HomeMy WebLinkAbout2026-9-150 CDS_ SUPPORTING DOCSKITTITAS COUNTY
COMMUNITY DEVELOPMENT SERVICES
AGENDA ITEM STAFF REPORT
AGENDA DATE: September 15te, 2026
TOPIC• Public Hearing to extend the moratorium regarding Data Centers for an
additional six (6) months, which includes a work plan
ACTION REQUESTED: Request to approve Resolution/Ordinance.
BACKGROUND: On August 10, 2026, the Kittitas Board of County Commissioners adopted
Resolution No. 2026-141 establishing an emergency six-month moratorium on
the acceptance, processing, review, and approval of land use applications for the
siting, establishment, construction, expansion, conversion, or operation of data
centers in unincorporated Kittitas County, pursuant to RCW 36.70A.390. The
statute requires the County to hold a public hearing on the moratorium within 60
days of its adoption.
Kittitas County's land use, zoning, development, environmental, building,
infrastructure, and permitting regulations do not adequately define or classify
data centers and related facilities, or establish appropriate review criteria,
conditions of approval, and mitigation measures for these types of projects.
Community Development Services has prepared a one-year Work Plan, attached
as Exhibit A and incorporated by this reference. The work plan outlines related
studies, stakeholder and public engagement, an analysis of the alternatives, and
the development of Comprehensive Plan policies and development regulations
addressing data centers.
CDS recommends that the Board of County Commissioners extend the
moratorium for an additional six (6) months and proceed with the work plan as
presented in Exhibit A. The extension is necessary, reasonable, to protect the
public health, safety, and welfare of Kittitas County.
INTERACTION: Kittitas County Community Development Services Department (CDS).
RECOATMENDATION: Approve Resolution with Exhibits extending the moratorium for six (6) months.
ATTACHMENTS: Resolution & Associated Exhibits
LEAD STAFF: Chad Bala, Director
Page 1 of 1
Community Development Services "Staff Report", 2026
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO. 2026-.
ADOPTING A WORK PLAN FOR THE STUDY OF DATA CENTER REGULATIONS;
EXTENDING THE EMERGENCY MORATORIUM ON THE ACCEPTANCE,
PROCESSING, AND APPROVAL OF LAND USE APPLICATIONS FOR DATA
CENTERS FOR AN ADDITIONAL PERIOD OF SIX MONTHS PURSUANT TO RCW
36.70A.390.
WHEREAS, on August 10, 2026, the Board of County Commissioners of Kittitas County
adopted Resolution No. 2026-141 establishing an emergency six-month moratorium on the
acceptance, processing, review, and approval of land use applications for the siting,
establishment, construction, expansion, conversion, or operation of data centers within
unincorporated Kittitas County, pursuant to RCW 36.70A.390; and
WHEREAS, RCW 36.70A.390 authorizes a county to adopt a moratorium without first holding
a public hearing, provided a public hearing is held within sixty days of adoption, and further
provides that such a moratorium may be effective for not longer than six months, but may be
effective for up to one year if a work plan is developed for related studies providing for such a
longer period; and
WHEREAS, RCW 36.70A.390 further provides that a moratorium may be renewed for one or
more six-month periods if a subsequent public hearing is held and findings of fact are made prior
to each renewal; and
WHEREAS, the Board held a public hearing on the original moratorium on September 151,
2026, within the time required by law, received public testimony, and adopted or reaffirmed
findings of fact supporting the continued need for the temporary restriction; and
WHEREAS, data centers remain a rapidly evolving land use involving large-scale buildings,
high electrical demand, backup power systems, mechanical cooling systems, water or wastewater
considerations, noise -producing equipment, exterior lighting, traffic and construction impacts,
emergency response considerations, and potential impacts to public infrastructure and
neighboring land uses; and
WHEREAS, Kittitas County's existing land use, zoning, development, environmental, building,
infrastructure, and permitting regulations do not adequately define, classify, review, condition, or
mitigate data center development or data center -related facilities; and
WHEREAS, the County has a legitimate and substantial public interest in evaluating whether
data centers should be specifically defined and regulated within the Kittitas County Code and
Comprehensive Plan, including review of zoning districts, conditional use requirements,
development standards, utility and infrastructure impacts, energy and water demand, emergency
access, fire protection, noise, lighting, screening, environmental review, transportation impacts,
and compatibility with surrounding rural, agricultural, commercial, industrial, and residential
uses; and
WHEREAS, Community Development Services has prepared a one-year Work Plan, attached
hereto as Exhibit A and incorporated by this reference, that provides for related studies,
stakeholder and public engagement, alternatives analysis, and the development of
Comprehensive Plan policies and development regulations addressing data centers; and
WHEREAS, the Work Plan is structured to address the findings supporting the original
moratorium and to produce legally sound, Growth Management Act -compliant legislative
proposals ready for Planning Commission recommendation and Board consideration before
expiration of the extended moratorium; and
WHEREAS, the Board finds that adoption of the Work Plan and extension of the moratorium
for a total period of up to one year from the original effective date is necessary and appropriate to
preserve the status quo, protect public health, safety, and welfare, and allow sufficient time for
the studies and public process contemplated by the Work Plan; and
WHEREAS, the Board finds that an emergency continues to exist because allowing data center
land use applications to be submitted, processed, or vested before completion of the County's
review could frustrate the purpose of future regulations and may result in impacts that the
County's existing code does not adequately address; and
WHEREAS, the Board desires to adopt the Work Plan as Exhibit A, extend the moratorium for
six months consistent with RCW 36.70A.390, and continue the public process set forth in the
Work Plan;
NOW, THEREFORE, BE IT RESOLVED by the Board of County Commissioners of Kittitas
County, Washington, as follows:
Section 1. Findings of Fact Adopted.
The Board adopts the recitals above as findings of fact in support of this Resolution. The Board
further adopts and reaffirms the findings of fact set forth in Resolution No. 2026-141 (the
original emergency moratorium resolution) and finds that the conditions giving rise to the
original emergency continue to exist. The Board additionally finds:
1. Data centers may have unique and significant land use, infrastructure, environmental, and
public service impacts that differ from other commercial, industrial, utility, warehouse, or
technology -related uses.
2. Potential impacts associated with data centers may include, but are not limited to,
electrical transmission and distribution demand; backup generator use and fuel storage;
water demand and wastewater impacts; cooling system impacts; noise from mechanical
and backup power equipment; exterior lighting and visual impacts; building scale,
massing, and screening; construction and operational traffic; fire protection and
emergency access; hazardous material or battery storage; stormwater, grading, and
impervious surface impacts; and impacts to agricultural, rural residential, commercial, or
industrial land use compatibility.
3. Kittitas County's current development regulations may not contain data center -specific
definitions, siting criteria, development standards, mitigation requirements, or permitting
procedures.
4. The one-year Work Plan attached as Exhibit A provides for the related studies necessary
to support an extended moratorium period under RCW 36.70A.390 and establishes a
clear path for public engagement, alternatives analysis, and development of
Comprehensive Plan policies and development regulations.
5. Immediate acceptance of land use applications for data centers may result in applications
vesting under existing regulations before the County completes its review.
6. Extension of the temporary moratorium is necessary to preserve the status quo and
protect the public health, safety, and welfare while the County evaluates appropriate
regulatory measures.
7. The moratorium as extended by this Resolution remains limited in scope to land use
applications for data centers and is limited in duration as set forth herein.
8. The attached work plan anticipates one year to complete the process. An additional public
hearing may be necessary after six months to ensure compliance with RCW 36.70A.390.
Section 2. Work Plan Adopted. The Work Plan for the Development of Regulations and
Comprehensive Plan Policies Associated with the Siting and Permitting of Data Centers in
Kittitas County, dated September 2026, attached hereto as Exhibit A, is hereby adopted.
Community Development Services is directed to implement the Work Plan, provide regular
progress updates to the Board and Planning Commission, and prepare legislative proposals
consistent with the Work Plan for consideration by the Planning Commission and BOCC.
Section 3. Moratorium Extended. The temporary emergency moratorium established by
Resolution No. 2026-141 on the acceptance, processing, review, and approval of any land use
application for the siting, establishment, construction, expansion, conversion, or operation of a
data center within unincorporated Kittitas County is hereby extended and shall remain in effect
for a total period of up six months from the effective date of this Resolution, unless earlier
repealed or further extended by the Board after a subsequent public hearing and findings of fact
as required by RCW 36.70A.390. The definition of "data center," the list of applications subject
to the moratorium, and all other operative provisions of the original moratorium resolution
remain in full force and effect during the extended period.
Section 4. Public Process. The Board directs Community Development Services to continue
implementation of the public engagement and formal public process elements of the Work Plan,
including Planning Commission and Board hearings on any proposed Comprehensive Plan or
development regulation amendments. At or following any subsequent public hearing on the
moratorium itself, the Board may adopt additional findings of fact, modify the moratorium,
continue the moratorium, or repeal the moratorium.
Section 5. Severability. If any section, sentence, clause, or phrase of this Resolution is held
invalid or unconstitutional by a court of competent jurisdiction, such invalidity or
unconstitutionality shall not affect the validity or constitutionality of any other section, sentence,
clause, or phrase.
Section 6. This Resolution shall take effect immediately upon adoption.
ADOPTED this 15 day of September 2026.
Attest:
❑ Clerk of the Board- Julie Kjorsvik
❑ Deputy Clerk of the Board- Mandy Buchholz
BOARD OF COUNTY COMMISSIONERS
KITTITAS COUNTY, WASHINGTON
Brett Wachsmith, Chairman
Laura Osiadacz, Vice -Chairman
Jeff Leichleiter, Commissioner
EXHIBIT A
WORK PLAN FOR THE DEVELOPMENT OF REGULATIONS AND
COMPREHNSIVE PLAN POLICIES ASSOCIATED WITH THE SITING AND
PERMITTING OF DATA CENTERS IN KITTITAS COUNTY
Kittitas County Community Development Services
September 2026
Purpose
This work plan guides Community Development Services (CDS), the Planning Commission, and
the Board of County Commissioners (BOCC) in evaluating whether and how data centers should
be defined, classified, sited, and regulated in the Kittitas County Comprehensive Plan and
development regulations.
This work plan is structured to directly address the findings in the emergency moratorium
resolution: data centers present unique, significant impacts (electrical demand, backup
generation/fuel storage, water/wastewater, cooling, noise, lighting/visual, scale/massing, traffic,
fire/emergency access, hazardous materials/batteries, stormwater/impervious surfaces, and
compatibility with agricultural, rural residential, commercial, and industrial uses) that existing
code may not adequately address.
Duration September 2026 — September 2027 (one year). The work plan may be updated by
Board direction. A subsequent public hearing and new findings would be required for any further
six-month renewal to complete the process in accordance with the work plan schedule.
Primary Objectives
1. Research data center impacts both to the natural environment and relevant community
impacts.
2. Evaluate and compare policies and regulations from other jurisdictions, especially those
jurisdictions within Washington State.
3. Conduct stakeholder and public engagement.
4. Produce legally sound, GMA-compliant legislative proposals ready for Planning
Commission and BOCC adoption before moratorium expiration.
Task 1: Research, Inventory & Baseline Analysis: September — December 2026
• Inventory existing Kittitas County Comprehensive Plan policies and development
regulations relevant to data centers, large industrial/utility uses, noise, lighting, critical
areas, shorelines, SEPA thresholds, and infrastructure concurrency.
• Compile and analyze regulations and outcomes from Grant, Skagit, Snohomish, Spokane,
, Douglas/Chelan, and other rural jurisdictions plus any relevant state or national model
ordinances.
• Identify potential suitable locations relative to existing zoning, agricultural lands of long-
term commercial significance, critical areas, transmission corridors, and water
availability.
• Engage Kittitas PUD, Puget Sound Energy (where overlapping), BPA, and water
purveyors on existing capacity, large -load policies, upgrade cost allocation, and
reliability impacts. Coordinate with Ecology (air quality/generators, water rights, SEPA)
and local fire districts.
• Identify data gaps (e.g., local noise baselines, water balance in drought years).
Milestone/Deliverable: Staff technical memo to Board and Planning Commission code
gaps, peer jurisdiction standards, and infrastructure constraints. (December 2026)
Task 2: Stakeholder Engagement & Public Outreach: October 2026 — April 2027
• Facilitate a series of focused meetings including CDS, Planning Commission members,
utility providers, agricultural organizations, environmental groups, emergency services,
economic -development interests, and industry representatives.
• Host public open houses or workshops and maintain a dedicated webpage with
frequently updated materials and participation information.
• Solicit written comments; brief BOCC and Planning Commission at regular intervals.
• Document input on priorities (e.g., ag protection, utility ratepayer impacts, rural
character, economic benefits).
Milestone/Deliverable: Public participation summary and key themes report to Board by
April 2027.
Task 3: Alternatives Analysis & Policy Framework: December 2026 — April 2027
• Develop and evaluate regulatory alternatives:
o Definition of "data center" (align with or refine the emergency -resolution
language to cover AI, cloud, crypto, high -density computing, and
associated infrastructure).
o Zoning treatment (permitted/conditional/prohibited by district; preference
for heavy industrial or specific overlays; strong limitations or prohibition
in Commercial Agriculture, Forest & Range, Rural Residential, etc.).
o Development standards: setbacks/buffers, building height/massing,
screening/fencing, noise, lighting, generator enclosures/fuel storage,
water -use and cooling -system requirements, stormwater/impervious limits,
traffic/construction management, fire/emergency access, hazardous
materialsibatteries, visual impacts.
o Process requirements: mandatory utility capacity letters, sound studies,
water -availability demonstration, SEPA, possible development agreements
or mitigation fees.
o Comprehensive Plan policy amendments (land -use, utilities, economic
development, rural/ag protection, climate/resiliency if relevant).
Assess fiscal/economic impacts (jobs, tax revenue after incentives, infrastructure costs
borne by ratepayers vs. applicant).
Milestone/Deliverable: Alternatives analysis memo with preferred framework
recommendation and staff report ready for Planning Commission review by April 2027.
Task 4: Draft Code & Comprehensive Plan Amendments: April — June 2027
• Prepare draft ordinance(s) amending Kittitas County Code (definitions, use tables,
performance standards, procedures) and any necessary Comprehensive Plan text/map
amendments.
• Integrate SEPA review and comment period.
• Internal review by legal.
• Planning Commission/BOCC Joint Study Session.
Milestone/Deliverable: Public -review draft code and plan amendments + SEPA
checklist/determination.
Task 5: Formal Public Process, Recommendation & Adoption: June — September 2027
Planning Commission work sessions and public hearing(s); recommendation to BOCC.
BOCC public hearing(s) and adoption of permanent regulations (or decision to
prohibit/restrict further).
If needed, prepare findings supporting any additional moratorium renewal while final
adoption occurs.
Milestone/Deliverable: Adopted ordinance(s) and any related plan amendments; updated
permitting procedures
Reporting & Accountability
CDS will provide brief progress updates to the BOCC and Planning Commission regularly and
as outlined in the work plan. The work plan itself, progress, and any recommended code changes
will be available for public review. Upon completion (or earlier if permanent regulations are
adopted), the moratorium can be allowed to expire or be formally repealed.
This Work Plan may be amended from time to time by Board direction to reflect new
information, resource availability, or evolving circumstances.
Workplan Table
Purpose: Provide a structured process to evaluate the impacts and appropriate development
criteria for data centers and similar uses, as will be determined through the adopted definition.
The work plan satisfies RCW 36.70A.390 requirements for extending the moratorium beyond six
months. The table below is an abridged version of the proposed workplan.
Duration: September 2026 — September 2027 (one year). Regular progress reports to the Board
of County Commissioners and Planning Commission as indicated in the workplan.
Task
1. Research,
Inventory & Baseline
Analysis
2. Stakeholder
Engagement &
Public Outreach
Timeframe
Months 1-3
Months 2-7 (concurrent
with Phases 1 & 3)
Description
Inventory existing
Comprehensive Plan policies and
development regulations
• Compile and analyze peer
regulations
• Identify potential locations
relative to zoning, agricultural
lands, critical areas, transmission
corridors, and water availability
• Engage stakeholders and experts
• Identify data gaps
• Facilitate a series of focused
meetings
• Host public open
house/workshop
• Maintain dedicated webpage
with materials, FAQs, and
comment form
• Solicit written comments and
brief BOCC/Planning
Commission regularly
• Document input on priorities
Primary Deliverables
Technical memo
summarizing code
gaps, peer standards,
and infrastructure
constraints
Public participation
summary and key
themes report
• Develop and evaluate
regulatory alternatives.
• Zoning treatment by
district.
Alternatives analysis
3. Alternatives
• Development standards.
memo with preferred
Analysis & Policy Months 4-7
• Process requirements.
framework
Framework
• Comprehensive Plan
recommendation
policy amendments.
• Assess fiscal/economic
impacts.
• Prepare draft ordinance(s)
amending Kittitas County Code.
public -review draft
4. Draft Code &
• Prepare any necessary
code and plan
Comprehensive Plan Months 7-9
Comprehensive Plan text/map
amendments + SEPA
Amendments
amendments
checklist/determination
• Conduct internal review
• Complete SEPA review
5. Formal Public
• Planning Commission work
sessions and public hearing(s);
Adopted ordinance(s)
Process, Months 9-12
formal recommendation to BOCC
and related plan
amendments; updated
Recommendation &
• BOCC public hearing(s) and
permitting procedures
Adoption
adoption of permanent regulations