HomeMy WebLinkAbout2025-11-10-pw-study-session-supporting-documents KITTITAS COUNTY
DEPARTMENT OF PUBLIC WORKS
PUBLIC WORKS—BOARD OF COUNTY COMMISSIONERS
STUDY SESSION STAFF REPORT
STUDY SESSION DATE: November 10,2025
TOPIC: Extension Letter RE: FEMA flood map revisions
ACTION REQUESTED: Finalize comment letter and invite City of
Kittitas to sign
LEAD STAFF:
Arden Thomas
RECOMMENDATION:
Finalize extension letter regarding FEMA flood map revisions and invite the City of
Kittitas to sign the comment letter.
BRIEFING SUMMARY:
• At the March 25, 2024 Public Works Study Session,the Board of County
Commissioners (BOCC) directed staff to remain engaged in the Federal
Emergency Management Agency's (FEMA) ongoing efforts to improve flood risk
modeling and mapping, and to provide periodic updates regarding the status of
this initiative.
• The FEMA study area includes land located just east of Cle Elum and several
streams on the eastern side of the Kittitas Valley—areas where County staff have
concerns that current FEMA mapping does not adequately assess flood risk.
• Draft maps have been shared with the County, and we were informed that
comments on the draft maps may be submitted until November 24, 2025.
■ Proposed mapping in the Kittitas Valley area significantly expands the mapped
floodplain area.
• Kittitas County staff recommend a more in-depth technical review of the
modeling and mapping work conducted in the Kittitas Valley study area and
propose to utilize our on-call Hydraulic and Hydrologic (H&H) contractor to
conduct this review.
• Our H&H contractor has not yet been able to complete the review because the
necessary technical documents have not been provided.
• Staff recommend that the BOCC submit a formal comment letter requesting an
extension of the review period, as FEMA has not provided the requested technical
information.
Page 1 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
BACKGROUND:
Many of the mapped floodplains within Kittitas County were assessed for flood risk in
the late 1970s using approximate mapping techniques. In 2024, FEMA proposed new
flood studies for several streams on the east side of the Kittitas Valley, including within
the City of Kittitas, and for an area east of Cle Elum. These studies will ultimately update
the regulatory maps.
FEMA conducted surveys in 2024 and recently shared draft versions of the proposed
regulatory maps. On October 23, 2025, FEMA's mapping partner, STAR II, hosted a
Flood Risk Review meeting to present the modeling work and mapping outcomes.
During this meeting, we were informed that comments on the draft maps are due by
November 24, 2025.
DISCUSSION:
During and following the October 23, 2025, Flood Risk Review meeting, County staff
requested two technical reports and the associated hydraulic model to support a
comprehensive technical review of FEMA's work. To date,these materials have not been
received. It appears that FEMA's lack of response may be related to the ongoing federal
government shutdown.
Given the absence of the required technical information, staff recommend that the BOCC
formally request an extension of the public comment period to ensure adequate time for
technical evaluation once the data have been provided. Given the magnitude of the
changes between the current effective maps and the proposed draft maps in the Kittitas
Valley area, allowing adequate time for local review is essential to ensuring confidence in
the final outcomes of this process.
FISCAL IMPACTS:
Staff time and consultant costs associated with the technical review will be funded
through existing Flood Control Zone District resources. No budget amendment is
anticipated to be necessary at this time.
ATTACHMENTS:
Exhibit 1: Draft Extension Letter
Exhibit 2: Example maps illustrating changes between existing and proposed mapping in
the Cle Elum and City of Kittitas vicinities.
Page 2 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
EXHIBIT 1: Draft Extension Letter
Page 3 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
.pES..rp r,y Kittitas County, Washington
pS�t• L
BOARD OF COUNTY COMMISSIONERS
District One District Two District Three
;tTY Cory Wright Laura Osiadacz Brett Wachsmith
November 10,2025
Wendy L. Shaw, P.E.
Risk Analysis Branch Chief
Mitigation Division
FEMA Region 10
RE: Extension Request for Flood Risk Review Comment Period
Dear Ms. Shaw,
On Thursday,October 23,2025, Kittitas County staff met with representatives from FEMA's
mapping partner, STAR I1,for a Flood Risk Review(FRR) meeting. During this meeting,the STAR
11 team presented the results of newly restudied areas outside the City of Cie Elum and multiple
creeks within the Kittitas Valley area,encompassing both unincorporated Kittitas County and the
City of Cie Kittitas.
At the FRR meeting, we were informed that comments from local jurisdictions on the presented
materials are due by November 24,2025. To date,we have not received formal written notification
regarding this comment period. During the meeting,and subsequently by email, Kittitas County
requested additional technical documentation to facilitate our review and preparation of comments.
Specifically,we requested two technical reports and the hydraulic model associated with the Kittitas
Valley study area. We have not received the requested materials.This lack of response appears to be
associated with the ongoing federal government shutdown.
Given that the requested documentation has not been made available and is necessary to conduct a
complete and technically sound review,Kittitas County respectfully requests an extension of the
comment period to at least thirty(30)days following receipt of the requested materials.
Kittitas County and the City of Kittitas support FEMA's stated objective of developing useful,
credible data through a fair and transparent process that enables informed decision-making regarding
flood risk in our communities. Your correspondence dated March 13,2024, regarding this study
effort, emphasized FEMA's reliance on local "feedback,partnership,and knowledge."Consistent
with that principle,our preliminary review of the materials presented indicates that the Kittitas
Valley Creek study should include a model run utilizing unsteady modeling techniques, in addition to
the quasi-unsteady model employed. We further recommend that predicted flooding extents be
compared with observed flood extents from past events to ensure the study's validity.
We also request the opportunity to review model outputs in addition to the mapped flood hazard
areas presented.Regarding the restudied area in the vicinity of Cle Elum,we specifically request that
the"Zone A" Special Flood Hazard Area located north of Airport Road be updated through a
Floodplain Refinement process to more accurately align with existing topography. This requested
revision is on FIRM Panel 53037C0685D,which is subject to revision under the new study. For all
Kittitas County Courthouse 205 West 51Avenue,STE 108 -Ellensburg,WA 98926
(509)962-7508 FAX(509)962-7679
tvww co,klttdas waus
restudied areas,we additionally request that any Letters of Map Revision(LOMRs) be revalidated.
While these comments represent our preliminary feedback,we emphasize the importance of being
afforded sufficient opportunity,prior to the initiation of the appeal period,to conduct a
comprehensive technical review upon receipt of the requested documentation. We anticipate that we
may have additional or more refined comments after conducting a more detailed technical review.
Given the magnitude of the changes between the current effective maps and the proposed draft maps,
allowing adequate time for local review is essential to ensuring confidence in the final outcomes of
this process.
Respectfully,
KITTITAS COUNTY CITY OF KITTITAS
By: �' By:
Ms..tau s da Mr. Richard Hink
Cha.i-r.Kittitas County Board of Commissioners Mayor
Kittitas County Courthouse 205 West 5$Avenue,STE 108 Ellensburg,WA 98926
(509)962-7508 FAX(509)962-7679
www co kittitas.waus
EXHIBIT 2: Example maps illustrating changes between existing and proposed mapping
in the Cle Elum and City of Kittitas vicinities.
Page 4 of 4
PUBLIC WORKS BOARD OF COUNTY COMMISSIONERS WORK SESSION STAFF REPORT
r
Changes Since Last FIRM(as of August 28 2025)
sru
Flood Risk Classification
Change.Removed from Area of High
Flood Risk(1%Annual Chance).
No Change.Remains Arca of High Flood �' 1
Risk(1%Annual Chartcey I i
rV
Change.Added to Area of High Flood Risk
(1%Annual Chance).
No Change.Remains outside Area of High t
Flood Risk(1%Annual Chance).
Figure 1: Map changes within the Cle Elum vicinity..
t�
Gomm 1i3�7 - �Wfif �pf[3n
Changes Since Last FIRM(as of August 28 2025) } �
Flood Risk Classification
Change.Removed from Area of High
Flood Risk(1%Annual Chance)-
No Change.Remains Area of High Flood
Risk(1%Annual Chance)
Change.Added to Area of High Flood Risk
Ik (1%Annual Chanco).
No Change.Remains outside Area of High
Flood Risk(1%Annual Chance).
Figure 2: Map changes within the City of Kittitas vicinity.
KITTITAS COUNTY COMMISSIONERS
Public Works Study Session
Regular Meeting
Monday November 10, 2025 - 1 :30 PM
BoCC Auditorium
205 West 5th Room 109-Ellensburg
1.Call to Order
2.Citizen Comments (1 min.time limit)
3. Extension Letter RE: FEMA flood map revisions
4.Other Business-No Action to be taken
S.Concluded
Created on 11/6/2025 10:30:59 AM