There are architectural pieces of Old Heat that have been salvaged or retained in
<br /> the building during phases I and II of the construction projects. These pieces can
<br /> be used in the adaptive reuse of the building to bring the history and character of
<br /> the building to life when renovated with four overarching objectives that guide the
<br /> project's design, partnerships, and outcomes:
<br /> Division Item 2018 Bid 2025 Escalated Cost(45%) 2025 Cost w/Prevailing Wage(45%)
<br /> GCs Soft Costs (OH&P, Insurance, Bonding, B&O tax) $ 1,134,596.00 $ 1,645,164.20 $ 1,891,938.83
<br /> Existing Conditions (demo and abatement) $ 237,190.00 $ 343,925.50 $ 395,514.33
<br /> Earthwork $ 156,895.00 $ 227,497.75 $ 261,622.41
<br /> Exterior Improvements $ 126,332.00 $ 183,181.40 $ 210,658.61
<br /> Concrete $ 261,604.00 $ 379,325.80 $ 436,224.67
<br /> Masonry $ 242,348.00 $ 351,404.60 $ 404,115.29
<br /> Metals $ 645,514.00 $ 935,995.30 $ 1,076,394.60
<br /> Wood and Plastic $ 74,603.00 $ 108,174.35 $ 124,400.S0
<br /> Thermal and Moisture Protection $ 230,053.00 $ 333,576.85 $ 383,613.38
<br /> Doors and Windows $ 392,907.00 $ 569,715.15 $ 655,172.42
<br /> Finishes $ 658,582.00 $ 954,943.90 $ 1,098,185.49
<br /> Specialties $ 56,385.00 $ 81,758.25 $ 94,021.99
<br /> Conveyance $ 199,500.00 $ 289,275.00 $ 332,666.25
<br /> Fire Protection $ 82,050.00 $ 118,972.50 $ 136,818.38
<br /> Plumbing and Mechanical $ 687,727.00 $ 997,204.15 $ 1,146,784.77
<br /> Electrical $ 694,297.00 $ 1,006,730.65 $ 1,157,740.25
<br /> Design Contingency $ 179,666.00 $ 260,515.70 $ 299,593.06
<br /> TOTALS $ 5,880,583.00 $ 8,526,845.35 $ 9,805,872.15
<br /> Table 2:Build Detail
<br /> Old Heat CERB Feasibility Study 125
<br />
|