Description Old New Difference SCS Comment
<br />Outside Tunnel Footings 72,920.00$ 73,080.00$ 160.00$ (19,000.00)$
<br />OLD outside wall footings reduced by 19 CY. Estimated reduction of
<br />$19,000.
<br />Concrete 32,680.00$ 20,780.00$
<br />labor Form/Pour/Strip/Sack 36,800.00$ 44,000.00$
<br />Forms/Misc 4,000.00$ 5,300.00$
<br />Pump Truck 3,000.00$ 3,000.00$
<br />73,080.00$
<br />Inside Tunnel Footings 75,800.00$ 83,090.00$ 7,290.00$ 7,290.00$ OK
<br />Concrete 30,800.00$ 35,690.00$
<br />labor Form/Pour/Strip/Sack 38,000.00$ 38,000.00$
<br />Forms/Misc 4,000.00$ 5,800.00$
<br />Pump Truck 3,000.00$ 3,600.00$
<br />75,800.00$ 83,090.00$
<br />Stair Footing 23,400.00$ -$ (23,400.00)$ (23,400.00)$ OK
<br />Concrete 4,000.00$
<br />labor Form/Pour/Strip/Sack 16,800.00$
<br />Forms/Misc 1,400.00$
<br />Pump Truck 1,200.00$
<br />23,400.00$
<br />Outside Tunnel Wall 169,520.00$ 88,840.00$ (80,680.00)$ (80,680.00)$ OK
<br />Concrete 37,620.00$ 11,440.00$
<br />labor Form/Pour/Strip/Sack 97,200.00$ 61,600.00$
<br />Forms/Misc 29,000.00$ 11,500.00$
<br />Pump Truck 3,200.00$ 1,800.00$
<br />ForkLift/Scoffolding 2,500.00$ 2,500.00$
<br />169,520.00$ 88,840.00$
<br />Tunnel Wall to Bottom of Slab 114,860.00$ 146,010.00$ 31,150.00$ 31,150.00$ OK
<br />Concrete 28,160.00$ 22,660.00$
<br />labor Form/Pour/Strip/Sack 69,200.00$ 92,000.00$
<br />Forms/Misc 12,000.00$ 25,250.00$
<br />Pump Truck 3,000.00$ 3,600.00$
<br />ForkLift/Scoffolding 2,500.00$ 2,500.00$
<br />114,860.00$ 146,010.00$
<br />Stairway 15,250.00$ 15,250.00$ -$ -$ OK
<br />Concrete 1,600.00$ 1,600.00$
<br />labor Form/Pour/Strip/Sack 10,800.00$ 10,800.00$
<br />Forms/Misc 2,050.00$ 2,050.00$
<br />Pump Truck 800.00$ 800.00$
<br />15,250.00$ 15,250.00$
<br />Pushwall 80,200.00$ 119,300.00$ 39,100.00$ -$ Drawing 1_S202 shows 12' high wall.
<br />Concrete 16,800.00$ 22,500.00$
<br />labor Form/Pour/Strip/Sack 52,000.00$ 68,400.00$
<br />Forms/Misc 4,000.00$ 10,000.00$
<br />Pump Truck 2,400.00$ 3,000.00$
<br />ForkLift/Scoffolding 5,000.00$ 9,000.00$
<br />Labor- Scaffolding Set Up -$ 6,400.00$
<br />80,200.00$ 119,300.00$
<br />Piers increase height-8EA 24,000.00$ 30,380.00$ 6,380.00$ 6,380.00$ OK
<br />Concrete 660.00$
<br />labor Form/Pour/Strip/Sack 3,200.00$
<br />Forms/Misc/Anchor Bolts 2,520.00$
<br />6,380.00$
<br />Bollards 10 EA -$ 9,000.00$ 9,000.00$ 9,000.00$ OK
<br />Materials 5,500.00$
<br />Labor 2,500.00$
<br />Paint- Sub 1,000.00$
<br />9,000.00$
<br />Retaining Wall Footings -$ 63,700.00$ 63,700.00$ 63,700.00$ OK
<br />Concrete 14,620.00$
<br />labor Form/Pour/Strip/Sack 44,000.00$
<br />Forms/Misc 2,080.00$
<br />Pump Truck 3,000.00$
<br />63,700.00$
<br />Added Exterior 4' Wall- Tunnel -$ 35,380.00$ 35,380.00$ 35,380.00$ OK
<br />Concrete 4,400.00$
<br />labor Form/Pour/Strip/Sack 26,400.00$
<br />Forms/Misc 2,580.00$
<br />Pump Truck 2,000.00$
<br />35,380.00$
<br />Exterior Retaining Walls -$ 91,040.00$ 91,040.00$ 91,040.00$ OK
<br />Concrete 13,640.00$
<br />labor Form/Pour/Strip/Sack 60,400.00$
<br />Forms/Misc 9,500.00$
<br />Pump Truck 3,000.00$
<br />ForkLift/Scoffolding 4,500.00$
<br />91,040.00$
<br />Added Cold Weather Protection 17,600.00$ 17,600.00$ 17,600.00$ OK
<br />Labor 12,000.00$
<br />Diesel/Heater 5,600.00$
<br />17,600.00$
<br />Added Concrete Sidewalk 816.00$ 816.00$ 816.00$ OK
<br />Concrete 250.00$
<br />Labor 500.00$
<br />Forms 66.00$
<br />816.00$
<br />Exterior Concrete Curb-440 Lf -$ 21,220.00$ 21,220.00$ 21,220.00$ OK
<br />Concrete 1,470.00$
<br />labor Form/Pour/Strip/Sack 16,000.00$
<br />Forms/Misc 750.00$
<br />Pump Truck 3,000.00$
<br />21,220.00$
<br />Additional Rebar 25,576.00$ 25,576.00$ 25,576.00$ OK
<br />Subtotal 244,332.00$ 186,072.00$
<br />Transfer Station Concrete Changes
|