DEPARTMENT OF PUBLIC WORKS
AGENDA STAFF REPORT
AGENDA DATE: February 7`h, 2017
ACTION REQUESTED: Approve County Road Project for the repair and re-establishment
of Taneum Road from MP 3.80 to MP 3.98
BACKGROUND: Currently Taneum Road from MP 3.80 to MP 3.98 is restricted to
one lane of traffic and under a stop controlled condition. This was
required due to the washout and erosion of the roadway by
Taneum Creek during a high flow event in 2016.
Public Works intends to design the project in house which will
include repair of the roadway, bank and stream stabilization
measures, and possibly some realignment in order to re-establish
two lanes of traffic.
During the budget adoption process the BOCC recommended
including the proposed project and adopted it as part of the 2017
budget. The project is formally included in the annual construction
program for 2017.
Upon CRP approval the project will be designed and constructed
by Public Works staff in 2017. The project will be paid using
county road funds.
INTERACTION: Public Works
RECOMMENDATION: Board of County Commissioners to approve and sign the CRP
form for the Taneum Road Realignment — Slope Stabilization MP
3.80 to MP 3.98 Project.
HANDLING: Return one original to Public Works
ATTACHMENTS: CRP form for Board approval
LEAD STAFF: Lucas Huck
County Engineer
RESOLUTION NO.
BEFORE THE BOARD OF COUNTY COMMISSIONERS OF KITTITAS COUNTY, STATE OF WASHINGTON, in the matter
of initiating a county road project designated as:
CRP NO: 274-17
JOB NO: RC1571-E1
IT IS HEREBY RESOLVED that the Taneum Road from MP 3.80 to MP 4.00 be improved as follows:
Repair a portion of the roadway that has washed out; construct slope
stabilization, re -align, and re-establish two lanes of traffic.
ARTERIAL
ACCESS ❑
This project is hereby declared to be a public necessity and the County Engineer is hereby ordered and authorized to report
and proceed thereon as by law provided. (RCW 36.75.050, 36.80.030, 36.80.070).
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on the Director of
Public Works' estimate, is hereby made in the amounts and for the purposes shown:
PURPOSE
AMOUNT
TOTALS
PRELMINARY ENGINEERING
$ 90,000
CONSTRUCTION ENGINEERING
$ 19,000
RIGHT-OF-WAY ACQUISITION
$ 20,000
SUB -TOTAL
$ 129,000
COUNTY FORCES CONSTRUCTION
$ 0
CONTRACT CONSTRUCTION
$ 626,000
SUB -TOTAL
$ 626,000
TOTAL PROJECT COST
$ 755,000
GRANT OR OTHER FUNDS
$
Grant Source: WSDOT
is
TOTAL COUNTY ROAD FUND ALLOCATION
755,000
i
G. Lucas Ruck, P.E.
County Engineer
® THIS PROJECT IS INCLUDED IN THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM AS
ITEM NO. 04
❑ THIS PROJECT IS HEREBY MADE A PART OF THE OFFICIALLY ADOPTED ANNUAL ROAD PROGRAM IN
ACCORDANCE WITH RCW 36.81.130
IT IS FURTHER RESOLVED THAT:
® THE CONSTRUCTION IS TO BE ACCOMPLISHED BY CONTRACT IN ACCORDANCE WITH RCW 36.77.020 ET.SEQ.
❑ THE CONSTRUCTION IS TO BE ACCOMPLISHED BY COUNTY FORCES IN ACCORDANCE WITH RCW 36.77.065 AND
WAC 136-18.
ADOPTED this 7th day of February 2017.
Attest:
Clerk of the Board
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Vice -Chair
Commissioner