Laserfiche WebLink
22 | Old Heat CERB Feasibility Study <br />TASK 4: PROJECT COSTS <br />a. Costs of architecture and <br />construction are necessary to <br />repurpose existing industrial <br />building to Class B commercial <br />space for innovation and <br />technology commercialization. <br />b. Costs of architecture and <br />construction are necessary to <br />repurpose existing industrial <br />buildings to business incubation <br />and meeting spaces. <br />A design for the Old Heat Welcome <br />Center with engineering was <br />performed in 2016 to be bid in three <br />phases. The table below shows the <br />history of the project and an updated <br />construction cost for what would have <br />been phase 3 of the project. The <br />design created for the Welcome Center <br />and Community Education Center <br />serves as a good platform to build on <br />for the current project being explored. <br />Variations to tenant improvements will <br />be made to meet the specific needs <br />of the new use in the future as those <br />are developed. The capital cost of the <br />project should be in the range of the <br />estimates that have been brought up to <br />2025 construction costs. <br />DIVISION ITEM 2018 BID 2025 ESCALATED COST <br />(45%) <br />2025 COST W/ <br />PREVAILING WAGE <br />(45%) <br />GCs Soft Costs (OH&P, Insurance, <br />Bonding, B&O tax)$1,134,596.00 $ 1,645,164.20 $ 1,891,938.83 <br />Existing Conditions (demo and <br />abatement)$ 237,190.00 $ 343,925.50 $ 395,514.33 <br />Earthwork $ 156,895.00 $ 227,497.75 $ 261,622.41 <br />Exterior Improvements $ 126,332.00 $ 183,181.40 $ 210,658.61 <br />Concrete $ 261,604.00 $ 379,325.80 $ 436,224.67 <br />Masonry $ 242,348.00 $ 351,404.60 $ 404,115.29 <br />Metals $ 645,514.00 $ 935,995.30 $ 1,076,394.60 <br />Wood and Plastic $ 74,603.00 $ 108,174.35 $ 124,400.50 <br />Thermal and Moisture Protection $ 230,053.00 $ 333,576.85 $ 383,613.38 <br />Doors and Windows $ 392,907.00 $ 569,715.15 $ 655,172.42 <br />Finishes $ 658,582.00 $ 954,943.90 $ 1,098,185.49 <br />Specialties $ 56,385.00 $ 81,758.25 $ 94,021.99 <br />Conveyance $ 199,500.00 $ 289,275.00 $ 332,666.25 <br />Fire Protection $ 82,050.00 $ 118,972.50 $ 136,818.38 <br />Plumbing and Mechanical $ 687,727.00 $ 997,204.15 $ 1,146,784.77 <br />Electrical $ 694,297.00 $ 1,006,730.65 $ 1,157,740.25 <br />Design Contingency $ 179,666.00 $ 260,515.70 $ 299,593.06 <br />TOTALS $5,880,583.00 $ 8,526,845.35 $ 9,805,872.15 <br />Table 1: Costs <br />TASK 04