HomeMy WebLinkAbout09.28.2026 PW SS Briefing KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS—BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 28, 2026
TOPIC: Request to Approve a Resolution Accepting
Washington State Department of Transportation
Aviation Division grant GCC 1495 Supporting
the Bowers Field Hangar Taxilane Complex
Project
ACTION REQUESTED: Approve a Resolution
LEAD STAFF:
Josh Fredrickson
RECOMMENDATION:
Approve a resolution authorizing the Public Works Director signature on the WSDOT
Aviation Division grant agreement GCC 1495 accepting the grant funding.
BRIEFING SUMMARY:
• The Federal Aviation Administration(FAA)provided a grant to support the
construction of the Hangar Taxilane Complex Project
• FAA grant requires a local match
• An Airport Aid application was submitted to the Washington State Department of
Transportation Aviation Division for Bowers Field improvements
• WSDOT Aviation Division has noticed Kittitas County of an award, and provided
an associated Grant Agreement
BACKGROUND:
An Airport Layout Plan(ALP) for Bowers Field was approved in 2018 by Resolution
2018-136. The ALP identifies existing facilities and future facilities at Bowers
Field. One of the future facilities identified on the ALP is the development of a
Hangar Taxilane Complex area located on current vacant lots H-3 and H-4. This
Taxilane project will allow for additional hangar space to be constructed and
associated access to the active runway.
DISCUSSION:
The Federal Aviation Administration previously provided funds for the design of the
hangar taxilane complex. The FAA provided funding through grant number 3-53-0026-
025-2026.
The FAA grant is for$830,625.00 to support construction. A local match of 5% is
required. Funds are currently budgeted in the Airport Fund.
Washington Department of Transportation Aviation Division has noticed Public Works
of available funds to support the hangar taxilane complex project through Grant
Agreement No. GCC 1495. The maximum amount of the State grant is $23,750.00. This
funding helps to offset a portion of the local match required for Federal Funding on this
project.
FISCAL IMPACT:
Grant funding reduces the local match required for the project
ATTACHMENTS:
1. Resolution
2. Grant Offer Letter
BOARD OF COUNTY COMMISSIONERS
COUNTY OF KITTITAS
STATE OF WASHINGTON
RESOLUTION NO.2026-
RESOLUTION ACCEPTING WASHINGTON STATE DEPARTMENT OF
TRANSPORTATION AVIATION DIVISION GRANT FUNDING FOR
CONSTRUTCION OF THE BOWERS FIELD HANGAR TAXILANE COMPLEX
PROJECT AND AUTHORIZE THE PUBILC WORKS DIRECTOR TO
EXECUTE THE SAME
WHEREAS: The Federal Aviation Administration(FAA) authorized grant funding for the
Hangar Taxilane Complex project at Bowers Field; and
WHEREAS: Funding for the construction phase includes a 5 percent match required with the
federal grant funds; and
WHEREAS: An aid application was submitted to Washington state Department of
Transportation(WSDOT)Aviation Division to support this project; and
WHEREAS: WSDOT has noticed Public Works of grant award through Grant Agreement No.
GCC 1495 with a maximum amount of$23,750.00; and
WHEREAS: The state funding reduces the County's match obligation from the Airport Fund.
NOW,THEREFORE BE IT RESOLVED the Board of County Commissioners, after due
consideration, does hereby accept Washington State Department of
Transportation Aviation Division funding for the construction phase of the
hangar taxilane complex project; and
NOW,BE IT FURTHER RESOLVED the Board of County Commissioners does authorize the
Director of Public Works to execute the documents necessary to accept and
utilize the grant funds.
DATED on this 28th day of September 2026,at Ellensburg,Washington.
BOARD OF COUNTY
COMMISSIONERS
KITTITAS COUNTY,WASHINGTON
Brett Wachsmith, Chairman
Attest:
❑ Clerk of the Board-Julie Kjorsvik
Laura Osiadacz,Vice-Chairman
❑ Deputy Clerk of the Board-Mandy Buchholz
Jeff Leichleiter, Commissioner
GCC 1495
.M,
Washington State
vV Department of Thansportation
Public Entity and Address
Grant Agreement Kittitas county
4ll North Ruby Street, Suite #1
Washington Airport Aid Program
Ellensburg, Washington 98926
Airport Name
Bowers Field
Maximum State Grant Obligatic
$ $23,750.00
THIS AGREEMENT, made and entered into this day of September 2026 between the STATE
OF WASHINGTON, acting by and through the Aviation Division, Department of Transportation, (hereinafter the"STATE")and the
above named Public Entity, (hereinafter the"PUBLIC ENTITY").
WHEREAS,the Public Entity has submitted to the State for Subvention of the Washington Airport Aid Program for
(acquisition and/or development)of the Bowers Field Airport together with the plans and
specifications for such project, which project application has been approved by the State and is hereby incorporated
herein and made a part hereof;
WHEREAS,the State has approved a project for development of the airport consisting of the following described airport
development:
Project Number Detailed Breakdown By ItemE
ELL-01-26 $23,750.00 - Hangar Taxilane Complex Construction,including eligible items as
GCC 1495 of May 15th, 2026.
NOW, THEREFORE, pursuant to and for the purpose of carrying out the provisions of the State Act, and in consideration of
the(a) Public Entity's adoption and ratification of the representations and assurances contained in said project application,
and its acceptance of this offer as hereinafter provided, and (b)the benefits to accrue to the State of Washington and the
public from the accomplishment of the project and the operation and maintenance of the airport as herein provided, the State
hereby agrees to pay as its allowable costs incurred in accomplishing the project.
The terms and conditions of this grant agreement are as follows:
The maximum obligation of the State payable under this grant shall be 23,750
The Public Entity shall:
1. Deposit in an Aviation Fund for said airport, at least$ 23,750 to match the State's participation in
said project.
2. Carry out and complete the project in accordance with the plans and specifications and property map, incorporated
herein, as they may be revised or modified with the approval of the state.
3. In connection with the acquisition of real property for the project,the Public Entity shall secure at least two written
appraisals by competent, experienced appraisers who are members of a recognized professional appraisal organization
and shall not pay in excess of the highest appraisal without the written consent of the state except as otherwise directed
by a court of competent jurisdiction after contested trial and judgment not resulting from an agreement between the
parties.
DOT Form 900-078 EF
Revised 5/98 Page 1 of 3
GCC 1495
4. No state funds will be paid to the Public Entity in any case until it certifies in writing that it has Aviation Funds for
said airport in an amount equal to the state's participation, or the amount designated in paragraph (1)above,which
deposited amount will be used solely for the purpose in question.
5. The Public Entity agrees to hold said airport open to the flying public during the useful life of the facilities
developed under this project; that no exclusive operating or use agreements shall be granted to any person, company,
or corporation;that failure to abide by such agreement shall automatically obligate the immediate and full return of all
State of Washington money expended in behalf of the project to the State of Washington with reasonable interest.
Further,the Public Entity agrees to keep the facility open during the useful life of the project or for a stated term of
years,whichever is longer, as determined by the Aviation Division.
6. The Public Entity will make no charge to the State or its agencies for a limited, but reasonable, amount of state
agency use or for state activity in search and rescue. And,further, RCW 47.68 is followed to best serve the public.
The allowable cost of the project shall not include any cost determined by the State to be ineligible for consideration as to
allowability.
The State reserves the right to amend or withdraw this offer at any time prior to its acceptance by the Public Entity.
This offer shall expire and the State shall not be obligated to pay any part of the costs of the project unless this agreement
has been accepted by the Public Entity on such subsequent date as are prescribed in writing by the State, in the approval
letter for each project.
Except for those projects receiving both state and federal aid,the following inspection scheduled, and reporting system will be
required:
A. Inspection Schedule and Reporting system will vary for each project. Basically,the inspection schedule will be
placed on a quarterly basis. On project taking less than three(3)months,the Public Entity will be required to make
reports and be inspected on the following schedule:
1. Public Entity project commencement date.
2. Public Entity report project completion date and request final inspection.
3. State will make final inspection and sign-off project as completed.
4. State will arrange for audit of account in accordance with regularly scheduled audit program.
B. Projects taking over three(3)months will be set up on a quarterly inspection and progress report system. The
Public Entity will be required to make reports and be inspected on the following schedule:
1. Report project commencement date.
2. Public Entity will make a three(3)months progress report. This will be a letter report giving percentage of
project completed, fund expenditures to date, and short narrative of the project progress, problems encountered
and plans for project completion.
3. State will make quarterly project inspections and prepare the report of inspection. A copy of the report will
be delivered to the Public Entity.
4. Public Entity will make report of completion of project and request final inspection.
5. State will make final inspection and sign-off as completed.
6. State will arrange for audit of account in accordance with regularly scheduled audit program.
It should be made clear that a violation of any of the terms of the Grant Agreement will leave the State free to choose among
one or more of the following remedies:
A. The withholding of any future airport aid, and/or
B. The return of grant funds awarded as an action for specific performance, and/or
C. Enforcement of the commitment made by the applicant.
Page 2 of 3
GCC 1495
The Public Entity's acceptance of this offer and ratification and adoption of the project application incorporated herein shall be
evidenced by execution of this instrument by the Public Entity, as hereafter provided, and said offer and acceptance shall
comprise allocation agreement, constituting the obligation and rights of the State and the Public Entity with respect to the
accomplishment of the project and the operation and maintenance of the airport. Such allocation agreement shall become
effective upon the Public Entity's acceptance of this offer and shall remain in full force and effect throughout the useful life of
the facilities developed under the project but in any event not to exceed twenty(20)years from the date of acceptance.
By:
Deputy Director,Aviation Division
The Kittitas County does hereby ratify and adopt all statements,
representations,warranties, covenants, and agreements contained in the project application and incorporated materials
referred to in the foregoing offer and does hereby accept said offer and by such acceptance agrees to all of the terms and
conditions thereof.
Executed this day of September 2026
Name of Public Entity: Kittitas County
By:
Title: Public Works Director
DOT Form 900-078 EF Page 3 of 3
Revised 5/98 g
KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS—BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: September 28, 2026
TOPIC: Gladmar Reach Flood Impacts
ACTION REQUESTED: Direction to Staff
LEAD STAFF: Arden Thomas
RECOMMENDATION: Direct staff to conduct initial technical evaluation
and scoping potential partnerships to inform next
steps
BRIEFING SUMMARY:
• The Cascade Irrigation District recently notified Public Works that Yakima River
channel changes associated with the December 2025 flooding are affecting its
ability to divert irrigation water. The flooding also caused erosion along the
Washington State Parks Palouse to Cascade Trail.
• The historical record indicates that infrastructure within this area is vulnerable to
flooding, channel migration, and erosion.
• Additional work is needed to identify potential remedies, evaluate permitting
considerations, and estimate the costs of potential improvements.
• Given the history of channel changes and flood impacts in this area, flood control
measures may not deliver permanent solutions.
BACKGROUND:
The Cascade Irrigation District recently notified Public Works that channel changes
resulting from the December 2025 flooding are affecting its ability to divert irrigation
water. The altered channel became problematic later in the irrigation season when
Reclamation implemented its annual "flip-flop" operation, which substantially decreases
Upper Yakima River flows. Drone footage obtained by the Kittitas County Conservation
District has also identified significant erosion along the Washington State Parks Palouse
to Cascade ("PTC") Trail. Kittitas County Public Works has contacted State Parks and
has reached out to the Washington State Department of Transportation because I-90 is
adjacent to the PTC Trail.
These flood impacts occurred within the Gladmar Reach of the Yakima River, in the
vicinity of the former Gladmar gravel pit and Kittitas County park. Research indicates a
history of significant channel changes and flood impacts in this area. In 1964, the
Packwood diversion dam, which supplies water to Packwood Ditch, was breached. In
1996, flooding destroyed Gladmar Park, a County-owned facility, and the section of
Page I of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
Gladmar Road used to access the park. In response to the 1996 flooding, the County
constructed the Gladmar Park—Spur Dike and Gladmar Park levees in 1997.
The County Park was not re-established following the 1996 flooding. In 2004, the County
declared its intent to vacate any interest in the historic roads located in Gladmar Park and
the undeveloped Wade Road, including associated flood control structures.
The Gladmar Park levee was breached following the 2009 flooding, and Kittitas County
subsequently prepared the Yakima River at Gladmar Park Alternatives Assessment
Report in 2012. The record contains no formal Board decision following preparation of
the report, and none of the alternatives identified in the report have proceeded to
construction.
DISCUSSION:
Initial reports and reconnaissance indicate that the primary current flood impact is to
Cascade Irrigation District's ability to deliver water during September and October. In
addition, a significant amount of bank material has eroded along the PTC Trail, leaving
the trail vulnerable to additional erosion.
Because Kittitas County vacated the historical roads in the area and is no longer
managing its ownership for park use, there are currently no County assets at risk.
The Flood Control Zone District was established to address flood management needs
within the County. Public Works staff recommends proceeding at this time by updating
the technical evaluation, researching permitting considerations, and engaging with
entities with impacted infrastructure to discuss potential partnerships. This initial effort
would inform next steps and help define the appropriate scope of the County's response.
As a long-term consideration, given the history of channel migration, flooding, and
erosion in this area, flood control measures may not deliver a permanent solution.
FISCAL IMPACTS:
This work is not currently included in the 2026 Flood Control Zone District budget.
There is sufficient fund balance to conduct an initial technical evaluation and scoping
efforts. Project implementation would have more significant budget implications that
would need to be evaluated once potential project costs are known. Public Works will
also work to identify potential cost-share and partnership opportunities.
ATTACHMENTS:
Exhibit 1: Vicinity Map.
Exhibit 2: Flood Impact Photographs
Page 2 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
EXHIBIT 1: VICINITY MAP
Page 3 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
-' •'
0
s
M 59 f
e
Ak
Pa/o lse to Cdsca
des State Park
ti.
ZPI
Bowers F,eld
Rotary
:.,
I
EXHIBIT 2: FLOOD IMPACT PHOTOGRAPHS
PHOTO 1: CASCADE IRRIGATION DISTRICT HEADGATE
j :
b
PHOTO 2: BANK EROSION ALONG PALOUSE TO CASCADE TRAIL
� F N
r,
A �
~` ,• A"!
Page 4 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT