Vantage to Pomona Heights Chapter 4 <br />230 kV Transmission Line Project FEIS Environmental Consequences <br /> PAGE 4-203 <br />contrasts would remain strong/moderate to moderate, visual impacts would not substantially differ should <br />the route segment utilize JBLM YTC access roads. <br />Scenic Quality Impacts and Development Character <br />Scenic quality impacts would be moderate to low in the undeveloped Class C landscape that is similar to <br />the other routes located in the undeveloped Yakima Ridge area. <br />Sensitive Viewer Impacts <br />Sensitive viewers, which include residences and State Route (SR) 24 travelers (see Appendix C-3: KOP <br />4) would view moderate to strong Project contrasts in the background or seldom seen distance zone <br />except on the far western end of the route segment, where high impacts on residences located at the east <br />end of Postma Road and Deeringhoff Road would occur for a short distance. The implementation of <br />mitigation measure VIS-2 between MP 0.0 and MP 0.4 would reduce the contrast created by the <br />conductor wires and reduce high impacts to moderate and moderate impacts to low. Moderate impacts <br />created as a result of strong or moderate/strong impacts seen in the background from residential viewers <br />and SR-24 motorists would also occur from MP 11.5 to the east end of the route. Implementation of <br />mitigation measure VIS-2 (non-specular conductors) would reduce these impacts to a low level. <br />Agency Management Compliance <br />BLM Interim VRM Class III lands are crossed at MP 4.0-4.2 and MP 12.4-12.9. Project contrasts would <br />be strong because of structures contrasts and access road construction in 0 to 15 percent slope areas with <br />Group 3 vegetation cover. The route segment would be compliant with the Interim Class III from <br />residences north of SR-24, the nearest viewpoint, because strong to strong-moderate contrasts are seen in <br />the background or seldom-seen distance zone. The route segment is in the seldom seen and background <br />distance zone from the nearest KOP (KOP 4) causing low impacts. <br />The route segment would also comply with the visual standards identified in the Yakima County <br />Comprehensive Plan. <br />4.8.5.6 Route Segment 2c <br />Visual Contrasts <br />Structure contrasts for Route Segment 2c would vary depending on whether or not the route segment is <br />paralleling the Union Gap-Midway 230 kV and Midway-Moxee 115 kV corridor or not and which <br />structure type (single pole or H-frame) is proposed. Where the route segment parallels the existing <br />transmission line corridor, structure contrasts would be either moderate/weak or weak (see Table 4.8-2 <br />Structure Contrast: Configuration 4 or 5). This route segment crosses grassland/herbaceous vegetation <br />and the clearing and grading associated with access road construction, work pad installation, and other <br />construction activities would cause moderate to weak landscape contrasts. <br />Scenic Quality Impacts and Development Character <br />Scenic quality impacts would be moderate to low in the undeveloped Class C landscape that is similar to <br />the other route segments located in the undeveloped Yakima Ridge area. As the route segment enters the <br />Moxee Valley Agricultural Development Character Area (as described in Section 3.8.2.3), it would also <br />follow the existing Union Gap-Midway 230 kV and Midway-Moxee 115 kV transmission line corridor. <br />The route segment would be compatible with the existing character as it parallels these existing <br />transmission lines. <br />Sensitive Viewer Impacts <br />Moderate impacts would occur on residences located north of SR-24 in the Moxee Valley viewing <br />moderate Project contrasts in the immediate foreground for a short distance (0.4 mile). Background views