readiness:Please provide a detailed project schedule,including milestones
necessary for completion as mentioned in question 1 above.On the schedule,indicate
items completed and exactly where in the schedule the project is at this time.Be sure to
include expected completion date
2006 -Community visioningactivities
2010 -A foundation and the rehabilitationof the ground floor were completed.
2012-An emergency,temporary roof was added and front and west-side exterior siding replaced
2017 -A roof update,addition of a new entrance and ADA access
2018-2019 -install 2nd floor ceiling and wall insulation;install interior and exterior doors;
refurbish interior windows;complete new finishes on 1st floor and ground floor where needed;
install signage,toilets,accessories and partitions;complete fire sprinkler systems for ground and
1st floors;install bathrooms on the 1st floor;install kitchenette;install HVAC system for 1st floor
and modify where needed on ground floor;complete electrical for 1st floor and effected areas on
1st floor;refurbish exterior siding where needed.
The timeline includes putting out a bid for contractors in a public process,choosing a contractor
with expertise in historical reconstruction and beginning work on refurbishing the first floor.
Work may include landscaping and paving for off-street parking.
The City of Roslyn and the Friends of the Roslyn Library,a local non-profit,all-volunteercitizen
organization,have been working together in partnership since 2004 to restore the Historic
Community Center,Library and City Hall Building,with financial assistance from many other
friends.The City of Roslyn has successfullymanaged the renovation project,involvingcitizens and
community groups in all phases and complying with all grant requirements and reporting
deadlines.
The restored historic building will continue to be in the ownership of the City of Roslyn.The
Project Manager of this phase is Jeff Adams,a 5th generation Roslyn citizen who has many years'
experience in construction and renovation.He is supported by a team including Councilman
11
Cordy Cook,Roslyn mayor and Planning and Historic Preservation Commission Chair Janine
Brodine.
12
Appendix I -Community Visioning by Project Stakeholders
September 30,2015
7:00 Welcome and report from the joint City Council/RPHPC committee
7:30 Small group idea and discussion
8:00 Feedback between groups
8:15 Closure and next steps
Review of the Process
•We had a community discussion on August 12
•The City Council and RPHPC members reviewed th ideas and developed rough plans
•This community meeting is convened to review and understand options
•City Council chooses the final plan
•The project continues to completion
What we know
•Some permits and approvals have expired
•There is a limited amount of money for resign and engineering'
•Some structural pieces form the original plans have been completes
•The building belongs to the City
•The City Council has been authorized to make the final decision on the plans
•Each interest group agrees on the three most important elements of the building design to
meet their needs
•Each group meets to come up with their top there and also to code them
U -unanimous C -consensus S-split
Summarization -Groups all seemed in agreement to:
•Moving the library back upstairs
•Having City offices and related work be on ground floor
•Removing the stage but keeping the 'footprint'of the gym as close to current size as
possible
•Sharing the space
13
The Library
1)U --Keep space (current footprint size)of current existing library including storage and
event space
2)U -Come to a final plan and not change it (phasing is okay but not piece meal)
3)C --Easily accessible space between the library itself and an event space (doesn't mean
ADA)
The City
1)U -Have admin offices on ground floor where most Council and Committee work would
occur
2)U -Main library moves back upstairs including stacks,computer lab and office
3)C-Maintain gym footprint relativeto the edge of the proposed Bolla stairway
The Arts
1)U --Want to keep the large space -the entire gym floor maybe without or without the
balcony
2)U --Power for lighting and sound (4-50 amps)
3)U --Our group sees potentialin multiple configurations that using the large space could
accommodate
The Community
1)U -have an event space that's big enough but intimate enough -the present space to
the stage edge/remove stage
2)U -Have a kitchen and a multi-purpose'green'room that could be used for instruction
3)U --Have upstairs be for library and community and the ground floor for City Admin
and Council;
Attendeeson September30 and August 12
Roslyn Businesses -Roslyn Rag,,Roslyn Candy Company,Copper Spring Farm,Basecamp Books and
Bites,Maggie's Pantry,Red Bird Café,High Country Artist
Roslyn Library and Friends of Library -Erin Krake,Cindy Gregory,Tuesday Bosch,Marc Brodine,
Katia Merkel
Boulet Productions-Jock Young,Lynna Bates,Karen Ingalls.]imMiller,Susan Bronkhurst,Lily
Bates
High Country Artists:Charlene Kauzlarich
Citizens Advisory Committeefor Roslyn's Urban Forest -Margaret Bryant,Ellie Belew
Community-Maura Woodwell,Chris and Katie Fitch;Susie Martin,Liz Wise
City of Roslyn -Myke Woodwell,Mitch Long,Andy]anuszkiewicz,Chis Martin
14
Tourism-Related,Large-Scale Municipality-Owned Capital Project Budget
Funding Sources for 2018-2019 Phase of building renovation
Funding Sources
Lodging Tax Funds Request $500,000 to be requested
Sale of City property and unsecured loan $400,000 pending
Washington State Department of Commerce,2015 $260,000 secured
(portion of $388,000 grant went to 2017 work)
Volunteer management and community labor $40,000 secured
Total Funding Source $1,200,000
Project Expenses
Real Property or "Right-of-Way"Acquisition Cost $0.00
Capital Asset Cost $0.00
Construction Cost or "Hard"Cost:$710,000
install 2nd floor ceiling and wall insulation;install interior
and exterior doors;refurbish interior windows;complete
new finishes on 1st floor and ground floor where needed;
install signage,toilets,accessories and partitions;complete
fire sprinkler systems for ground and 1st floors;install
bathrooms on the 1st floor;install kitchenette;install HVAC
system for 1st floor and modify where needed on ground
floor;completing electrical for 1st floor and effected areas
on 1st floor;refurbish exterior siding where needed.*
*Project management does not have sufficient
informationto break out individual costs.
Construction Management $20,000
Engineering fees,permitting costs,special inspections,$10,000
Landscaping $100,000
Soft Cost -architectural design and details $360,000
Total Project Costs $1,200,000
This project budget,being submittedas part of this application,will be considered an estimate.As
the project progresses through the four-step process,applicants will be required to update the
project budget as more informationbecomes available and at the time of funding award.
*At the time funding awards are being considered (Steps 3 and 4),verifying documentation shall
be required and attached to the final project budget.Verifying documentation may include award
letters,letters of commitment,or loan approval documentation.If the funding source includes
applicant funds,proof of available funding in the form of a letter of commitmentfrom an
authorized body or representative of the applicant is adequate.
15
Vicinity Map -Roslyn,Washington
Location of Historic Library,Community Center and City Hall Building:
201 South First Street,at Dakota Avenue
*HISTORIC LIBRARY,COMMUNITY
>D CENTER &CITY HALL BUILDING
E
South Ave
16
dhy
Allyson Brooks Ph.D.,Director
State Historic Preservation Officer
April 12,2017
Commissioner Paul Jewell
Kittitas County Lodging Tax Committee
2015 West 5"'Avenue
Suite 108
Ellensburg,WA 98926
In future correspondence please refer to:
Project Tracking Code:042814-33-COMM
Property:Roslyn City Hall;201 S 16'St,Roslyn
Re:Letter of Support for Kittitas County Grant
Dear Commissioner Jewell,
The Department of Archaeology and Historic Preservation (DAHP)fully supports the grant
application put forth by the City of Roslyn for funds to finish the top floor of Old City Hall.We
reviewed this project in 2014 and the City of Roslyn has been working tirelessly for many years
to realize their vision for this exquisite historic jewel in the heart of downtown Roslyn.
The project rests on the merits of repurposing an underutilized historic structure,which if
properly rehabilitated as is currently proposed,will continue to serve the citizens of Roslyn and
Kittitas County for several generations.Rehabilitating this structure also provides a tangible
connection to the past and its adaptive reuse will strengthen community relationships.A grant
from the Kittitas Lodging Tax Committee will allow the City of Roslyn to create a much larger
library space and a community center which will also be a venue for events.
We support this project and hope you will give it full funding.We thank you for this opportunity
and would be happy to provide any additional insight or comments on this project as necessary.
Sincerely,
Nicholas Vann,AIA
State Historical Architect
Department of Archaeology and Historic Preservation
(360)586-3079
nicholas.vann@dahp.wa.gov
State of Washington •Department of Archaeology &Historic Preservation
P.O.Box 48343 •Olympia,Washington 98504-8343 •(360)586-3065
www.dahp.wa.gov
)
Tl¯!E SPRUŒ
MOOSE INN
ilo2 E.Pennsylvania Ave.
Roslyn,WA 9894]l
5°9 554-2966
Commissioner Paul Jewell
Kittitas County Lodging Tax Committee
2015 West 5th Avenue,Suite 108
EIIensburg,WA 98926
April 11,2017
Dear Commissioner Jewell,
We fully support the grant application put forth by the City of Roslyn for funds to finish the top
floor of City Hall.
A grant from the Kittitas Lodging Tax Committee would allow the City of Roslyn to create a much
larger Library space and a community center that will also be a venue for events and meetings.
As business owners and innkeepers,we are often asked if we will rent the entire inn to groups
for meetings and events.We have been approached about using our space for weekend retreats
by quilters,corporations,fish and game folks,writers,shamans and artists.They are delighted
with our accommodations and the catering possibilities from the Red Bird Café below the inn,
but when it comes to the question of large meeting space,and breakout rooms for small
discussions Roslyn fails miserably,and they take their business somewhere else.The new Library
design has created a wonderful,large,flexible,multi-purpose space.It would be a fabulous
support for both local community life as well as local business.
We enthusiastically support this project and hope you will give it full funding!
Sincerely,
John Macisaac and Kate Regan
Proprietors,The Spruce Moose Inn
April 12,2017
Commissioner Paul Jewell
Kittitas County Lodging Tax Committee
2015 West 56 Avenue
Suite 108
Ellensburg,WA 98926
Dear Commissioner Jewell,
As members of the Boulet Productions Board we fully support the grant application put
forth by the City of Roslyn for funds to finish the top floor of City Hall.
A grant from the Kittitas Lodging Tax Committee could allow the City of Roslyn to create a
much larger library space and a community center which will also be a venue for various
events.We in Upper County need this space as it further enhances opportunitiesto
support the arts through live performance which our group currently provides three to
four times annually.We struggle to find a venue and this space would suit our needs.
We supportthis project and hope you will give it full funding.
We thank you for this opportunity.
Sincerely,
This letter was approved by the Boulet Board,April 12,2017
Board of Boulet Productions:Jock Young,Lynna Bates,Jeff Miller,Lily Bates,Jen McGarry,
Susan Bronkhorst,Joseph Farnik,Lisa French,Jim Miller
Boulet Productions |201 Elk Haven Rd,Cle Elum,WA 98922
HIGH COUNTRYARTISTS
Carpenter House Museum &Art Gallery
rlists C30e2 Wenst 8r9e2e2
April 13,2017
CommissionerPaul Jewell
Kittitas County Lodging Tax Committee
2015 West 5th Avenue,Suite 108
Ellensburg,WA 98926
Dear CommissionerJewell,
We fully supportthe grant application put forth by the City of Roslyn staff.We urge
your approvaland funding of this request so that the City can completethe second floor
and exterior rehabilitationof the City Hall.The time is certainly right for this project to
be completed NOW so that people can start utilizing a much larger Library space,City
Hall improvement,and a much longed for renovatedgymnasium which will provide
room for art,culture,and theater displays.
Please give this project full funding.
Sincerely,
Charlene Kauzlarich
Treasurer
RatingsCriteria and Score Card
Tourism-Related,Large-Scale,Municipality-Owned Capital Projects
1.Criteria:Kittitas County Tourism InfrastructurePlan
Points Possible:60 Score Awarded:
How closely does the application Up to 20 Comments:
meet the goals to further points
geotourism opportunities as
presented in Section 6 of the Awarded:
Plan?
How closely related is the High =20 Comments:
application to the high,Moderate =15
moderate,or low priority Action Low =10
Tasks contained in Section 7 of
the Plan?Awarded:
How effective will the project be Up to 20 Comments:
in directly promoting tourism Points
and increasing economic activity
resulting from tourists?Awarded:
2.Criteria:Stakeholder Support
Points Possible:10 Score Awarded:
Has the applicant clearly Up to 10 Comments:
described how the project is points
being coordinated with other
interested parties?Are the Awarded:
stakeholders supportive?
3.Criteria:Project Readiness and Feasibility
Points Possible:30 Score Awarded:
Can the project be completed Yes =10 Comments:
within 5 years?No =0
Awarded:
Has the applicant clearly Up to 20 Comments:
articulated a feasible long term points
maintenance and operations
strategy for the project?Awarded:
Total Score Awarded:
3