documents, or any part thereof, to conform with any other part of the documents, any of which <br />failure shall be corrected by ESCO. <br />SECTION 9. CONSTRUCTION SCHEDULE AND EQUIPMENT <br />INSTALLATION; APPROVAL <br />Section 9.1. Construction Schedule. Construction and equipment installation shall <br />proceed in accordance with the construction schedule approved by the Owner and attached hereto <br />as Schedule F (Construction and Installation Schedule). <br />Section 9.2. Systems Startup and Equipment Commissioning. ESCO shall conduct a <br />thorough and systematic performance test of the installed Equipment in accordance with the <br />procedures to be provided during the construction period as noted in Schedule G (Systems Start - <br />Up and Commissioning) and prior to final acceptance by the Owner. ESCO shall be responsible <br />for correcting and/or adjusting all deficiencies in systems and Equipment operations in a timely <br />manner during system commissioning procedures. <br />Section 9.3. Inspection and Final Approval. The Owner has the right to inspect, test and <br />approve the work conducted in the Premises during construction and operation. The Owner shall <br />have the right to review and access to the account books, records, and other compilations of data <br />that pertain to the performance of the provisions and requirements of this Contract. Records shall <br />be kept on a generally recognized accounting basis, and calculations will be kept on file in legible <br />form and retained for three (3) years after the expiration of the term of this Contract and any <br />renewals relevant thereto. <br />SECTION 10. STANDARDS OF COMFORT <br />The standards set forth in Schedule H (Standards of Comfort) are guidelines used to <br />evaluate the FIMs in this program. It is understood that existing and installed equipment may not <br />allow for exact times and temperatures to be met, but every effort will be made to meet such <br />standards as the Guaranteed Maximum Implementation Cost, equipment and project design allow. <br />The Owner also retains the right to make further control and schedule adjustments beyond the <br />standards listed in Schedule H, only in an effort to provide further energy savings. In the case <br />where this produces a Material Change per section 15, the Owner will inform the ESCO in writing <br />of the specific changes and/or adjustments, wherein the ESCO will adjust the baseline and Energy <br />Savings Guarantee, as necessary. All costs associated with the changes and/or adjustments are the <br />sole responsibility of the Owner. <br />SECTION 11. WARRANTIES AND COMPATIBILITY <br />Manufacturer's Warranties: ESCO covenants and agrees that the Equipment, installed <br />pursuant to this Contract is or will be new, in good and proper working condition, and covered by <br />applicable manufacturers' warranties covering all parts and equipment performance. <br />Demonstrators, previously rented, refurbished, or reconditioned items are not considered "new" <br />except as specifically provided in this section. "New" means items that have not been used <br />previously and that are being actively marketed by the manufacturer. Equipment may contain new <br />or minimal amounts of recycled or recovered parts that have been reprocessed to meet the <br />manufacturer's new product standards. Equipment must have the Owner as its first customer and <br />ESCO (McKinstry)/OWNER/PERFORMANCE CONTRACT 10 <br />