Laserfiche WebLink
SECTION 6 – FINAL RECOMMENDATION AND NEXT STEPS <br />6-2 AX0622181133PDX <br />− Rights-of-way and easements – for site and road access may be tied to the site acquisition <br />process <br />• Public meetings – as required by any permitting processes <br />• Other special meetings – as needed between municipal entities or agencies <br />The overall permitting schedule is highly dependent on the results of the preapplication meetings and <br />the SEPA Determination of Significance. As described earlier, the final design will incorporate the <br />provisions and mitigation measures of the permits. Permitting is not formally complete until the <br />construction phase is complete because there are often requirements for monitoring or building activity <br />reports and inspections. <br />