Laserfiche WebLink
Vantage to Pomona Heights Chapter 4 <br />230 kV Transmission Line Project FEIS Environmental Consequences <br /> PAGE 4-177 <br />Access Levels for Route Segment NNR-2 are assumed as Levels 2 and 3 for most of the route and would <br />require the construction of approximately 3.5 miles of spur roads and approximately 5.8 miles of access <br />roads for a total of 9.4 miles of new roads. Moderate to low impacts would result from the construction of <br />Route Segment NNR-3. <br />4.7.4.13 Route Segment NNR-4o/4u <br />Overhead Design Option <br />This route segment would be accessed from Exit 11 through an existing gate adjacent to the stockpile area <br />on the southwest side of the I-82 or from the JBLM YTC Exit 11 access gate. Use of Exist 11 will require <br />FHWA and WSDOT approval. Existing roads on JBLM YTC or private land would be used and <br />improved as necessary (Access Level 2 or 3, typically), including those that follow Pacific Power’s <br />existing Pomona-Wanapum 230 kV transmission line. This route segment would cross I-82 and the JBLM <br />YTC secondary access road servicing the I-82 Exit 11 (Figure 4.7-3). <br />NNR-4o would cross I-82 approximately 200 feet north of Pacific Power’s existing Pomona-Wanapum <br />230 kV transmission line which is one mile south of Exit 11. This crossing would involve the placement <br />of one transmission structure on western side of the interstate on private property. The other structure <br />would be placed on the eastern side of the interstate on the JBLM YTC. No structures would be placed <br />within the interstate ROW corridor. The approximate length on this crossing would be 1,000 feet and <br />would utilize H-frame structures. Conductor to ground clearance of this crossing would be a minimum of <br />34 feet. A permanent access break, authorizing the use of Exit 11, would be required if access is <br />necessary from I-82. A permanent access break, authorizing the use of Exit 11, would be required for <br />maintenance purposes and a temporary access break would be required for construction. Temporary road <br />closure of I-82 during conductor stringing activities would occur to maintain safety. Other impacts on I- <br />82 traffic are discussed in Section 4.7.3 (Impacts Common to All Alternatives) and would be low. <br />Access Levels for Route Segment NNR-4o are assumed as Level 2 and 3 for most of the route segment as <br />it follows Pacific Power’s existing Pomona-Wanapum 230 kV transmission line. This route segment <br />would require the construction of approximately 1.8 miles of spur roads and approximately 1.0 mile of <br />access roads for a total of 2.8 miles of new roads. Low to moderate impacts would result from the <br />construction of Route Segment NNR-4o. <br />Underground Design Option <br />The alignment of the Underground Design Option (NNR-4u) would be similar to what is shown in Figure <br />2-6, with the transmission line overhead to underground transition stations located on the west and east <br />sides of the 1,000 foot overhead crossing of I-82 on private and JBLM YTC land. Impacts on <br />transportation would be similar in terms of access (from I-82 Exit 11 and JBLM YTC) and the crossing of <br />I-82. However, construction across JBLM YTC would cause the closure of the secondary access road <br />servicing Exit 11 for a short term during trenching and duct bank construction in this area. Other impacts <br />on I-82 traffic are discussed in Section 4.7.3 (Impacts Common to All Alternatives) and would be low. In <br />this area, extensive road construction in the bivouac area of Training Area 16 would allow for the <br />rerouting of traffic within the training center. RDFs would reduce traffic impacts to the JBLM YTC road. <br />Low to moderate impacts would result from the construction of Route Segment NNR-4u. <br />4.7.4.14 Route Segment NNR-5 <br />Route Segment NNR-5 crosses the southern portion of Badger Pocket within JBLM YTC, generally <br />paralleling the fire break road. Access would be provided from the perimeter road and from within JBLM <br />YTC. This road would be minimally affected during the construction of the route segment. Route <br />Segment NNR-5 would require the construction of approximately 0.7 mile of spur road and 0.1 mile of